Certifier le paiement intermédiaire et facturer l'administration

Enregistrez le contrat et ses garanties, mesurez la période par rapport au métré, récupérez l'avance et appliquez la retenue de garantie, faites établir par l'ingénieur le certificat de paiement intermédiaire et facturez l'administration sur ce montant dans le délai de paiement prévu par le droit de la commande publique.

7 étapes13 minEntreprise généraleSous-traitant spécialiséÉconomie de la construction / métré

Comment ça marche, étape par étape

7 étapes à travers la plateforme - ce que vous faites à chacune et pourquoi c’est important.

1

Register the contract and its payment regime

Contrats

Record the contract, its the government procurement payment rules payment regime and the dates it turns on, so every later step reads the same terms instead of somebody's memory of them.

Pourquoi: A payment regime that lives in a PDF nobody opens is a regime that gets applied differently by each person who applies it. Registered once, the deadlines below are computed rather than argued about.

EntréeSigned contractAdvance payment and performance guaranteesRésultatContract on recordCertification and payment terms attached
2

Measure the period BoQ item by BoQ item

Avancement

Record what was executed against each BoQ item for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

Pourquoi: An interim payment certificate built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one BoQ item rather than about the whole month, and the rest of the money moves while that one is settled.

EntréeContract bill of quantitiesWork executed this periodRésultatPercent complete per BoQ itemEarned quantities for the period
3

Value it at the contract rates

Devis quantitatif

Read the valuation back against the bill and check the rates it used are the contract rates. Where a BoQ item has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

Pourquoi: A variation order certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

EntréeEarned quantities for the periodContract ratesRésultatValuation for the periodVariation orders flagged
4

Apply retention and previous payments

Finances

Take the cumulative valuation, subtract what has already been certified, and apply retention at the contract percentage. The figure that leaves this step is the one the invoice is raised for, and the backup behind it is the measure that produced it. The advance is recovered on the proportion the period earned and the guarantee is reduced as it is recovered, so the two figures are read together rather than tracked in separate places by separate people.

Pourquoi: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

EntréeCumulative valuationAdvance payment outstandingPrevious payments and retentionRésultatAdvance payment recovered this periodNet due for the period
5

Get it approved by the people who have to approve it

Circuits d'approbation

Route the interim payment certificate to the Engineer, and to whoever the contract adds after them. Keep the approval date, because the invoice follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

Pourquoi: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

EntréeValuation for the periodEngineer named for certificationRésultatInterim payment certificate issuedCertification date on record
6

Issue the invoice against the approved figure

Finances

Raise the invoice against the approved interim payment certificate, carrying retention and any deduction the contract provides for, and reference the interim payment certificate on it.

Pourquoi: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the interim payment certificate also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

EntréeInterim payment certificate issuedRetention and deductionsRésultatInvoice submitted to the authorityAmount carried into the accounts
7

Open the payment clock on the right day

Horloge de paiement

Open a clock over the invoice starting from the day the invoice is submitted against the issued certificate, under the government procurement payment rules. Payment falls due 30 days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

Pourquoi: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the day the invoice is submitted against the issued certificate once makes the whole chain checkable. The window runs from a compliant submission, so an invoice returned for a missing attachment has not started anything even though it left your office. Recording what was submitted with it is what makes that visible on the day rather than at the end of the month.

EntréeInvoice and its submission dateCertificate dateRésultatOpen payment clockDue date computed
Modules

Modules de ce playbook

6 / 190 modules de la plateforme

Le marché pour lequel ce cas est écrit

Arabie saoudite

Tout dans ce cas suit la façon dont les travaux sont métrés, chiffrés et payés sur ce marché. Les formulaires, la décomposition des coûts et les règles de paiement sont ceux qui y sont utilisés, pas une version générique.

Normes qu’il suit

  • Saudi Building Code
  • Government Tenders and Procurement Law

Vous n’avez rien de tout cela à paramétrer à la main. Au premier démarrage, la plateforme demande sur quel marché vous travaillez. Choisissez celui-ci et elle règle la langue de l’interface, charge la base de coûts correspondante, enregistre la classification des coûts et ajoute un projet d’exemple que vous pouvez ouvrir tout de suite.

Les contrôles propres à ce marché sont eux aussi fournis avec la plateforme. Une fois activés, un devis auquel il manque quelque chose que le marché attend est signalé pendant que vous y travaillez, et non après l’envoi de l’offre.