Tillämpa den årliga reajustamento på ett brasilianskt kontrakt

Läs ut index, data-base och periodicitet ur kontraktet, ladda den publicerade serien, hitta det arbete vars årsdag har passerat, tillämpa formeln och registrera resultatet som en justering förd in i redovisningen.

6 steg15 minGeneralentreprenörSpecialunderentreprenörByggherre / beställare

Så fungerar det, steg för steg

6 steg genom plattformen - vad du gör i varje och varför det spelar roll.

1

Read the index and the data-base out of the contract

Kontrakt

Record three things from the contract itself: which index applies, and to which parcels of the work if there is more than one, what date the prices are referred to, and how the periodicity is counted. Note whether the data-base is the date of the proposal or the reference month of the orcamento, because they are often different.

Skärmbild, steg 1: Read the index and the data-base out of the contract (Kontrakt, Tillämpa den årliga reajustamento på ett brasilianskt kontrakt)
Kontrakt: Read the index and the data-base out of the contract

Varför: Lei 14.133 of 2021 requires the contract to state the criterion, the index and the date, and Lei 10.192 of 2001 fixes the periodicity at one year, so all three facts already exist and none of them is negotiable. What is negotiable is which of two plausible dates the parties meant, and settling that at the start of the contract costs a sentence rather than a claim.

IndataSigned contract termsEdital and its annexesResultatIndex named by the contractData-base date on the record
2

Load the index the contract names, not the one you follow

Prisindex

Load the published series for the named index, month by month, from the data-base to the month of application, and compute the factor between the two. Where the contract splits the work between several indices, load each one and keep the parcels apart.

Skärmbild, steg 2: Load the index the contract names, not the one you follow (Prisindex, Tillämpa den årliga reajustamento på ett brasilianskt kontrakt)
Prisindex: Load the index the contract names, not the one you follow

Varför: A construction cost index and a general price index diverge by several points a year, which on a long contract is the whole margin. Using the one you normally follow rather than the one the contract names produces a number that is defensible in every way except the one that matters, and the correction lands after the invoice is out.

IndataIndex named by the contractPublished index seriesResultatIndex series loaded by monthFactor between the two months
3

Find the work whose anniversary has passed

Framdrift

Split the measured work by the period it was executed in and separate what falls after the first anniversary of the data-base from what falls before it. Keep the two lists rather than applying an average to everything.

Skärmbild, steg 3: Find the work whose anniversary has passed (Framdrift, Tillämpa den årliga reajustamento på ett brasilianskt kontrakt)
Framdrift: Find the work whose anniversary has passed

Varför: The periodicity is annual under Lei 10.192 of 2001, so work executed inside the first year is not adjusted at all and work executed afterwards is adjusted by the factor for its own month. An average applied to the whole contract overpays one half and underpays the other, and it is the overpaid half that gets questioned.

IndataWork measured to dateData-base date on the recordResultatWork past its anniversaryWork still inside the year
4

Apply the formula to the eligible amounts

Mängdförteckning

Apply the factor to the eligible value, parcel by parcel where the contract uses more than one index, and keep the calculation visible: the base value, the two index readings, the factor and the result. Do not adjust an item that was already priced at a later reference month.

Varför: Reajustamento is one of the few figures in a contract that both sides can compute independently and get the same answer to, which makes showing the workings a cheap way of removing the argument entirely. An amount presented without them is treated as a request rather than as an entitlement.

IndataWork past its anniversaryFactor between the two monthsResultatAdjustment amount per itemWorkings anybody can repeat
5

Record it as an adjustment, not as a new price

Ändringsorder

Raise the reajustamento as its own entry against the contract, citing the clause and the index readings, and keep the original unit prices untouched underneath it. Do not fold the adjustment into the rates, and do not open a renegotiation of scope alongside it.

Skärmbild, steg 5: Record it as an adjustment, not as a new price (Ändringsorder, Tillämpa den årliga reajustamento på ett brasilianskt kontrakt)
Ändringsorder: Record it as an adjustment, not as a new price

Varför: An adjustment the contract already provides for is recorded by administrative note, while a change to the price itself is an amendment with a different approval path and a different audit reading. Folding it into the rates loses that distinction, and it also destroys the base the next annual adjustment has to be computed from.

IndataAdjustment amount per itemClause that provides for itResultatAdjustment recorded as its own lineApproval trail attached
6

Carry it into the accounts and set the next date

Ekonomi

Put the adjustment through with the medicao it belongs to so the invoice and the contract record hold the same figure, and set the next anniversary as a dated item somebody owns before you close the file.

Skärmbild, steg 6: Carry it into the accounts and set the next date (Ekonomi, Tillämpa den årliga reajustamento på ett brasilianskt kontrakt)
Ekonomi: Carry it into the accounts and set the next date

Varför: The second year is the one that gets missed, because the first was prompted by somebody noticing. On a four year contract that is three quarters of the entitlement, and it is not recoverable later by arithmetic alone, since the periods it belonged to have been invoiced and settled at the old prices.

IndataAdjustment recorded as its own lineMedicao for the periodResultatAdjustment carried to invoiceNext anniversary on the calendar
Moduler

Moduler i denna playbook

6 / 190 plattformsmoduler

The market this case is written for

Brasilien

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mer inom Kommersiellt och kontrakt

Kommersiellt och kontrakt

Driv ett underentreprenadpaket

Tilldela ett entreprenadpaket till en underentreprenör, sätt det på ett underentreprenadkont…

3 steg11 minÖppna
Kommersiellt och kontrakt

Fakturaunderlag och avstämning

Värdera arbetet som utförts under perioden mot kontraktet, skapa fakturaunderlaget med under…

3 steg12 minÖppna