Juhtumid / Äritegevus ja lepingud
Äritegevus ja lepingud

Nõua ajuste de costos't avalikul ehituslepingul

Tuvasta, millise menetluse leping valis, pane kirja tegur, mille iga periood avaldatud indeksitest andis, selgita välja, milliste töödeni korrigeerimine tegelikult ulatub, rakenda see costos directos'ile eraldi reana ning esita solicitud enne kuuekümne kalendripäeva möödumist.

6 sammu20 minPeatöövõtjaKulunõustamine / QSArendaja / klient

Kuidas see töötab, samm-sammult

6 sammu läbi platvormi - mida teete igas ja miks see loeb.

1

Find out which procedure the contract actually chose

Lepingud

Read the contract for three things and record them against it: that ajuste de costos was provided for at all, which of the procedures of article 57 LOPSRM it names, and the base month the adjustment runs from, which is fixed by the presentation and opening of proposals rather than by the day work started. Note that the unamortised anticipo is outside the adjustment, because the money for it was already in your hands.

Ekraanipilt, samm 1: Find out which procedure the contract actually chose (Lepingud, Nõua ajuste de costos't avalikul ehituslepingul)
Lepingud: Find out which procedure the contract actually chose

Miks: The procedure is chosen at signature and cannot be swapped later for the one that gives a better answer, which is exactly what a firm tries to do the first month it wants to claim. Establishing it at the start costs an hour and settles every claim for the life of the contract, and the base month settles more than the procedure does: the same published indices give a different result from a different base.

SisendContract and bases de licitacionProgramme as agreedVäljundArticle 57 procedure the contract choseBase month recorded
2

Record the factor each month produced

Hinnaindeks

Create a series for this contract and add one point per month: the period and the factor the chosen procedure produced for it, against the producer price indices for public works inputs that INEGI publishes. The arithmetic across the grupos de precios, with the relative weight of each insumo, is done outside the platform. What lives here is the factor it produced and the month it belongs to.

Ekraanipilt, samm 2: Record the factor each month produced (Hinnaindeks, Nõua ajuste de costos't avalikul ehituslepingul)
Hinnaindeks: Record the factor each month produced

Miks: Published indices are revised after publication, so an audit two years later can look the same month up and get a different number. A dated series of the factors you actually applied, kept beside the contract, is the difference between a calculation that can be defended twice and one that can only be defended by the person who did it, who by then works somewhere else.

SisendPublished INPP values for the monthGrupos de precios and their weightsVäljundIndex series, one point per periodFactor for each month
3

Work out which work the adjustment reaches

Edenemine

Take the programme and mark, month by month, the work that was still pending execution when the cost movement happened. Article 58 LOPSRM computes the adjustment from that month over work pending according to the agreed programme, so where the works are behind for a reason that is your own, the eligible quantity is the one the original programme said would still be outstanding, not the one that actually was.

Ekraanipilt, samm 3: Work out which work the adjustment reaches (Edenemine, Nõua ajuste de costos't avalikul ehituslepingul)
Edenemine: Work out which work the adjustment reaches

Miks: This is the sentence that decides most ajuste disputes, and it cuts both ways. A contractor running late cannot enlarge a claim by being later; a contractor running early is not punished for it. Working the eligible quantity out from the programme, in writing, at the time, is what turns the claim into a check rather than a negotiation.

SisendAgreed programme against actual progressMonth the cost movement happenedVäljundWork the adjustment reachesWork excluded, with the reason
4

Put the ajuste on its own line, on the costos directos

Finants

Apply the factor to the eligible amount and carry the result as a separate line beside the estimacion, never inside it. The precios unitarios of the contract stay exactly as awarded, the adjustment moves the costos directos, and the percentages of indirectos and utilidad stay as they were tendered.

Ekraanipilt, samm 4: Put the ajuste on its own line, on the costos directos (Finants, Nõua ajuste de costos't avalikul ehituslepingul)
Finants: Put the ajuste on its own line, on the costos directos

Miks: An adjustment folded into the unit rates destroys the one comparison anybody has, which is what was certified against what was contracted, and it compounds without anybody deciding to: next month is adjusted against rates that were already adjusted. It surfaces at the finiquito, when the paid total will not reconcile to the catalogo and nobody can say which month the drift started in.

SisendEligible amount for the periodFactor for that periodVäljundAjuste as its own lineContract precios unitarios untouched
5

File the solicitud before the sixty days run out

Kirjavahetus

Present the solicitud de ajuste de costos in writing with the studies and documentation behind it, and record the date the indices for that month were published as well as the date you filed. The count is sixty natural days from the publication, and natural means it does not stretch for weekends or holidays.

Ekraanipilt, samm 5: File the solicitud before the sixty days run out (Kirjavahetus, Nõua ajuste de costos't avalikul ehituslepingul)
Kirjavahetus: File the solicitud before the sixty days run out

Miks: When that period passes the contractor loses the possibility of asking, and a right that has lapsed is not recovered by being obviously correct. This is the single most expensive deadline on a Mexican public contract precisely because nothing happens on the day it passes: no letter arrives, no meeting is called, and the loss is only discovered when somebody finally gets round to preparing the claim.

SisendFactor, eligible work and the arithmeticDate the indices were publishedVäljundSolicitud filed and datedThe dependencia's own period running
6

Track what the adjustment is worth across the job

Aruanded

Report the ajuste recognised so far against the value certified, and carry the trend of the factors over the work still to come so the forecast and the cash plan carry it too. Check every month that a solicitud was filed for the month before, because that is the check nobody runs.

Ekraanipilt, samm 6: Track what the adjustment is worth across the job (Aruanded, Nõua ajuste de costos't avalikul ehituslepingul)
Aruanded: Track what the adjustment is worth across the job

Miks: Ajuste is usually treated as a windfall that turns up in the accounts, which means it is never in the forecast and nobody notices when a month is missed. On a three year contract it is a material share of turnover, and one skipped month is not visible in any total until the job is over.

SisendAjuste recognised to dateWork still to comeVäljundReport of ajuste against certified valueForecast carrying the trend forward
Moodulid

Selle tegevusjuhendi moodulid

6 / 190 platvormi moodulit

The market this case is written for

Mehhiko

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Rohkem valdkonnas Äritegevus ja lepingud

Äritegevus ja lepingud

Halda alltöövõtjapaketti

Anna eriala pakett alltöövõtjale, pane see allhankelepingule koos väärtuste ajakava ja kinni…

3 sammu11 minAva
Äritegevus ja lepingud

Maksetaotlus ja sobitamine

Hinnasta selle perioodi paigaldatud töö lepingu vastu, tõsta taotlus koos selle taga oleva t…

3 sammu12 minAva