Ajuste de costos bei einem öffentlichen Bauauftrag geltend machen

Stellen Sie fest, welches Verfahren der Vertrag gewählt hat, erfassen Sie den Faktor, den jede Periode aus den veröffentlichten Indizes ergibt, ermitteln Sie, welche Leistung die Anpassung tatsächlich erreicht, wenden Sie sie als eigene Zeile auf die costos directos an und reichen Sie die solicitud ein, bevor die sechzig natürlichen Tage ablaufen.

6 Schritte20 Min.GeneralunternehmerKosten- / MengenberatungProjektentwickler / Bauherr

So funktioniert es, Schritt für Schritt

6 Schritte über die Plattform hinweg - was Sie bei jedem tun und warum es zählt.

1

Find out which procedure the contract actually chose

Verträge

Read the contract for three things and record them against it: that ajuste de costos was provided for at all, which of the procedures of article 57 LOPSRM it names, and the base month the adjustment runs from, which is fixed by the presentation and opening of proposals rather than by the day work started. Note that the unamortised anticipo is outside the adjustment, because the money for it was already in your hands.

Warum: The procedure is chosen at signature and cannot be swapped later for the one that gives a better answer, which is exactly what a firm tries to do the first month it wants to claim. Establishing it at the start costs an hour and settles every claim for the life of the contract, and the base month settles more than the procedure does: the same published indices give a different result from a different base.

EingangContract and bases de licitacionProgramme as agreedErgebnisArticle 57 procedure the contract choseBase month recorded
2

Record the factor each month produced

Preisindex

Create a series for this contract and add one point per month: the period and the factor the chosen procedure produced for it, against the producer price indices for public works inputs that INEGI publishes. The arithmetic across the grupos de precios, with the relative weight of each insumo, is done outside the platform. What lives here is the factor it produced and the month it belongs to.

Warum: Published indices are revised after publication, so an audit two years later can look the same month up and get a different number. A dated series of the factors you actually applied, kept beside the contract, is the difference between a calculation that can be defended twice and one that can only be defended by the person who did it, who by then works somewhere else.

EingangPublished INPP values for the monthGrupos de precios and their weightsErgebnisIndex series, one point per periodFactor for each month
3

Work out which work the adjustment reaches

Fortschritt

Take the programme and mark, month by month, the work that was still pending execution when the cost movement happened. Article 58 LOPSRM computes the adjustment from that month over work pending according to the agreed programme, so where the works are behind for a reason that is your own, the eligible quantity is the one the original programme said would still be outstanding, not the one that actually was.

Warum: This is the sentence that decides most ajuste disputes, and it cuts both ways. A contractor running late cannot enlarge a claim by being later; a contractor running early is not punished for it. Working the eligible quantity out from the programme, in writing, at the time, is what turns the claim into a check rather than a negotiation.

EingangAgreed programme against actual progressMonth the cost movement happenedErgebnisWork the adjustment reachesWork excluded, with the reason
4

Put the ajuste on its own line, on the costos directos

Finanzen

Apply the factor to the eligible amount and carry the result as a separate line beside the estimacion, never inside it. The precios unitarios of the contract stay exactly as awarded, the adjustment moves the costos directos, and the percentages of indirectos and utilidad stay as they were tendered.

Warum: An adjustment folded into the unit rates destroys the one comparison anybody has, which is what was certified against what was contracted, and it compounds without anybody deciding to: next month is adjusted against rates that were already adjusted. It surfaces at the finiquito, when the paid total will not reconcile to the catalogo and nobody can say which month the drift started in.

EingangEligible amount for the periodFactor for that periodErgebnisAjuste as its own lineContract precios unitarios untouched
5

File the solicitud before the sixty days run out

Korrespondenz

Present the solicitud de ajuste de costos in writing with the studies and documentation behind it, and record the date the indices for that month were published as well as the date you filed. The count is sixty natural days from the publication, and natural means it does not stretch for weekends or holidays.

Warum: When that period passes the contractor loses the possibility of asking, and a right that has lapsed is not recovered by being obviously correct. This is the single most expensive deadline on a Mexican public contract precisely because nothing happens on the day it passes: no letter arrives, no meeting is called, and the loss is only discovered when somebody finally gets round to preparing the claim.

EingangFactor, eligible work and the arithmeticDate the indices were publishedErgebnisSolicitud filed and datedThe dependencia's own period running
6

Track what the adjustment is worth across the job

Berichte

Report the ajuste recognised so far against the value certified, and carry the trend of the factors over the work still to come so the forecast and the cash plan carry it too. Check every month that a solicitud was filed for the month before, because that is the check nobody runs.

Warum: Ajuste is usually treated as a windfall that turns up in the accounts, which means it is never in the forecast and nobody notices when a month is missed. On a three year contract it is a material share of turnover, and one skipped month is not visible in any total until the job is over.

EingangAjuste recognised to dateWork still to comeErgebnisReport of ajuste against certified valueForecast carrying the trend forward
Module

Module in diesem Playbook

6 / 190 Plattform-Modulen

Der Markt, für den dieses Fallbeispiel geschrieben ist

Mexiko

Alles in diesem Fallbeispiel folgt der Art, wie Bauleistungen in diesem Markt aufgemessen, kalkuliert und abgerechnet werden. Die Formulare, die Kostengliederung und die Zahlungsregeln sind die, die dort gelten, und keine allgemeine Fassung davon.

Standards, denen es folgt

  • CFDI 4.0
  • Ley de Obras Publicas

Das müssen Sie nicht von Hand einrichten. Beim ersten Start fragt die Plattform, in welchem Markt Sie arbeiten. Wählen Sie diesen aus, und sie stellt die Oberflächensprache ein, lädt die passende Kostendatenbank, hinterlegt die Kostengliederung und legt ein Beispielprojekt an, das Sie sofort öffnen können.

Die Prüfregeln für diesen Markt sind ebenfalls dabei. Einmal eingeschaltet, fällt eine Kalkulation, der etwas Marktübliches fehlt, schon während der Arbeit auf und nicht erst nach der Abgabe.

Mehr aus Kaufmännisch & Verträge

Kaufmännisch & Verträge

Nachunternehmerpaket abwickeln

Ein Gewerkepaket an einen Nachunternehmer vergeben, es mit einem Zahlungsplan und Sicherheit…

3 Schritte11 Min.Öffnen
Kaufmännisch & Verträge

Zahlungsantrag und Abgleich

Bewerten Sie die in dieser Periode erbrachte Leistung gegen den Vertrag, stellen Sie den Zah…

3 Schritte12 Min.Öffnen