Scenariji / Procjena i troškovi
Procjena i troškovi

Preračunati smeta u baznim cijenama indeksom Minstroja

Zabilježite cjenovnu osnovicu i tromjesečje na koje se odnosi, unesite indeks objavljen za vašu regiju i vrstu gradnje, primijenite ga samo na stavke koje su ostale u baznim cijenama, i navedite u dokumentu koeficijent i njegov izvor.

6 koraka12 minKonzalting za troškove / QSGlavni izvođačInvestitor / naručitelj

Kako funkcionira, korak po korak

6 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Declare the price base and the date it belongs to

Troškovnik

Set the base date on the bill header, the 2001 base or the quarter of a current price base, so the estimate states which roubles it is in, and record the period you need the money brought to, the region and the type of construction in the basis of estimate beside it.

Snimka zaslona, korak 1: Declare the price base and the date it belongs to (Troškovnik, Preračunati smeta u baznim cijenama indeksom Minstroja)
Troškovnik: Declare the price base and the date it belongs to

Zašto: An index is a ratio between two periods and it means nothing without both of them. The base date on the bill is the price level validation reads, and a smeta that does not state it cannot be re-checked by anyone, including the person who wrote it six months later.

UlazSmeta in base pricesTarget quarterRezultatBase date on the billRegion and type of construction
2

Enter the index the Ministry published for the quarter

Indeks cijena

Create an index series for the recalculation index the Ministry of Construction published for your type of construction, with the quarter as the period and the published value as the factor, and where the publication splits the index by element make a series for each: one for construction and assembly work as a whole, and separate ones for labour, machine operation and materials. Put the region on the location factor and the publication reference in the series description.

Snimka zaslona, korak 2: Enter the index the Ministry published for the quarter (Indeks cijena, Preračunati smeta u baznim cijenama indeksom Minstroja)
Indeks cijena: Enter the index the Ministry published for the quarter

Zašto: One index for the whole smeta is the shortcut that costs most. Labour, machines and materials move at different speeds, and where the publication gives separate coefficients an expertise reviewer expects them applied separately. An index taken from a neighbouring region or from a different type of construction produces a defensible looking total that is simply the wrong one.

UlazIndex published for the quarterRegion and type of constructionRezultatCoefficients by elementPublication reference
3

Apply the factor only to what is still in base money

Indeks cijena

Run the escalation preview scoped to this project, from each rate's own price date to the target quarter, and read it line by line: the factor, the escalated rate and, for a rate the preview could not escalate, the note saying why. Then carry the escalated rates onto the positions still in base money yourself, leave anything already priced from a quotation or an invoice untouched, and keep the preview's list of what was left out.

Snimka zaslona, korak 3: Apply the factor only to what is still in base money (Indeks cijena, Preračunati smeta u baznim cijenama indeksom Minstroja)
Indeks cijena: Apply the factor only to what is still in base money

Zašto: Double indexing is the quiet error of this method: equipment bought on a current quotation, or a material priced from a real invoice, gets multiplied a second time by a coefficient built for base year money. The preview writes nothing to the bill, which is the point: the rate that reaches a position is one an estimator read and accepted, and the note on a rate with no price date is the exception list rather than a silent skip.

UlazPositions in base moneyCoefficients by elementRezultatEscalated rate per positionRates the preview could not escalate
4

Check what the coefficient should never have touched

Validacija

Run validation on the indexed bill and read what the Russian rules report: a bill with no base date declared, a line without a norm code or with one that is not in the base, a rate with no resources behind it, and any markup line whose base is not settled. Then go back to the preview's list for the positions the coefficient should not have touched, and clear both lists before the smeta leaves.

Snimka zaslona, korak 4: Check what the coefficient should never have touched (Validacija, Preračunati smeta u baznim cijenama indeksom Minstroja)
Validacija: Check what the coefficient should never have touched

Zašto: The arithmetic of indexing is trivial and always passes, so validation reads the document rather than the sum: whether it says which roubles it is in and whether every line can be traced to a published norm, which is what an expertise reviewer checks first. The positions indexed twice or priced from a quotation are not a rule's business, they are the preview's, and the two lists together are the whole check.

UlazIndexed smetaValidation rule setRezultatException listCorrections applied
5

Test the heaviest positions against a resource price

Preglednik troškova

Take the positions that carry most of the total, price a handful of them from resources at today's money, and compare the two answers. Record the gap and the reason for it, not only the number.

Zašto: This is the resource index method used as a check rather than as a method. An index describes an average, and the positions that dominate your total are the ones least likely to be average. Where the two answers diverge sharply you have found either a stale coefficient or a position built on the wrong norm, and both are far cheaper to find before the contract is signed.

UlazPositions carrying the costResource priced checkRezultatGap per positionReason on record
6

Show the coefficient and its source on the document

Izvješća

Issue the smeta with the base, the base date, the target quarter, the coefficient applied to each element and where it was published, printed on the face of the document rather than kept in a working file on somebody's machine.

Snimka zaslona, korak 6: Show the coefficient and its source on the document (Izvješća, Preračunati smeta u baznim cijenama indeksom Minstroja)
Izvješća: Show the coefficient and its source on the document

Zašto: The customer, the expertise reviewer and the auditor all check the same thing first: which coefficient was used and for which period. A smeta that carries that on its face is checked in minutes, one that does not comes back as a request for clarification and costs a full review cycle.

UlazChecked smetaIndex provenanceRezultatIssued smetaReproducible calculation trail
Moduli

Moduli u ovom playbooku

5 / 190 modula platforme

The market this case is written for

Rusija

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Više u kategoriji Procjena i troškovi

Procjena i troškovi

Provjerite ponudu prije slanja

Provedite izrađenu ponudu kroz pravila provjere, uklonite svako upozorenje i grešku, zatim i…

3 koraka8 minOtvori
Procjena i troškovi

Izradi procjenu iz baze troškova

Preuzmite cijenjene stavke iz stvarne baze troškova, izgradite troškovnik na temelju njih, o…

4 koraka12 minOtvori