对巴西合同适用年度reajustamento

从合同中读出指数、data-base和周期,加载已公布的数列,找出周年已过的工程,套用公式,并把结果作为记入账目的调整予以记录。

6 个步骤15 分钟总承包商专业分包商开发商/业主

运作方式,逐步说明

贯穿平台的 6 个步骤 - 每一步做什么,以及为什么重要。

1

Read the index and the data-base out of the contract

合同

Record three things from the contract itself: which index applies, and to which parcels of the work if there is more than one, what date the prices are referred to, and how the periodicity is counted. Note whether the data-base is the date of the proposal or the reference month of the orcamento, because they are often different.

原因: Lei 14.133 of 2021 requires the contract to state the criterion, the index and the date, and Lei 10.192 of 2001 fixes the periodicity at one year, so all three facts already exist and none of them is negotiable. What is negotiable is which of two plausible dates the parties meant, and settling that at the start of the contract costs a sentence rather than a claim.

输入Signed contract termsEdital and its annexes成果Index named by the contractData-base date on the record
2

Load the index the contract names, not the one you follow

价格指数

Load the published series for the named index, month by month, from the data-base to the month of application, and compute the factor between the two. Where the contract splits the work between several indices, load each one and keep the parcels apart.

原因: A construction cost index and a general price index diverge by several points a year, which on a long contract is the whole margin. Using the one you normally follow rather than the one the contract names produces a number that is defensible in every way except the one that matters, and the correction lands after the invoice is out.

输入Index named by the contractPublished index series成果Index series loaded by monthFactor between the two months
3

Find the work whose anniversary has passed

进度

Split the measured work by the period it was executed in and separate what falls after the first anniversary of the data-base from what falls before it. Keep the two lists rather than applying an average to everything.

原因: The periodicity is annual under Lei 10.192 of 2001, so work executed inside the first year is not adjusted at all and work executed afterwards is adjusted by the factor for its own month. An average applied to the whole contract overpays one half and underpays the other, and it is the overpaid half that gets questioned.

输入Work measured to dateData-base date on the record成果Work past its anniversaryWork still inside the year
4

Apply the formula to the eligible amounts

工程量清单

Apply the factor to the eligible value, parcel by parcel where the contract uses more than one index, and keep the calculation visible: the base value, the two index readings, the factor and the result. Do not adjust an item that was already priced at a later reference month.

原因: Reajustamento is one of the few figures in a contract that both sides can compute independently and get the same answer to, which makes showing the workings a cheap way of removing the argument entirely. An amount presented without them is treated as a request rather than as an entitlement.

输入Work past its anniversaryFactor between the two months成果Adjustment amount per itemWorkings anybody can repeat
5

Record it as an adjustment, not as a new price

变更增项

Raise the reajustamento as its own entry against the contract, citing the clause and the index readings, and keep the original unit prices untouched underneath it. Do not fold the adjustment into the rates, and do not open a renegotiation of scope alongside it.

原因: An adjustment the contract already provides for is recorded by administrative note, while a change to the price itself is an amendment with a different approval path and a different audit reading. Folding it into the rates loses that distinction, and it also destroys the base the next annual adjustment has to be computed from.

输入Adjustment amount per itemClause that provides for it成果Adjustment recorded as its own lineApproval trail attached
6

Carry it into the accounts and set the next date

财务

Put the adjustment through with the medicao it belongs to so the invoice and the contract record hold the same figure, and set the next anniversary as a dated item somebody owns before you close the file.

原因: The second year is the one that gets missed, because the first was prompted by somebody noticing. On a four year contract that is three quarters of the entitlement, and it is not recoverable later by arithmetic alone, since the periods it belonged to have been invoiced and settled at the old prices.

输入Adjustment recorded as its own lineMedicao for the period成果Adjustment carried to invoiceNext anniversary on the calendar
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

巴西

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 商务与合同 案例

商务与合同

把变更转化为已付款的变更单

在范围变更还新鲜时就记录下来,依据你已约定的单价将其作为合同变更报价,并在下一期进度付款申请中计入,使额外工作能够获得补偿,而不是被悄悄吸收。

3 个步骤11 分钟打开
商务与合同

管理分包工程

将某工种分包给分包商,以带付款计划表和保留金条款的分包合同确定下来,再按实际完成的工作逐期支付款项。

3 个步骤11 分钟打开
商务与合同

付款申请与对账

按合同对本期已完成工作进行估值,附上依据提出申请,并将已核证的金额与账户实际到账的金额进行对账。

3 个步骤12 分钟打开