Zatražite extension of time prema AS 4000

Dajte obavijest o kašnjenju čim se uzrok pojavi, bilježite kašnjenje dan po dan dok traje, prikažite ga na dinamičkom planu umjesto da ga tvrdite, podnesite claim unutar roka koji klauzula dopušta, cijenite troškove kašnjenja zasebno, i zabilježite novi datum za practical completion.

7 koraka18 minGlavni izvođačSpecijalizirani podizvođačUred za upravljanje projektima / gradnjomKonzalting za troškove / QS

Kako funkcionira, korak po korak

7 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Give the notice of delay as soon as the cause appears

Dopisivanje

Send the notice as soon as you become aware of anything likely to delay the work, naming the cause and its likely effect, addressed to the Superintendent and recorded in the correspondence register with the date and the way it was sent. Do not wait until the delay can be quantified.

Snimka zaslona, korak 1: Give the notice of delay as soon as the cause appears (Dopisivanje, Zatražite extension of time prema AS 4000)
Dopisivanje: Give the notice of delay as soon as the cause appears

Zašto: The early notice exists so the Superintendent can do something about the cause while it is still cheap, which is why the clause asks for it before anyone knows how long the delay will be. A notice sent when the contractor finally has the numbers is a notice sent after the only moment it could have been acted on, and it invites the answer that the delay could have been mitigated.

UlazEvent likely to cause delayDate you became awareRezultatNotice of delay servedDate and manner of service
2

Record the delay while it is happening

Dnevnik gradilišta

Keep the daily record through the delay: which activities could not proceed, which crews and plant were standing, what work was moved forward instead, and the weather where the claim is a wet weather claim. Record the days the site could not work, not just the days it rained.

Snimka zaslona, korak 2: Record the delay while it is happening (Dnevnik gradilišta, Zatražite extension of time prema AS 4000)
Dnevnik gradilišta: Record the delay while it is happening

Zašto: A wet weather claim is refused more often for measuring the wrong thing than for being untrue. Rainfall from the nearest station proves it rained; the diary proves the excavation could not be worked, which is the fact the claim is actually about, and it can only be written on the day.

UlazWhat happened on site each dayWeather and lost daysRezultatDay by day recordResources standing by
3

Show the delay on the programme, not in a sentence

4D raspored

Take the programme as it stood before the event, insert the delay where it actually landed, and read off what it does to the critical path and to the date for practical completion. Keep both versions so the difference between them is the claim.

Snimka zaslona, korak 3: Show the delay on the programme, not in a sentence (4D raspored, Zatražite extension of time prema AS 4000)
4D raspored: Show the delay on the programme, not in a sentence

Zašto: An extension is owed for delay to the work as a whole, so a fortnight lost on an activity carrying three weeks of float earns nothing however real the disruption was. The programme is the only place that distinction can be shown, and showing it is also the fastest way to find out that a claim you were about to spend a month on is not there.

UlazProgramme before the delayDay by day recordRezultatDelay shown on the programmeEffect on the critical path
4

Lodge the claim with the cause tied to the effect

Dokazi zahtjeva

Assemble the claim as one pack: the qualifying cause, the facts that establish it, the programme showing what it delayed and the number of days sought. Under AS 4000 the claim must be made within twenty eight days of when the contractor should reasonably have become aware of the causation of the delay, and the Annexure can make that period shorter.

Snimka zaslona, korak 4: Lodge the claim with the cause tied to the effect (Dokazi zahtjeva, Zatražite extension of time prema AS 4000)
Dokazi zahtjeva: Lodge the claim with the cause tied to the effect

Zašto: Assessors reject extension claims on the join rather than on the parts. A cause everyone accepts and a programme everyone accepts still fail when nothing in between says which activity this event stopped on which day. Assembling the pack in one place is what forces that link to be made while the evidence to make it still exists.

UlazDelay shown on the programmeRecords supporting the causeRezultatExtension of time claimCause, effect and evidence together
5

Watch the windows the clause and the Annexure set

Rokovi

Put the claim window and the period the Superintendent has to assess it under watch, taking the lengths from the Annexure rather than from the printed default, and let each one warn before it lands.

Zašto: Both sides of this clause run on dates that nobody rereads once the job is busy. A claim lodged a day late is barred, and a Superintendent who lets the assessment period pass without a decision leaves the contractor an argument it would not otherwise have had. Either way the date decides, and the date is in the Annexure.

UlazExtension of time claimPeriods from the AnnexureRezultatClaim and response dates watchedWarning before each date
6

Price the time separately from the entitlement to it

Financije

Work out what the extended period costs from the time related preliminaries the job actually carries, site staff, accommodation, standing plant, scaffold hire and site running costs, and separate the days that carry delay damages from the days that only move the date.

Snimka zaslona, korak 6: Price the time separately from the entitlement to it (Financije, Zatražite extension of time prema AS 4000)
Financije: Price the time separately from the entitlement to it

Zašto: An extension of time protects the contractor from liquidated damages and does not, by itself, pay for anything. Whether the days are also compensable depends on which cause they came from, so a claim that runs the two together invites a refusal of both, and a contractor who assumed the time came with money has already spent it.

UlazDays of extension grantedTime related site costsRezultatDelay costs pricedCompensable time separated
7

Record the new date everything else counts from

Ugovori

Post the determination against the contract so the date for practical completion moves, and keep the trail of the days claimed, the days granted and the days still in dispute beside it.

Snimka zaslona, korak 7: Record the new date everything else counts from (Ugovori, Zatražite extension of time prema AS 4000)
Ugovori: Record the new date everything else counts from

Zašto: The date for practical completion is the date liquidated damages run from, the date the defects liability period is measured from and the date the security reduction hangs on, so an extension that is granted and never recorded leaves three other things wrong. It is also the number a principal will assume was never granted once the people who remember have left the job.

UlazSuperintendent's determinationDate for practical completionRezultatNew date on the contractLiquidated damages reset
Moduli

Moduli u ovom playbooku

7 / 190 modula platforme

The market this case is written for

Australija

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Više u kategoriji Planiranje i kontrola

Planiranje i kontrola

Izradite osnovu i pratite napredak

Isplanirajte terminski plan, zamrznite osnovu za usporedbu, unesite stvarni napredak s gradi…

4 koraka12 minOtvori
Planiranje i kontrola

Ostvarena vrijednost i prognoza

Vidite gdje se posao stvarno nalazi u odnosu na plan i proračun: ažurirajte terminski plan,…

3 koraka13 minOtvori