Casos prácticos / Calidad y seguridad
Calidad y seguridad

Firma el acta de trabajos ocultos (akt skrytykh rabot) antes de cubrir la obra

Enumere lo que va a ocultar la siguiente operación, avise a las partes, documente los materiales, hágalo inspeccionar, haga firmar el acta a todos los que deben firmarla, y deje fuera de la recepción del mes cualquier partida sin su acta.

7 pasos13 minContratista generalSubcontratista especialistaPromotor / cliente

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

List what will be hidden and who has to attend

Gestión de calidad

Go through the coming section and put every operation whose result the next one will cover on the inspection and test plan as a hold point: reinforcement before the pour, waterproofing before the screed, bedding and buried services before backfill. Against each, set the signatories the act needs, the client's technical supervision and the designer where author supervision is required, the notice period you owe them, and the predecessor item that has to pass before it.

Por que: The form of the act and who signs it are set by the Ministry of Construction's rules on ispolnitelnaya dokumentatsiya, order 344/pr, and the parties have to be given time to get there. A hold point discovered on the morning of the pour becomes either a delayed pour or an act signed by whoever happened to be on site, and it is the second version that fails at handover.

EntradaProgramme for the sectionDesign and specificationResultadoHold points listedNotice given to each party
2

Have the documents for what is going in

Envíos

Log the passports, certificates of conformity and test reports for every material and product going into the hidden work as submittals of their own kind, certificate or test report, and check the batch named on the document against the batch that actually arrived before the submittal is approved.

Captura de pantalla, paso 2: Have the documents for what is going in (Envíos, Firma el acta de trabajos ocultos (akt skrytykh rabot) antes de cubrir la obra)
Envíos: Have the documents for what is going in

Por que: The act certifies the materials as well as the work, and it names them. A certificate covering a different batch, or one issued after the act was signed, is the first thing an inspection finds, because it is checkable from the paperwork alone without anybody going near the structure.

EntradaDelivered batchPassports and certificatesResultadoDocuments matched to the batchTest results on file
3

Write the day into the works journal

Diario de obra

Record the day in the general works journal: what was done and where, by whom, the weather where the process depends on it, the batch of concrete or mix used, and the entry number the act will refer back to.

Captura de pantalla, paso 3: Write the day into the works journal (Diario de obra, Firma el acta de trabajos ocultos (akt skrytykh rabot) antes de cubrir la obra)
Diario de obra: Write the day into the works journal

Por que: The journal and the act have to agree, because the journal is the continuous record and the act is a statement about one moment inside it. A dispute about when something was built is settled from the journal, and an act whose date has no matching entry is worth a great deal less than one that has.

EntradaWork done that dayConditions and batch usedResultadoJournal entryEntry the act refers to
4

Have construction control look at it while it is visible

Control de obra

Raise the inspection as hidden works at the hold point: your own construction control first, then the client's technical supervision, both against the drawing and the acceptance criteria rather than against the last act that was signed. Record a fail as a nonconformance and re-inspect once it is fixed; the gate stays closed until the result is a pass.

Captura de pantalla, paso 4: Have construction control look at it while it is visible (Control de obra, Firma el acta de trabajos ocultos (akt skrytykh rabot) antes de cubrir la obra)
Control de obra: Have construction control look at it while it is visible

Por que: Construction control is a duty on the contractor and on the client, not a courtesy either of them extends, and this is the last moment at which a mistake in a hidden element can still be put right cheaply. After it is covered, the correction is demolition.

EntradaHold point reachedDrawing and tolerancesResultadoInspection resultRe-inspection after fixes
5

Get the act signed by everyone who has to sign it

Firmas Electrónicas

Draw up the act of examination of hidden works with the design references, the materials and their documents, the result of the inspection and the permission to begin the following works, then run a signing session that collects the signature of every required party before anything is covered.

Captura de pantalla, paso 5: Get the act signed by everyone who has to sign it (Firmas Electrónicas, Firma el acta de trabajos ocultos (akt skrytykh rabot) antes de cubrir la obra)
Firmas Electrónicas: Get the act signed by everyone who has to sign it

Por que: The act is what permits the next operation to start and the only evidence that the hidden work was ever examined. An act drawn up later, with dates written to fit, is the document that gets challenged, because a signature added afterwards is not evidence that anybody looked.

EntradaInspection resultParties who must signResultadoSigned actPermission to proceed
6

Keep the set complete as it accumulates

Documentos

File each signed act together with the journal entries, the material documents and the survey results it refers to, indexed by structure and by date, and keep a running list of the acts the programme still expects against the ones that exist.

Captura de pantalla, paso 6: Keep the set complete as it accumulates (Documentos, Firma el acta de trabajos ocultos (akt skrytykh rabot) antes de cubrir la obra)
Documentos: Keep the set complete as it accumulates

Por que: The set is assembled at handover and checked as a whole, and that is the point at which a missing act stops being retrievable at all. A running list of expected against actual turns a scramble at the end of the job into a line on the weekly meeting.

EntradaSigned actsActs the programme expectsResultadoSet indexed by structureOutstanding acts listed
7

Let the act gate the payment for the work it covers

Avance

Tie each completed hidden operation to the position it belongs to in the month's acceptance, and record the period's quantity for a position only once its act is signed, so a position whose act is missing stays out of the submission until the act is there.

Captura de pantalla, paso 7: Let the act gate the payment for the work it covers (Avance, Firma el acta de trabajos ocultos (akt skrytykh rabot) antes de cubrir la obra)
Avance: Let the act gate the payment for the work it covers

Por que: The client's technical supervision certifies what it can verify, and hidden work is verifiable only through its act. A position submitted without one is not just paid later, it invites the client to question the whole submission, and a disputed line is struck out while everything behind it waits.

EntradaHidden work completedActs covering itResultadoPositions eligible for the monthPositions held back
Módulos

Módulos de este playbook

7 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Rusia

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • GESN/FER
  • KS-2 / KS-3

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Calidad y seguridad