AS 4000에 따라 extension of time 청구하기

원인이 나타나는 즉시 지연 통지를 보내고, 지연이 발생하는 동안 하루하루 기록하고, 주장이 아니라 공정표에서 보여주고, 조항이 허용하는 기간 안에 claim을 제출하고, 지연 비용을 별도로 산정하고, practical completion의 새로운 날짜를 기록한다.

7단계18 분종합건설사전문건설사PM/CM 업체원가 컨설팅 / 적산 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Give the notice of delay as soon as the cause appears

서신

Send the notice as soon as you become aware of anything likely to delay the work, naming the cause and its likely effect, addressed to the Superintendent and recorded in the correspondence register with the date and the way it was sent. Do not wait until the delay can be quantified.

이유: The early notice exists so the Superintendent can do something about the cause while it is still cheap, which is why the clause asks for it before anyone knows how long the delay will be. A notice sent when the contractor finally has the numbers is a notice sent after the only moment it could have been acted on, and it invites the answer that the delay could have been mitigated.

입력Event likely to cause delayDate you became aware결과Notice of delay servedDate and manner of service
2

Record the delay while it is happening

현장 일지

Keep the daily record through the delay: which activities could not proceed, which crews and plant were standing, what work was moved forward instead, and the weather where the claim is a wet weather claim. Record the days the site could not work, not just the days it rained.

이유: A wet weather claim is refused more often for measuring the wrong thing than for being untrue. Rainfall from the nearest station proves it rained; the diary proves the excavation could not be worked, which is the fact the claim is actually about, and it can only be written on the day.

입력What happened on site each dayWeather and lost days결과Day by day recordResources standing by
3

Show the delay on the programme, not in a sentence

4D 일정

Take the programme as it stood before the event, insert the delay where it actually landed, and read off what it does to the critical path and to the date for practical completion. Keep both versions so the difference between them is the claim.

이유: An extension is owed for delay to the work as a whole, so a fortnight lost on an activity carrying three weeks of float earns nothing however real the disruption was. The programme is the only place that distinction can be shown, and showing it is also the fastest way to find out that a claim you were about to spend a month on is not there.

입력Programme before the delayDay by day record결과Delay shown on the programmeEffect on the critical path
4

Lodge the claim with the cause tied to the effect

클레임 증거

Assemble the claim as one pack: the qualifying cause, the facts that establish it, the programme showing what it delayed and the number of days sought. Under AS 4000 the claim must be made within twenty eight days of when the contractor should reasonably have become aware of the causation of the delay, and the Annexure can make that period shorter.

이유: Assessors reject extension claims on the join rather than on the parts. A cause everyone accepts and a programme everyone accepts still fail when nothing in between says which activity this event stopped on which day. Assembling the pack in one place is what forces that link to be made while the evidence to make it still exists.

입력Delay shown on the programmeRecords supporting the cause결과Extension of time claimCause, effect and evidence together
5

Watch the windows the clause and the Annexure set

마감일

Put the claim window and the period the Superintendent has to assess it under watch, taking the lengths from the Annexure rather than from the printed default, and let each one warn before it lands.

이유: Both sides of this clause run on dates that nobody rereads once the job is busy. A claim lodged a day late is barred, and a Superintendent who lets the assessment period pass without a decision leaves the contractor an argument it would not otherwise have had. Either way the date decides, and the date is in the Annexure.

입력Extension of time claimPeriods from the Annexure결과Claim and response dates watchedWarning before each date
6

Price the time separately from the entitlement to it

재무

Work out what the extended period costs from the time related preliminaries the job actually carries, site staff, accommodation, standing plant, scaffold hire and site running costs, and separate the days that carry delay damages from the days that only move the date.

이유: An extension of time protects the contractor from liquidated damages and does not, by itself, pay for anything. Whether the days are also compensable depends on which cause they came from, so a claim that runs the two together invites a refusal of both, and a contractor who assumed the time came with money has already spent it.

입력Days of extension grantedTime related site costs결과Delay costs pricedCompensable time separated
7

Record the new date everything else counts from

계약

Post the determination against the contract so the date for practical completion moves, and keep the trail of the days claimed, the days granted and the days still in dispute beside it.

이유: The date for practical completion is the date liquidated damages run from, the date the defects liability period is measured from and the date the security reduction hangs on, so an extension that is granted and never recorded leaves three other things wrong. It is also the number a principal will assume was never granted once the people who remember have left the job.

입력Superintendent's determinationDate for practical completion결과New date on the contractLiquidated damages reset
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 7

The market this case is written for

오스트레일리아

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

계획 및 관리 카테고리의 더 보기

계획 및 관리

프로젝트 설정 및 인도

프로젝트를 최초 설정부터 최종 인도까지 처리한다. 프로젝트를 생성하고, 공사비를 산정하며, 공정을 계획하고, 현장에서 진척을 관리한 후 깔끔하게 마무리한다. 전체 생…

5단계20 분열기
계획 및 관리

베이스라인 구축 및 진척 추적

공정표를 계획하고, 비교 기준이 될 베이스라인을 확정하고, 현장의 실제 진척을 반영한 뒤 편차를 확인하여 지연을 조기에 발견합니다.

4단계12 분열기
계획 및 관리

실적 가치 분석 및 예측

현장이 계획과 예산 대비 실제로 어디에 있는지 파악합니다. 공정표를 최신화하고, CPI와 SPI를 확인한 뒤, 준공 예상 비용과 예상 완료일에 신뢰할 수 있는 값을…