案例 / 商务与合同
商务与合同

认证期中付款并向业主开票

登记合同及其保函,按工程量清单计量本期完成量,回收预付款并扣留履约金,由 Engineer 签发期中付款证书,再据此在采购法规定的期限内向业主开票。

7 个步骤13 分钟总承包商专业分包商造价咨询 / 工料测量顾问

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

Register the contract and its payment regime

合同

Record the contract, its the government procurement payment rules payment regime and the dates it turns on, so every later step reads the same terms instead of somebody's memory of them.

原因: A payment regime that lives in a PDF nobody opens is a regime that gets applied differently by each person who applies it. Registered once, the deadlines below are computed rather than argued about.

输入Signed contractAdvance payment and performance guarantees成果Contract on recordCertification and payment terms attached
2

Measure the period BoQ item by BoQ item

进度

Record what was executed against each BoQ item for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

原因: An interim payment certificate built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one BoQ item rather than about the whole month, and the rest of the money moves while that one is settled.

输入Contract bill of quantitiesWork executed this period成果Percent complete per BoQ itemEarned quantities for the period
3

Value it at the contract rates

工程量清单

Read the valuation back against the bill and check the rates it used are the contract rates. Where a BoQ item has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

原因: A variation order certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

输入Earned quantities for the periodContract rates成果Valuation for the periodVariation orders flagged
4

Apply retention and previous payments

财务

Take the cumulative valuation, subtract what has already been certified, and apply retention at the contract percentage. The figure that leaves this step is the one the invoice is raised for, and the backup behind it is the measure that produced it. The advance is recovered on the proportion the period earned and the guarantee is reduced as it is recovered, so the two figures are read together rather than tracked in separate places by separate people.

原因: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

输入Cumulative valuationAdvance payment outstandingPrevious payments and retention成果Advance payment recovered this periodNet due for the period
5

Get it approved by the people who have to approve it

审批路线

Route the interim payment certificate to the Engineer, and to whoever the contract adds after them. Keep the approval date, because the invoice follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

原因: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

输入Valuation for the periodEngineer named for certification成果Interim payment certificate issuedCertification date on record
6

Issue the invoice against the approved figure

财务

Raise the invoice against the approved interim payment certificate, carrying retention and any deduction the contract provides for, and reference the interim payment certificate on it.

原因: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the interim payment certificate also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

输入Interim payment certificate issuedRetention and deductions成果Invoice submitted to the authorityAmount carried into the accounts
7

Open the payment clock on the right day

付款时钟

Open a clock over the invoice starting from the day the invoice is submitted against the issued certificate, under the government procurement payment rules. Payment falls due 30 days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

原因: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the day the invoice is submitted against the issued certificate once makes the whole chain checkable. The window runs from a compliant submission, so an invoice returned for a missing attachment has not started anything even though it left your office. Recording what was submitted with it is what makes that visible on the day rather than at the end of the month.

输入Invoice and its submission dateCertificate date成果Open payment clockDue date computed
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

沙特阿拉伯

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 商务与合同 案例

商务与合同

把变更转化为已付款的变更单

在范围变更还新鲜时就记录下来,依据你已约定的单价将其作为合同变更报价,并在下一期进度付款申请中计入,使额外工作能够获得补偿,而不是被悄悄吸收。

3 个步骤11 分钟打开
商务与合同

管理分包工程

将某工种分包给分包商,以带付款计划表和保留金条款的分包合同确定下来,再按实际完成的工作逐期支付款项。

3 个步骤11 分钟打开
商务与合同

付款申请与对账

按合同对本期已完成工作进行估值,附上依据提出申请,并将已核证的金额与账户实际到账的金额进行对账。

3 个步骤12 分钟打开