ब्राज़ीलियाई अनुबंध पर वार्षिक reajustamento लागू करें

अनुबंध से सूचकांक, data-base और आवधिकता निकालें, प्रकाशित श्रृंखला लोड करें, वह work खोजें जिसकी वर्षगांठ बीत चुकी है, फ़ॉर्मूला लागू करें और परिणाम को खातों में दर्ज होने वाले समायोजन के रूप में रिकॉर्ड करें।

6 चरण15 मिनटमुख्य ठेकेदारविशेषज्ञ उपठेकेदारडेवलपर / क्लाइंट

यह कैसे काम करता है, चरण दर चरण

प्लेटफ़ॉर्म भर में 6 चरण - हर एक में आप क्या करते हैं और यह क्यों मायने रखता है।

1

Read the index and the data-base out of the contract

अनुबंध

Record three things from the contract itself: which index applies, and to which parcels of the work if there is more than one, what date the prices are referred to, and how the periodicity is counted. Note whether the data-base is the date of the proposal or the reference month of the orcamento, because they are often different.

स्क्रीनशॉट, चरण 1: Read the index and the data-base out of the contract (अनुबंध, ब्राज़ीलियाई अनुबंध पर वार्षिक reajustamento लागू करें)
अनुबंध: Read the index and the data-base out of the contract

क्यों: Lei 14.133 of 2021 requires the contract to state the criterion, the index and the date, and Lei 10.192 of 2001 fixes the periodicity at one year, so all three facts already exist and none of them is negotiable. What is negotiable is which of two plausible dates the parties meant, and settling that at the start of the contract costs a sentence rather than a claim.

इनपुटSigned contract termsEdital and its annexesपरिणामIndex named by the contractData-base date on the record
2

Load the index the contract names, not the one you follow

मूल्य सूचकांक

Load the published series for the named index, month by month, from the data-base to the month of application, and compute the factor between the two. Where the contract splits the work between several indices, load each one and keep the parcels apart.

स्क्रीनशॉट, चरण 2: Load the index the contract names, not the one you follow (मूल्य सूचकांक, ब्राज़ीलियाई अनुबंध पर वार्षिक reajustamento लागू करें)
मूल्य सूचकांक: Load the index the contract names, not the one you follow

क्यों: A construction cost index and a general price index diverge by several points a year, which on a long contract is the whole margin. Using the one you normally follow rather than the one the contract names produces a number that is defensible in every way except the one that matters, and the correction lands after the invoice is out.

इनपुटIndex named by the contractPublished index seriesपरिणामIndex series loaded by monthFactor between the two months
3

Find the work whose anniversary has passed

प्रगति

Split the measured work by the period it was executed in and separate what falls after the first anniversary of the data-base from what falls before it. Keep the two lists rather than applying an average to everything.

स्क्रीनशॉट, चरण 3: Find the work whose anniversary has passed (प्रगति, ब्राज़ीलियाई अनुबंध पर वार्षिक reajustamento लागू करें)
प्रगति: Find the work whose anniversary has passed

क्यों: The periodicity is annual under Lei 10.192 of 2001, so work executed inside the first year is not adjusted at all and work executed afterwards is adjusted by the factor for its own month. An average applied to the whole contract overpays one half and underpays the other, and it is the overpaid half that gets questioned.

इनपुटWork measured to dateData-base date on the recordपरिणामWork past its anniversaryWork still inside the year
4

Apply the formula to the eligible amounts

मात्रा विवरण

Apply the factor to the eligible value, parcel by parcel where the contract uses more than one index, and keep the calculation visible: the base value, the two index readings, the factor and the result. Do not adjust an item that was already priced at a later reference month.

क्यों: Reajustamento is one of the few figures in a contract that both sides can compute independently and get the same answer to, which makes showing the workings a cheap way of removing the argument entirely. An amount presented without them is treated as a request rather than as an entitlement.

इनपुटWork past its anniversaryFactor between the two monthsपरिणामAdjustment amount per itemWorkings anybody can repeat
5

Record it as an adjustment, not as a new price

अतिरिक्त कार्य

Raise the reajustamento as its own entry against the contract, citing the clause and the index readings, and keep the original unit prices untouched underneath it. Do not fold the adjustment into the rates, and do not open a renegotiation of scope alongside it.

स्क्रीनशॉट, चरण 5: Record it as an adjustment, not as a new price (अतिरिक्त कार्य, ब्राज़ीलियाई अनुबंध पर वार्षिक reajustamento लागू करें)
अतिरिक्त कार्य: Record it as an adjustment, not as a new price

क्यों: An adjustment the contract already provides for is recorded by administrative note, while a change to the price itself is an amendment with a different approval path and a different audit reading. Folding it into the rates loses that distinction, and it also destroys the base the next annual adjustment has to be computed from.

इनपुटAdjustment amount per itemClause that provides for itपरिणामAdjustment recorded as its own lineApproval trail attached
6

Carry it into the accounts and set the next date

फ़ाइनेंस

Put the adjustment through with the medicao it belongs to so the invoice and the contract record hold the same figure, and set the next anniversary as a dated item somebody owns before you close the file.

स्क्रीनशॉट, चरण 6: Carry it into the accounts and set the next date (फ़ाइनेंस, ब्राज़ीलियाई अनुबंध पर वार्षिक reajustamento लागू करें)
फ़ाइनेंस: Carry it into the accounts and set the next date

क्यों: The second year is the one that gets missed, because the first was prompted by somebody noticing. On a four year contract that is three quarters of the entitlement, and it is not recoverable later by arithmetic alone, since the periods it belonged to have been invoiced and settled at the old prices.

इनपुटAdjustment recorded as its own lineMedicao for the periodपरिणामAdjustment carried to invoiceNext anniversary on the calendar
मॉड्यूल

इस प्लेबुक के मॉड्यूल

प्लेटफ़ॉर्म के 190 में से 6 मॉड्यूल

The market this case is written for

ब्राज़ील

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

वाणिज्यिक और अनुबंध में और देखें

वाणिज्यिक और अनुबंध

उपठेकेदार पैकेज चलाएँ

किसी उपठेकेदार को एक ट्रेड पैकेज दें, इसे मूल्यों की अनुसूची और रिटेंशन के साथ एक उपअनुबंध प…

3 चरण11 मिनटखोलें
वाणिज्यिक और अनुबंध

भुगतान आवेदन और मिलान

इस अवधि में किए गए काम का अनुबंध के अनुसार मूल्यांकन करें, इसके पीछे के प्रमाण के साथ आवेदन…

3 चरण12 मिनटखोलें