Reclamar o ajuste de costos num contrato de obras públicas

Apure que procedimento o contrato escolheu, registe o fator que cada período produziu a partir dos índices publicados, determine que trabalhos o ajuste alcança de facto, aplique-o aos costos directos como linha autónoma, e apresente a solicitud antes de esgotados os sessenta dias naturais.

6 etapas20 minEmpreiteiro geralConsultoria de custos / QSPromotor / cliente

Como funciona, passo a passo

6 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Find out which procedure the contract actually chose

Contratos

Read the contract for three things and record them against it: that ajuste de costos was provided for at all, which of the procedures of article 57 LOPSRM it names, and the base month the adjustment runs from, which is fixed by the presentation and opening of proposals rather than by the day work started. Note that the unamortised anticipo is outside the adjustment, because the money for it was already in your hands.

Por quê: The procedure is chosen at signature and cannot be swapped later for the one that gives a better answer, which is exactly what a firm tries to do the first month it wants to claim. Establishing it at the start costs an hour and settles every claim for the life of the contract, and the base month settles more than the procedure does: the same published indices give a different result from a different base.

EntradaContract and bases de licitacionProgramme as agreedResultadoArticle 57 procedure the contract choseBase month recorded
2

Record the factor each month produced

Índice de preços

Create a series for this contract and add one point per month: the period and the factor the chosen procedure produced for it, against the producer price indices for public works inputs that INEGI publishes. The arithmetic across the grupos de precios, with the relative weight of each insumo, is done outside the platform. What lives here is the factor it produced and the month it belongs to.

Por quê: Published indices are revised after publication, so an audit two years later can look the same month up and get a different number. A dated series of the factors you actually applied, kept beside the contract, is the difference between a calculation that can be defended twice and one that can only be defended by the person who did it, who by then works somewhere else.

EntradaPublished INPP values for the monthGrupos de precios and their weightsResultadoIndex series, one point per periodFactor for each month
3

Work out which work the adjustment reaches

Avanço

Take the programme and mark, month by month, the work that was still pending execution when the cost movement happened. Article 58 LOPSRM computes the adjustment from that month over work pending according to the agreed programme, so where the works are behind for a reason that is your own, the eligible quantity is the one the original programme said would still be outstanding, not the one that actually was.

Por quê: This is the sentence that decides most ajuste disputes, and it cuts both ways. A contractor running late cannot enlarge a claim by being later; a contractor running early is not punished for it. Working the eligible quantity out from the programme, in writing, at the time, is what turns the claim into a check rather than a negotiation.

EntradaAgreed programme against actual progressMonth the cost movement happenedResultadoWork the adjustment reachesWork excluded, with the reason
4

Put the ajuste on its own line, on the costos directos

Finanças

Apply the factor to the eligible amount and carry the result as a separate line beside the estimacion, never inside it. The precios unitarios of the contract stay exactly as awarded, the adjustment moves the costos directos, and the percentages of indirectos and utilidad stay as they were tendered.

Por quê: An adjustment folded into the unit rates destroys the one comparison anybody has, which is what was certified against what was contracted, and it compounds without anybody deciding to: next month is adjusted against rates that were already adjusted. It surfaces at the finiquito, when the paid total will not reconcile to the catalogo and nobody can say which month the drift started in.

EntradaEligible amount for the periodFactor for that periodResultadoAjuste as its own lineContract precios unitarios untouched
5

File the solicitud before the sixty days run out

Correspondência

Present the solicitud de ajuste de costos in writing with the studies and documentation behind it, and record the date the indices for that month were published as well as the date you filed. The count is sixty natural days from the publication, and natural means it does not stretch for weekends or holidays.

Por quê: When that period passes the contractor loses the possibility of asking, and a right that has lapsed is not recovered by being obviously correct. This is the single most expensive deadline on a Mexican public contract precisely because nothing happens on the day it passes: no letter arrives, no meeting is called, and the loss is only discovered when somebody finally gets round to preparing the claim.

EntradaFactor, eligible work and the arithmeticDate the indices were publishedResultadoSolicitud filed and datedThe dependencia's own period running
6

Track what the adjustment is worth across the job

Relatórios

Report the ajuste recognised so far against the value certified, and carry the trend of the factors over the work still to come so the forecast and the cash plan carry it too. Check every month that a solicitud was filed for the month before, because that is the check nobody runs.

Por quê: Ajuste is usually treated as a windfall that turns up in the accounts, which means it is never in the forecast and nobody notices when a month is missed. On a three year contract it is a material share of turnover, and one skipped month is not visible in any total until the job is over.

EntradaAjuste recognised to dateWork still to comeResultadoReport of ajuste against certified valueForecast carrying the trend forward
Módulos

Módulos deste playbook

6 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

México

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • CFDI 4.0
  • Ley de Obras Publicas

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Comercial e contratos

Comercial e contratos

Gerir um pacote de subempreitada

Adjudique um pacote de trabalhos a um subempreiteiro, coloque-o num subcontrato com um mapa…

3 etapas11 minAbrir
Comercial e contratos

Fatura de pagamento e conciliação

Valorize o trabalho executado neste período face ao contrato, apresente a fatura com a evidê…

3 etapas12 minAbrir