Vérifier un devis avant de l'envoyer
Passez un bordereau chiffré dans les règles de validation, corrigez chaque avertissement et…
Consignez la base de prix et le trimestre auquel elle appartient, saisissez l'index publié pour votre région et votre type de construction, appliquez-le uniquement aux postes encore exprimés en monnaie de base, et indiquez le coefficient et sa source sur le document.
6 étapes à travers la plateforme - ce que vous faites à chacune et pourquoi c’est important.
Set the base date on the bill header, the 2001 base or the quarter of a current price base, so the estimate states which roubles it is in, and record the period you need the money brought to, the region and the type of construction in the basis of estimate beside it.

Pourquoi: An index is a ratio between two periods and it means nothing without both of them. The base date on the bill is the price level validation reads, and a smeta that does not state it cannot be re-checked by anyone, including the person who wrote it six months later.
Create an index series for the recalculation index the Ministry of Construction published for your type of construction, with the quarter as the period and the published value as the factor, and where the publication splits the index by element make a series for each: one for construction and assembly work as a whole, and separate ones for labour, machine operation and materials. Put the region on the location factor and the publication reference in the series description.

Pourquoi: One index for the whole smeta is the shortcut that costs most. Labour, machines and materials move at different speeds, and where the publication gives separate coefficients an expertise reviewer expects them applied separately. An index taken from a neighbouring region or from a different type of construction produces a defensible looking total that is simply the wrong one.
Run the escalation preview scoped to this project, from each rate's own price date to the target quarter, and read it line by line: the factor, the escalated rate and, for a rate the preview could not escalate, the note saying why. Then carry the escalated rates onto the positions still in base money yourself, leave anything already priced from a quotation or an invoice untouched, and keep the preview's list of what was left out.

Pourquoi: Double indexing is the quiet error of this method: equipment bought on a current quotation, or a material priced from a real invoice, gets multiplied a second time by a coefficient built for base year money. The preview writes nothing to the bill, which is the point: the rate that reaches a position is one an estimator read and accepted, and the note on a rate with no price date is the exception list rather than a silent skip.
Run validation on the indexed bill and read what the Russian rules report: a bill with no base date declared, a line without a norm code or with one that is not in the base, a rate with no resources behind it, and any markup line whose base is not settled. Then go back to the preview's list for the positions the coefficient should not have touched, and clear both lists before the smeta leaves.

Pourquoi: The arithmetic of indexing is trivial and always passes, so validation reads the document rather than the sum: whether it says which roubles it is in and whether every line can be traced to a published norm, which is what an expertise reviewer checks first. The positions indexed twice or priced from a quotation are not a rule's business, they are the preview's, and the two lists together are the whole check.
Take the positions that carry most of the total, price a handful of them from resources at today's money, and compare the two answers. Record the gap and the reason for it, not only the number.
Pourquoi: This is the resource index method used as a check rather than as a method. An index describes an average, and the positions that dominate your total are the ones least likely to be average. Where the two answers diverge sharply you have found either a stale coefficient or a position built on the wrong norm, and both are far cheaper to find before the contract is signed.
Issue the smeta with the base, the base date, the target quarter, the coefficient applied to each element and where it was published, printed on the face of the document rather than kept in a working file on somebody's machine.

Pourquoi: The customer, the expertise reviewer and the auditor all check the same thing first: which coefficient was used and for which period. A smeta that carries that on its face is checked in minutes, one that does not comes back as a request for clarification and costs a full review cycle.
5 / 190 modules de la plateforme
Tout dans ce cas suit la façon dont les travaux sont métrés, chiffrés et payés sur ce marché. Les formulaires, la décomposition des coûts et les règles de paiement sont ceux qui y sont utilisés, pas une version générique.
Normes qu’il suit
Vous n’avez rien de tout cela à paramétrer à la main. Au premier démarrage, la plateforme demande sur quel marché vous travaillez. Choisissez celui-ci et elle règle la langue de l’interface, charge la base de coûts correspondante, enregistre la classification des coûts et ajoute un projet d’exemple que vous pouvez ouvrir tout de suite.
Les contrôles propres à ce marché sont eux aussi fournis avec la plateforme. Une fois activés, un devis auquel il manque quelque chose que le marché attend est signalé pendant que vous y travaillez, et non après l’envoi de l’offre.
Passez un bordereau chiffré dans les règles de validation, corrigez chaque avertissement et…
Extraire des postes chiffrés d'une base de coûts réelle, construire le devis à partir d'eux,…
Transformer une estimation ponctuelle en fourchette, exécuter une simulation Monte Carlo sur…