Cas / Appels d'offres & achats
Appels d'offres & achats

Soumissionner un marché public sous 44-FZ

Lisez l'avis pour déterminer si c'est le 44-FZ ou le 223-FZ qui s'applique, reconstituez la NMCK à partir de la smeta du client, intégrez votre propre risque dans le prix de l'offre, déposez la zayavka avec sa garantie et faites entrer le marché dans l'horloge de paiement que fixe la loi.

7 étapes15 minEntreprise généraleSous-traitant spécialiséÉconomie de la construction / métré

Comment ça marche, étape par étape

7 étapes à travers la plateforme - ce que vous faites à chacune et pourquoi c’est important.

1

Establish which law the purchase runs under

Appels d'offres

Read the notice in the unified information system and settle three things before touching the price: which law it names, 44-FZ or 223-FZ, which procedure is being run, and for a 223-FZ purchase which version of the customer's own procurement regulation applies. Note as well whether the purchase is reserved for small business.

Pourquoi: Under 44-FZ the procedure, the forms and the grounds for rejecting an application come from the statute and are identical for every customer in the country. Under 223-FZ they come from a regulation the customer writes itself, so two purchases run by two state companies can demand entirely different documents. Reading the wrong rulebook ends in rejection on formal grounds with your price never opened.

EntréePublished noticeCustomer's procurement regulationRésultatGoverning law identifiedRulebook that applies
2

Rebuild the NMCK from the customer's smeta

Devis quantitatif

Load the smeta published with the notice position by position and price it against your own rates and your own norms. Mark every position where the quantity, the norm or the price does not survive contact with how the work is actually done, and total what the difference is worth.

Capture d’écran, étape 2 : Rebuild the NMCK from the customer's smeta (Devis quantitatif, Soumissionner un marché public sous 44-FZ)
Devis quantitatif: Rebuild the NMCK from the customer's smeta

Pourquoi: The NMCK is both a ceiling and a claim about what the work costs. If it was built on a stale index or on a norm that does not fit the method the site will use, you learn it either now, while you can still decide not to bid, or eleven months in while carrying the difference yourself. Under 44-FZ the contract price is fixed on signature, so there is no later.

EntréeCustomer's smetaYour own rates and normsRésultatRebuilt pricePositions that do not hold
3

Price your own overhead, profit and risk into the offer

Devis quantitatif

In the bill's Markups & Overheads panel, set the overhead and profit this company actually needs rather than the normed percentages the NMCK was built with, add what the bid security, the performance security and the payment terms cost you in working capital, and work out the largest discount you could still carry at the end of the job.

Capture d’écran, étape 3 : Price your own overhead, profit and risk into the offer (Devis quantitatif, Soumissionner un marché public sous 44-FZ)
Devis quantitatif: Price your own overhead, profit and risk into the offer

Pourquoi: Normed NR and SP describe an average contractor on an average job, which is not this one. The discount settled here governs the whole contract, because a state contract is not renegotiated, and a bidder who goes a quarter or more below the NMCK triggers the anti-dumping measures in article 37 of 44-FZ and must post increased security or prove good faith before the contract can be signed.

EntréeRebuilt priceSecurity and payment termsRésultatOffer priceDiscount you can carry
4

Assemble the zayavka and post its security

Gestion des offres

Build the application the notice actually asks for: the price, the consent to the customer's terms, the declarations about the bidder, the evidence of comparable experience where the purchase demands it, and the bid security in one of the forms the notice allows. Check every deadline against the notice rather than against what the last purchase did.

Pourquoi: Most public work is lost on a missing declaration or on security posted in a form the notice did not accept, not on price. The commission checks the application against the notice mechanically, and once the deadline passes there is no route to add what was left out.

EntréeOffer priceDocuments the notice listsRésultatSubmitted zayavkaBid security posted
5

Take the contract at the price you offered

Contrats

Sign at your offered price with the performance security in place, and record the terms that will govern the whole job in one place: the intermediate and final deadlines, the penalty regime, the advance if there is one, the retention, and the narrow grounds on which the price or the scope may change.

Capture d’écran, étape 5 : Take the contract at the price you offered (Contrats, Soumissionner un marché public sous 44-FZ)
Contrats: Take the contract at the price you offered

Pourquoi: A contract under 44-FZ is signed on the customer's terms and its price is fixed by the law, with only the grounds the statute names for changing it afterwards. Whatever was not priced into the bid is yours to carry, so the contract record has to be the version the site, the estimator and the accounts all read, not a copy in one person's mailbox.

EntréeAward decisionPerformance securityRésultatSigned contract on recordTerms everyone works from
6

Put the payment term on the clock the law sets

Horloge de paiement

Put the contract on the 44-FZ public regime and let it count from the right event, the customer's signature on the acceptance document rather than the day you sent it. That gives seven working days to payment, ten where settlements run under treasury support or the acceptance was signed outside the unified system, which the regime does not compute for you, and the interest on delay is a statutory rate rather than a negotiated one.

Pourquoi: The term comes from article 34 of 44-FZ and is not a matter of local custom, so a customer paying late is in default from a date that can be named to the day. A clock started on the right event is what turns a conversation about slow payment into a claim with a figure attached.

EntréeSigned contractAcceptance documentRésultatPayment due dateStatutory delay interest
7

Watch the deadlines the penalty regime hangs on

Échéances

Load the intermediate and final deadlines the contract sets together with the notices you owe the customer, and let each one warn you before it lands instead of appearing in a letter afterwards.

Capture d’écran, étape 7 : Watch the deadlines the penalty regime hangs on (Échéances, Soumissionner un marché public sous 44-FZ)
Échéances: Watch the deadlines the penalty regime hangs on

Pourquoi: On a state contract a missed deadline produces a penalty calculated by formula, and a termination for your default puts the company into the register of unscrupulous suppliers, which closes public work to it for two years. The penalty is arithmetic and survivable, the register is not, and both start from a date nobody was watching.

EntréeContract deadlinesNotices you oweRésultatDeadlines under watchWarning before each date
Modules

Modules de ce playbook

6 / 190 modules de la plateforme

Le marché pour lequel ce cas est écrit

Russie

Tout dans ce cas suit la façon dont les travaux sont métrés, chiffrés et payés sur ce marché. Les formulaires, la décomposition des coûts et les règles de paiement sont ceux qui y sont utilisés, pas une version générique.

Normes qu’il suit

  • GESN/FER
  • KS-2 / KS-3

Vous n’avez rien de tout cela à paramétrer à la main. Au premier démarrage, la plateforme demande sur quel marché vous travaillez. Choisissez celui-ci et elle règle la langue de l’interface, charge la base de coûts correspondante, enregistre la classification des coûts et ajoute un projet d’exemple que vous pouvez ouvrir tout de suite.

Les contrôles propres à ce marché sont eux aussi fournis avec la plateforme. Une fois activés, un devis auquel il manque quelque chose que le marché attend est signalé pendant que vous y travaillez, et non après l’envoi de l’offre.

Plus dans Appels d'offres & achats

Appels d'offres & achats

Comparer les offres et attribuer

Prenez un dossier d'offres reçues qui ne concordent jamais tout à fait, ramenez-les au même…

3 étapes12 minOuvrir