Obračunajte predujam (avans) i oslobodite jamstveno zadržavanje

Zabilježite iznos avans i zadržanog sredstva prema ugovoru, proknjižite avans i porez na njega, prebijajte ga sa svakim aktom prema dogovorenom udjelu, vodite neto iznos za plaćanje prema zakonskom roku, oslobodite zadržano sredstvo po ispunjenju uvjeta i usuglasite završno stanje.

7 koraka13 minGlavni izvođačSpecijalizirani podizvođačInvestitor / naručitelj

Kako funkcionira, korak po korak

7 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Record the advance and the retention the contract sets

Ugovori

Take from the contract the size of the advance and what it may be spent on, the rate at which it is recovered from each act, the retention percentage, the event that releases it and how long it is held, together with any bank guarantee standing in place of either of them.

Snimka zaslona, korak 1: Record the advance and the retention the contract sets (Ugovori, Obračunajte predujam (avans) i oslobodite jamstveno zadržavanje)
Ugovori: Record the advance and the retention the contract sets

Zašto: These two terms are negotiated once and then govern every payment for years. A retention rate remembered wrongly is an error repeated monthly, and an advance recovery schedule that was never written down is how a contractor reaches the end of a job still owing an advance against acts that have all been paid in full.

UlazSigned contractBank guarantees heldRezultatAdvance and recovery rateRetention rate and release event
2

Book the advance and the document that goes with it

Financije

Raise the advance invoice with the schet-faktura on it and book the receipt as a payment against it, and where the contract restricts what the money may be spent on, keep that restriction with the contract record. The balance still to recover is not a figure the ledger carries: keep it as the running total you deduct from on each act, starting from the advance received.

Snimka zaslona, korak 2: Book the advance and the document that goes with it (Financije, Obračunajte predujam (avans) i oslobodite jamstveno zadržavanje)
Financije: Book the advance and the document that goes with it

Zašto: An advance is not revenue, it is money held against work not yet done, and the only figure that matters day to day is how much of it is still outstanding. On state contracts an advance is often ring-fenced to particular expenditure and monitored through the treasury, so spending it elsewhere is a breach quite apart from whether the work eventually gets done.

UlazAdvance receivedRestriction on its useRezultatAdvance on the ledgerBalance still to recover
3

Decide which NDS rate each document carries

Porezne stope

Set the rate that applies to the advance and to each act, and check which date decides it in each case: the day the advance was received for the advance, the day the work was accepted for the act. Keep the earlier rate available for documents that belong to an earlier period.

Snimka zaslona, korak 3: Decide which NDS rate each document carries (Porezne stope, Obračunajte predujam (avans) i oslobodite jamstveno zadržavanje)
Porezne stope: Decide which NDS rate each document carries

Zašto: The standard rate became 22 percent on 1 January 2026, having been 20 percent before that. A contract running across the change carries both, and the tax charged on an advance received at the old rate does not become the new rate because the act is signed later. A system that only knows today's rate will quietly restate history and put the return out.

UlazDate of receipt and of acceptanceRates by effective periodRezultatRate on each documentDeduction on the advance
4

Set the advance off against each act

Financije

For every certified act, enter the retention on the invoice so the claim carries gross, retention and net, deduct the agreed share of the advance from what you claim and say so on the invoice, so the gross value, each deduction and the net payable read from one document. Carry the remaining advance forward so the next act starts from it.

Snimka zaslona, korak 4: Set the advance off against each act (Financije, Obračunajte predujam (avans) i oslobodite jamstveno zadržavanje)
Financije: Set the advance off against each act

Zašto: The set-off is the reason both sides can reconcile at all, because the client's ledger has to show the advance shrinking at exactly the rate yours does. Where the two disagree it is almost always because one side applied the percentage to a different base, the gross act or the act after retention, and that gap grows quietly every single month.

UlazCertified act for the monthRecovery and retention ratesRezultatNet payableAdvance carried forward
5

Put the net payable on the clock

Sat plaćanja

Send the net figure with the documents that support it and let the payment term run from the event the contract or the law names, which is the signing of the acceptance document rather than the day you got round to issuing the invoice.

Zašto: The deductions do not move the due date. On work under 44-FZ payment falls due within seven working days of the acceptance document being signed and interest on delay runs at a statutory rate, so the day the clock starts is the difference between a claim you can put a number on and a complaint you cannot.

UlazNet payableEvent the term runs fromRezultatDue dateInterest if it is late
6

Release the retention when its trigger actually arrives

Zadržana sredstva

Track the accumulated retention against its release conditions, completion of the works, the end of the guarantee period, defects actually closed out, and release it against the condition that has been met rather than against a date somebody remembered.

Snimka zaslona, korak 6: Release the retention when its trigger actually arrives (Zadržana sredstva, Obračunajte predujam (avans) i oslobodite jamstveno zadržavanje)
Zadržana sredstva: Release the retention when its trigger actually arrives

Zašto: Retention is money already earned and held back, and it is the balance most often forgotten on a finished job, because by the time it falls due the project team has moved to the next one. The condition that releases it is usually not a date at all, it is the closing of the last defect, which means somebody has to still be watching.

UlazRetention accumulatedRelease conditionsRezultatRetention releasedAmount still held
7

Agree the closing balance with the other side

Plaćanja

Assemble the statement from the invoices and payments on this contract, acts certified, advance received and recovered, retention withheld and released, tax at each rate and every payment made, then set it against the figures the client is carrying and have the two sides agreed and signed.

Snimka zaslona, korak 7: Agree the closing balance with the other side (Plaćanja, Obračunajte predujam (avans) i oslobodite jamstveno zadržavanje)
Plaćanja: Agree the closing balance with the other side

Zašto: A signed akt sverki is what closes the contract as a financial matter, and it is the document any later dispute starts from. Left unagreed, the two ledgers stay a few percent apart for years, and the difference is usually one deduction taken on the wrong base far enough back that nobody can reconstruct which month it was.

UlazYour ledger for the contractClient's figuresRezultatSigned reconciliationAgreed closing balance
Moduli

Moduli u ovom playbooku

4 / 190 modula platforme

The market this case is written for

Rusija

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Više u kategoriji Komercijala i ugovori

Komercijala i ugovori

Vodite podizvođački paket

Dodijelite paket radova podizvođaču, sklopite podugovor s tabelarnim pregledom vrijednosti i…

3 koraka11 minOtvori
Komercijala i ugovori

Zahtjev za plaćanje i usklađivanje

Vrednujte radove izvedene u ovom razdoblju u odnosu na ugovor, podnesite zahtjev za plaćanje…

3 koraka12 minOtvori