Juhtumid / Kvaliteet ja ohutus
Kvaliteet ja ohutus

Allkirjastage varjatud tööde akt (akt skrytykh rabot), enne kui töö kaetakse

Loetle, mida järgmine tööetapp peidab, teavita pooli, dokumenteeri materjalid, lase see üle vaadata, lase akt allkirjastada kõigil, kes peavad seda tegema, ning jäta positsioon, millel akti pole, kuu vastuvõtust välja.

7 sammu13 minPeatöövõtjaErialaalltöövõtjaArendaja / klient

Kuidas see töötab, samm-sammult

7 sammu läbi platvormi - mida teete igas ja miks see loeb.

1

List what will be hidden and who has to attend

Kvaliteedijuhtimine

Go through the coming section and put every operation whose result the next one will cover on the inspection and test plan as a hold point: reinforcement before the pour, waterproofing before the screed, bedding and buried services before backfill. Against each, set the signatories the act needs, the client's technical supervision and the designer where author supervision is required, the notice period you owe them, and the predecessor item that has to pass before it.

Miks: The form of the act and who signs it are set by the Ministry of Construction's rules on ispolnitelnaya dokumentatsiya, order 344/pr, and the parties have to be given time to get there. A hold point discovered on the morning of the pour becomes either a delayed pour or an act signed by whoever happened to be on site, and it is the second version that fails at handover.

SisendProgramme for the sectionDesign and specificationVäljundHold points listedNotice given to each party
2

Have the documents for what is going in

Esitised

Log the passports, certificates of conformity and test reports for every material and product going into the hidden work as submittals of their own kind, certificate or test report, and check the batch named on the document against the batch that actually arrived before the submittal is approved.

Ekraanipilt, samm 2: Have the documents for what is going in (Esitised, Allkirjastage varjatud tööde akt (akt skrytykh rabot), enne kui töö kaetakse)
Esitised: Have the documents for what is going in

Miks: The act certifies the materials as well as the work, and it names them. A certificate covering a different batch, or one issued after the act was signed, is the first thing an inspection finds, because it is checkable from the paperwork alone without anybody going near the structure.

SisendDelivered batchPassports and certificatesVäljundDocuments matched to the batchTest results on file
3

Write the day into the works journal

Päevik

Record the day in the general works journal: what was done and where, by whom, the weather where the process depends on it, the batch of concrete or mix used, and the entry number the act will refer back to.

Ekraanipilt, samm 3: Write the day into the works journal (Päevik, Allkirjastage varjatud tööde akt (akt skrytykh rabot), enne kui töö kaetakse)
Päevik: Write the day into the works journal

Miks: The journal and the act have to agree, because the journal is the continuous record and the act is a statement about one moment inside it. A dispute about when something was built is settled from the journal, and an act whose date has no matching entry is worth a great deal less than one that has.

SisendWork done that dayConditions and batch usedVäljundJournal entryEntry the act refers to
4

Have construction control look at it while it is visible

Ehituse juhtimine

Raise the inspection as hidden works at the hold point: your own construction control first, then the client's technical supervision, both against the drawing and the acceptance criteria rather than against the last act that was signed. Record a fail as a nonconformance and re-inspect once it is fixed; the gate stays closed until the result is a pass.

Ekraanipilt, samm 4: Have construction control look at it while it is visible (Ehituse juhtimine, Allkirjastage varjatud tööde akt (akt skrytykh rabot), enne kui töö kaetakse)
Ehituse juhtimine: Have construction control look at it while it is visible

Miks: Construction control is a duty on the contractor and on the client, not a courtesy either of them extends, and this is the last moment at which a mistake in a hidden element can still be put right cheaply. After it is covered, the correction is demolition.

SisendHold point reachedDrawing and tolerancesVäljundInspection resultRe-inspection after fixes
5

Get the act signed by everyone who has to sign it

E-allkirjad

Draw up the act of examination of hidden works with the design references, the materials and their documents, the result of the inspection and the permission to begin the following works, then run a signing session that collects the signature of every required party before anything is covered.

Ekraanipilt, samm 5: Get the act signed by everyone who has to sign it (E-allkirjad, Allkirjastage varjatud tööde akt (akt skrytykh rabot), enne kui töö kaetakse)
E-allkirjad: Get the act signed by everyone who has to sign it

Miks: The act is what permits the next operation to start and the only evidence that the hidden work was ever examined. An act drawn up later, with dates written to fit, is the document that gets challenged, because a signature added afterwards is not evidence that anybody looked.

SisendInspection resultParties who must signVäljundSigned actPermission to proceed
6

Keep the set complete as it accumulates

Dokumendid

File each signed act together with the journal entries, the material documents and the survey results it refers to, indexed by structure and by date, and keep a running list of the acts the programme still expects against the ones that exist.

Ekraanipilt, samm 6: Keep the set complete as it accumulates (Dokumendid, Allkirjastage varjatud tööde akt (akt skrytykh rabot), enne kui töö kaetakse)
Dokumendid: Keep the set complete as it accumulates

Miks: The set is assembled at handover and checked as a whole, and that is the point at which a missing act stops being retrievable at all. A running list of expected against actual turns a scramble at the end of the job into a line on the weekly meeting.

SisendSigned actsActs the programme expectsVäljundSet indexed by structureOutstanding acts listed
7

Let the act gate the payment for the work it covers

Edenemine

Tie each completed hidden operation to the position it belongs to in the month's acceptance, and record the period's quantity for a position only once its act is signed, so a position whose act is missing stays out of the submission until the act is there.

Ekraanipilt, samm 7: Let the act gate the payment for the work it covers (Edenemine, Allkirjastage varjatud tööde akt (akt skrytykh rabot), enne kui töö kaetakse)
Edenemine: Let the act gate the payment for the work it covers

Miks: The client's technical supervision certifies what it can verify, and hidden work is verifiable only through its act. A position submitted without one is not just paid later, it invites the client to question the whole submission, and a disputed line is struck out while everything behind it waits.

SisendHidden work completedActs covering itVäljundPositions eligible for the monthPositions held back
Moodulid

Selle tegevusjuhendi moodulid

7 / 190 platvormi moodulit

The market this case is written for

Venemaa

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Rohkem valdkonnas Kvaliteet ja ohutus

Kvaliteet ja ohutus

Ohutusbriifing ja kontroll

Briifi brigaad selle vahetuse tegelikest ohtudest, jäädvusta, kes viibis kohal, seejärel tõe…

2 sammu8 minAva
Kvaliteet ja ohutus

Saa materjali esitisele kinnitus

Pane toode, mida plaanid osta, projekteerija ette koos selle andmetega, lase see spetsifikat…

3 sammu9 minAva