案例 / 商务与合同
商务与合同

在公共工程合同上主张成本调整

先确认合同选定了哪一种调整程序,按公布的指数记下每一期产生的调整系数,算清 ajuste de costos 实际能覆盖哪些工作量,把它作为独立一行加到 costos directos 上,并在 60 个自然日用完之前递交 solicitud。

6 个步骤20 分钟总承包商造价咨询 / 工料测量顾问开发商/业主

运作方式,逐步说明

贯穿平台的 6 个步骤 - 每一步做什么,以及为什么重要。

1

Find out which procedure the contract actually chose

合同

Read the contract for three things and record them against it: that ajuste de costos was provided for at all, which of the procedures of article 57 LOPSRM it names, and the base month the adjustment runs from, which is fixed by the presentation and opening of proposals rather than by the day work started. Note that the unamortised anticipo is outside the adjustment, because the money for it was already in your hands.

原因: The procedure is chosen at signature and cannot be swapped later for the one that gives a better answer, which is exactly what a firm tries to do the first month it wants to claim. Establishing it at the start costs an hour and settles every claim for the life of the contract, and the base month settles more than the procedure does: the same published indices give a different result from a different base.

输入Contract and bases de licitacionProgramme as agreed成果Article 57 procedure the contract choseBase month recorded
2

Record the factor each month produced

价格指数

Create a series for this contract and add one point per month: the period and the factor the chosen procedure produced for it, against the producer price indices for public works inputs that INEGI publishes. The arithmetic across the grupos de precios, with the relative weight of each insumo, is done outside the platform. What lives here is the factor it produced and the month it belongs to.

原因: Published indices are revised after publication, so an audit two years later can look the same month up and get a different number. A dated series of the factors you actually applied, kept beside the contract, is the difference between a calculation that can be defended twice and one that can only be defended by the person who did it, who by then works somewhere else.

输入Published INPP values for the monthGrupos de precios and their weights成果Index series, one point per periodFactor for each month
3

Work out which work the adjustment reaches

进度

Take the programme and mark, month by month, the work that was still pending execution when the cost movement happened. Article 58 LOPSRM computes the adjustment from that month over work pending according to the agreed programme, so where the works are behind for a reason that is your own, the eligible quantity is the one the original programme said would still be outstanding, not the one that actually was.

原因: This is the sentence that decides most ajuste disputes, and it cuts both ways. A contractor running late cannot enlarge a claim by being later; a contractor running early is not punished for it. Working the eligible quantity out from the programme, in writing, at the time, is what turns the claim into a check rather than a negotiation.

输入Agreed programme against actual progressMonth the cost movement happened成果Work the adjustment reachesWork excluded, with the reason
4

Put the ajuste on its own line, on the costos directos

财务

Apply the factor to the eligible amount and carry the result as a separate line beside the estimacion, never inside it. The precios unitarios of the contract stay exactly as awarded, the adjustment moves the costos directos, and the percentages of indirectos and utilidad stay as they were tendered.

原因: An adjustment folded into the unit rates destroys the one comparison anybody has, which is what was certified against what was contracted, and it compounds without anybody deciding to: next month is adjusted against rates that were already adjusted. It surfaces at the finiquito, when the paid total will not reconcile to the catalogo and nobody can say which month the drift started in.

输入Eligible amount for the periodFactor for that period成果Ajuste as its own lineContract precios unitarios untouched
5

File the solicitud before the sixty days run out

往来函件

Present the solicitud de ajuste de costos in writing with the studies and documentation behind it, and record the date the indices for that month were published as well as the date you filed. The count is sixty natural days from the publication, and natural means it does not stretch for weekends or holidays.

原因: When that period passes the contractor loses the possibility of asking, and a right that has lapsed is not recovered by being obviously correct. This is the single most expensive deadline on a Mexican public contract precisely because nothing happens on the day it passes: no letter arrives, no meeting is called, and the loss is only discovered when somebody finally gets round to preparing the claim.

输入Factor, eligible work and the arithmeticDate the indices were published成果Solicitud filed and datedThe dependencia's own period running
6

Track what the adjustment is worth across the job

报告

Report the ajuste recognised so far against the value certified, and carry the trend of the factors over the work still to come so the forecast and the cash plan carry it too. Check every month that a solicitud was filed for the month before, because that is the check nobody runs.

原因: Ajuste is usually treated as a windfall that turns up in the accounts, which means it is never in the forecast and nobody notices when a month is missed. On a three year contract it is a material share of turnover, and one skipped month is not visible in any total until the job is over.

输入Ajuste recognised to dateWork still to come成果Report of ajuste against certified valueForecast carrying the trend forward
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

墨西哥

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 商务与合同 案例

商务与合同

把变更转化为已付款的变更单

在范围变更还新鲜时就记录下来,依据你已约定的单价将其作为合同变更报价,并在下一期进度付款申请中计入,使额外工作能够获得补偿,而不是被悄悄吸收。

3 个步骤11 分钟打开
商务与合同

管理分包工程

将某工种分包给分包商,以带付款计划表和保留金条款的分包合同确定下来,再按实际完成的工作逐期支付款项。

3 个步骤11 分钟打开
商务与合同

付款申请与对账

按合同对本期已完成工作进行估值,附上依据提出申请,并将已核证的金额与账户实际到账的金额进行对账。

3 个步骤12 分钟打开