公共工事契約において ajuste de costos による費用の調整を請求する

契約がどの手続を選んだかを確定し、公表された指数から各期に生じた係数を記録し、調整が実際に及ぶ工事の範囲を割り出し、それを独立した行として costos directos に適用し、60 暦日が尽きる前に solicitud を提出する。

6ステップ20 分総合建設会社コストコンサルティング会社 / 積算事務所デベロッパー / 発注者

仕組みをステップごとに

プラットフォーム全体で6ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Find out which procedure the contract actually chose

契約

Read the contract for three things and record them against it: that ajuste de costos was provided for at all, which of the procedures of article 57 LOPSRM it names, and the base month the adjustment runs from, which is fixed by the presentation and opening of proposals rather than by the day work started. Note that the unamortised anticipo is outside the adjustment, because the money for it was already in your hands.

理由: The procedure is chosen at signature and cannot be swapped later for the one that gives a better answer, which is exactly what a firm tries to do the first month it wants to claim. Establishing it at the start costs an hour and settles every claim for the life of the contract, and the base month settles more than the procedure does: the same published indices give a different result from a different base.

入力Contract and bases de licitacionProgramme as agreed出力Article 57 procedure the contract choseBase month recorded
2

Record the factor each month produced

物価指数

Create a series for this contract and add one point per month: the period and the factor the chosen procedure produced for it, against the producer price indices for public works inputs that INEGI publishes. The arithmetic across the grupos de precios, with the relative weight of each insumo, is done outside the platform. What lives here is the factor it produced and the month it belongs to.

理由: Published indices are revised after publication, so an audit two years later can look the same month up and get a different number. A dated series of the factors you actually applied, kept beside the contract, is the difference between a calculation that can be defended twice and one that can only be defended by the person who did it, who by then works somewhere else.

入力Published INPP values for the monthGrupos de precios and their weights出力Index series, one point per periodFactor for each month
3

Work out which work the adjustment reaches

進捗

Take the programme and mark, month by month, the work that was still pending execution when the cost movement happened. Article 58 LOPSRM computes the adjustment from that month over work pending according to the agreed programme, so where the works are behind for a reason that is your own, the eligible quantity is the one the original programme said would still be outstanding, not the one that actually was.

理由: This is the sentence that decides most ajuste disputes, and it cuts both ways. A contractor running late cannot enlarge a claim by being later; a contractor running early is not punished for it. Working the eligible quantity out from the programme, in writing, at the time, is what turns the claim into a check rather than a negotiation.

入力Agreed programme against actual progressMonth the cost movement happened出力Work the adjustment reachesWork excluded, with the reason
4

Put the ajuste on its own line, on the costos directos

財務

Apply the factor to the eligible amount and carry the result as a separate line beside the estimacion, never inside it. The precios unitarios of the contract stay exactly as awarded, the adjustment moves the costos directos, and the percentages of indirectos and utilidad stay as they were tendered.

理由: An adjustment folded into the unit rates destroys the one comparison anybody has, which is what was certified against what was contracted, and it compounds without anybody deciding to: next month is adjusted against rates that were already adjusted. It surfaces at the finiquito, when the paid total will not reconcile to the catalogo and nobody can say which month the drift started in.

入力Eligible amount for the periodFactor for that period出力Ajuste as its own lineContract precios unitarios untouched
5

File the solicitud before the sixty days run out

やり取り

Present the solicitud de ajuste de costos in writing with the studies and documentation behind it, and record the date the indices for that month were published as well as the date you filed. The count is sixty natural days from the publication, and natural means it does not stretch for weekends or holidays.

理由: When that period passes the contractor loses the possibility of asking, and a right that has lapsed is not recovered by being obviously correct. This is the single most expensive deadline on a Mexican public contract precisely because nothing happens on the day it passes: no letter arrives, no meeting is called, and the loss is only discovered when somebody finally gets round to preparing the claim.

入力Factor, eligible work and the arithmeticDate the indices were published出力Solicitud filed and datedThe dependencia's own period running
6

Track what the adjustment is worth across the job

レポート

Report the ajuste recognised so far against the value certified, and carry the trend of the factors over the work still to come so the forecast and the cash plan carry it too. Check every month that a solicitud was filed for the month before, because that is the check nobody runs.

理由: Ajuste is usually treated as a windfall that turns up in the accounts, which means it is never in the forecast and nobody notices when a month is missed. On a three year contract it is a material share of turnover, and one skipped month is not visible in any total until the job is over.

入力Ajuste recognised to dateWork still to come出力Report of ajuste against certified valueForecast carrying the trend forward
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 6

The market this case is written for

メキシコ

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

コマーシャルと契約の他のケース

コマーシャルと契約

変更を支払われる契約変更に変える

施工範囲の変更を発生時に記録し、合意単価に基づいて契約変更として見積もり、次の出来高請求に計上することで、追加工事が静かに吸収されるのではなく回収されるようにします。

3ステップ11 分開く
コマーシャルと契約

下請パッケージを運用する

下請業者に工種パッケージを発注し、出来高内訳書と保留金付きの下請契約に載せ、実際に完了した作業に対して出来高払いで支払っていく。

3ステップ11 分開く
コマーシャルと契約

出来高査定申請と照合

今期に実施した工事を契約に照らして評価し、根拠となる証憑とともに出来高査定申請を起票し、認定された内容と実際に入金された内容を照合する。

3ステップ12 分開く