在隐蔽前签署 akt skrytykh rabot(隐蔽工程验收记录)

列出下一道工序将要遮盖的内容,提前通知各方,记录所用材料,安排现场查验,让所有应签字的人在记录上签字,并把没有对应记录的子目排除在当月验收之外。

7 个步骤13 分钟总承包商专业分包商开发商/业主

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

List what will be hidden and who has to attend

质量管理

Go through the coming section and put every operation whose result the next one will cover on the inspection and test plan as a hold point: reinforcement before the pour, waterproofing before the screed, bedding and buried services before backfill. Against each, set the signatories the act needs, the client's technical supervision and the designer where author supervision is required, the notice period you owe them, and the predecessor item that has to pass before it.

原因: The form of the act and who signs it are set by the Ministry of Construction's rules on ispolnitelnaya dokumentatsiya, order 344/pr, and the parties have to be given time to get there. A hold point discovered on the morning of the pour becomes either a delayed pour or an act signed by whoever happened to be on site, and it is the second version that fails at handover.

输入Programme for the sectionDesign and specification成果Hold points listedNotice given to each party
2

Have the documents for what is going in

提交物

Log the passports, certificates of conformity and test reports for every material and product going into the hidden work as submittals of their own kind, certificate or test report, and check the batch named on the document against the batch that actually arrived before the submittal is approved.

原因: The act certifies the materials as well as the work, and it names them. A certificate covering a different batch, or one issued after the act was signed, is the first thing an inspection finds, because it is checkable from the paperwork alone without anybody going near the structure.

输入Delivered batchPassports and certificates成果Documents matched to the batchTest results on file
3

Write the day into the works journal

施工日志

Record the day in the general works journal: what was done and where, by whom, the weather where the process depends on it, the batch of concrete or mix used, and the entry number the act will refer back to.

原因: The journal and the act have to agree, because the journal is the continuous record and the act is a statement about one moment inside it. A dispute about when something was built is settled from the journal, and an act whose date has no matching entry is worth a great deal less than one that has.

输入Work done that dayConditions and batch used成果Journal entryEntry the act refers to
4

Have construction control look at it while it is visible

施工管控

Raise the inspection as hidden works at the hold point: your own construction control first, then the client's technical supervision, both against the drawing and the acceptance criteria rather than against the last act that was signed. Record a fail as a nonconformance and re-inspect once it is fixed; the gate stays closed until the result is a pass.

原因: Construction control is a duty on the contractor and on the client, not a courtesy either of them extends, and this is the last moment at which a mistake in a hidden element can still be put right cheaply. After it is covered, the correction is demolition.

输入Hold point reachedDrawing and tolerances成果Inspection resultRe-inspection after fixes
5

Get the act signed by everyone who has to sign it

电子签名

Draw up the act of examination of hidden works with the design references, the materials and their documents, the result of the inspection and the permission to begin the following works, then run a signing session that collects the signature of every required party before anything is covered.

原因: The act is what permits the next operation to start and the only evidence that the hidden work was ever examined. An act drawn up later, with dates written to fit, is the document that gets challenged, because a signature added afterwards is not evidence that anybody looked.

输入Inspection resultParties who must sign成果Signed actPermission to proceed
6

Keep the set complete as it accumulates

文档

File each signed act together with the journal entries, the material documents and the survey results it refers to, indexed by structure and by date, and keep a running list of the acts the programme still expects against the ones that exist.

原因: The set is assembled at handover and checked as a whole, and that is the point at which a missing act stops being retrievable at all. A running list of expected against actual turns a scramble at the end of the job into a line on the weekly meeting.

输入Signed actsActs the programme expects成果Set indexed by structureOutstanding acts listed
7

Let the act gate the payment for the work it covers

进度

Tie each completed hidden operation to the position it belongs to in the month's acceptance, and record the period's quantity for a position only once its act is signed, so a position whose act is missing stays out of the submission until the act is there.

原因: The client's technical supervision certifies what it can verify, and hidden work is verifiable only through its act. A position submitted without one is not just paid later, it invites the client to question the whole submission, and a disputed line is struck out while everything behind it waits.

输入Hidden work completedActs covering it成果Positions eligible for the monthPositions held back
模块

此方案使用的模块

190 个平台模块中的 7

The market this case is written for

俄罗斯

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 质量与安全 案例

质量与安全

检查工程并关闭不符合项

依据验收标准检查工程,一旦不合格立即提出不符合项,推动整改并复检,使记录能证明缺陷已确实修复。

3 个步骤10 分钟打开
质量与安全

安全讲话与安全检查

向班组说明本班次实际存在的隐患,记录出勤人员,然后在巡查中验证约定的管控措施是否真正落实。

2 个步骤8 分钟打开
质量与安全

获取材料报审批准

将拟采购的产品连同技术资料提交设计方审核,对照技术规格进行核查,获批后再放行下单。

3 个步骤9 分钟打开