Aplicar el reajustamento anual a un contrato brasileño

Lea el índice, la data-base y la periodicidad en el contrato, cargue la serie publicada, encuentre el trabajo cuyo aniversario ya pasó, aplique la fórmula, y registre el resultado como un ajuste llevado a la cuenta.

6 pasos15 minContratista generalSubcontratista especialistaPromotor / cliente

Cómo funciona, paso a paso

6 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Read the index and the data-base out of the contract

Contratos

Record three things from the contract itself: which index applies, and to which parcels of the work if there is more than one, what date the prices are referred to, and how the periodicity is counted. Note whether the data-base is the date of the proposal or the reference month of the orcamento, because they are often different.

Por que: Lei 14.133 of 2021 requires the contract to state the criterion, the index and the date, and Lei 10.192 of 2001 fixes the periodicity at one year, so all three facts already exist and none of them is negotiable. What is negotiable is which of two plausible dates the parties meant, and settling that at the start of the contract costs a sentence rather than a claim.

EntradaSigned contract termsEdital and its annexesResultadoIndex named by the contractData-base date on the record
2

Load the index the contract names, not the one you follow

Índice de precios

Load the published series for the named index, month by month, from the data-base to the month of application, and compute the factor between the two. Where the contract splits the work between several indices, load each one and keep the parcels apart.

Por que: A construction cost index and a general price index diverge by several points a year, which on a long contract is the whole margin. Using the one you normally follow rather than the one the contract names produces a number that is defensible in every way except the one that matters, and the correction lands after the invoice is out.

EntradaIndex named by the contractPublished index seriesResultadoIndex series loaded by monthFactor between the two months
3

Find the work whose anniversary has passed

Avance

Split the measured work by the period it was executed in and separate what falls after the first anniversary of the data-base from what falls before it. Keep the two lists rather than applying an average to everything.

Por que: The periodicity is annual under Lei 10.192 of 2001, so work executed inside the first year is not adjusted at all and work executed afterwards is adjusted by the factor for its own month. An average applied to the whole contract overpays one half and underpays the other, and it is the overpaid half that gets questioned.

EntradaWork measured to dateData-base date on the recordResultadoWork past its anniversaryWork still inside the year
4

Apply the formula to the eligible amounts

Presupuesto

Apply the factor to the eligible value, parcel by parcel where the contract uses more than one index, and keep the calculation visible: the base value, the two index readings, the factor and the result. Do not adjust an item that was already priced at a later reference month.

Por que: Reajustamento is one of the few figures in a contract that both sides can compute independently and get the same answer to, which makes showing the workings a cheap way of removing the argument entirely. An amount presented without them is treated as a request rather than as an entitlement.

EntradaWork past its anniversaryFactor between the two monthsResultadoAdjustment amount per itemWorkings anybody can repeat
5

Record it as an adjustment, not as a new price

Modificaciones

Raise the reajustamento as its own entry against the contract, citing the clause and the index readings, and keep the original unit prices untouched underneath it. Do not fold the adjustment into the rates, and do not open a renegotiation of scope alongside it.

Por que: An adjustment the contract already provides for is recorded by administrative note, while a change to the price itself is an amendment with a different approval path and a different audit reading. Folding it into the rates loses that distinction, and it also destroys the base the next annual adjustment has to be computed from.

EntradaAdjustment amount per itemClause that provides for itResultadoAdjustment recorded as its own lineApproval trail attached
6

Carry it into the accounts and set the next date

Finanzas

Put the adjustment through with the medicao it belongs to so the invoice and the contract record hold the same figure, and set the next anniversary as a dated item somebody owns before you close the file.

Por que: The second year is the one that gets missed, because the first was prompted by somebody noticing. On a four year contract that is three quarters of the entitlement, and it is not recoverable later by arithmetic alone, since the periods it belonged to have been invoiced and settled at the old prices.

EntradaAdjustment recorded as its own lineMedicao for the periodResultadoAdjustment carried to invoiceNext anniversary on the calendar
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Brasil

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.