حالات عملية / التجاري والعقود
التجاري والعقود

تسوية الدفعة المقدمة (avans) والإفراج عن ضمان الاحتجاز

سجّل الـ avans والمبلغ المحتجز كما يحددهما العقد، قيّد الـ avans وضريبته، اخصمه مقابل كل شهادة إنجاز بالمعدل المتفق عليه، أبقِ صافي المبلغ المستحق ضمن الجدول الزمني القانوني، أفرج عن المبلغ المحتجز عند تحقق شرطه، واتفق على الرصيد الختامي.

7 خطوة13 دقيقةمقاول عاممقاول باطن متخصصمطوّر / عميل

كيف يعمل، خطوة بخطوة

7 خطوات عبر المنصة - ما تفعله في كل منها ولماذا يهم.

1

Record the advance and the retention the contract sets

العقود

Take from the contract the size of the advance and what it may be spent on, the rate at which it is recovered from each act, the retention percentage, the event that releases it and how long it is held, together with any bank guarantee standing in place of either of them.

لقطة شاشة، الخطوة 1: Record the advance and the retention the contract sets (العقود, تسوية الدفعة المقدمة (avans) والإفراج عن ضمان الاحتجاز)
العقود: Record the advance and the retention the contract sets

لماذا: These two terms are negotiated once and then govern every payment for years. A retention rate remembered wrongly is an error repeated monthly, and an advance recovery schedule that was never written down is how a contractor reaches the end of a job still owing an advance against acts that have all been paid in full.

المدخلاتSigned contractBank guarantees heldالمخرجاتAdvance and recovery rateRetention rate and release event
2

Book the advance and the document that goes with it

المالية

Raise the advance invoice with the schet-faktura on it and book the receipt as a payment against it, and where the contract restricts what the money may be spent on, keep that restriction with the contract record. The balance still to recover is not a figure the ledger carries: keep it as the running total you deduct from on each act, starting from the advance received.

لقطة شاشة، الخطوة 2: Book the advance and the document that goes with it (المالية, تسوية الدفعة المقدمة (avans) والإفراج عن ضمان الاحتجاز)
المالية: Book the advance and the document that goes with it

لماذا: An advance is not revenue, it is money held against work not yet done, and the only figure that matters day to day is how much of it is still outstanding. On state contracts an advance is often ring-fenced to particular expenditure and monitored through the treasury, so spending it elsewhere is a breach quite apart from whether the work eventually gets done.

المدخلاتAdvance receivedRestriction on its useالمخرجاتAdvance on the ledgerBalance still to recover
3

Decide which NDS rate each document carries

معدلات الضريبة

Set the rate that applies to the advance and to each act, and check which date decides it in each case: the day the advance was received for the advance, the day the work was accepted for the act. Keep the earlier rate available for documents that belong to an earlier period.

لقطة شاشة، الخطوة 3: Decide which NDS rate each document carries (معدلات الضريبة, تسوية الدفعة المقدمة (avans) والإفراج عن ضمان الاحتجاز)
معدلات الضريبة: Decide which NDS rate each document carries

لماذا: The standard rate became 22 percent on 1 January 2026, having been 20 percent before that. A contract running across the change carries both, and the tax charged on an advance received at the old rate does not become the new rate because the act is signed later. A system that only knows today's rate will quietly restate history and put the return out.

المدخلاتDate of receipt and of acceptanceRates by effective periodالمخرجاتRate on each documentDeduction on the advance
4

Set the advance off against each act

المالية

For every certified act, enter the retention on the invoice so the claim carries gross, retention and net, deduct the agreed share of the advance from what you claim and say so on the invoice, so the gross value, each deduction and the net payable read from one document. Carry the remaining advance forward so the next act starts from it.

لقطة شاشة، الخطوة 4: Set the advance off against each act (المالية, تسوية الدفعة المقدمة (avans) والإفراج عن ضمان الاحتجاز)
المالية: Set the advance off against each act

لماذا: The set-off is the reason both sides can reconcile at all, because the client's ledger has to show the advance shrinking at exactly the rate yours does. Where the two disagree it is almost always because one side applied the percentage to a different base, the gross act or the act after retention, and that gap grows quietly every single month.

المدخلاتCertified act for the monthRecovery and retention ratesالمخرجاتNet payableAdvance carried forward
5

Put the net payable on the clock

ساعة الدفع

Send the net figure with the documents that support it and let the payment term run from the event the contract or the law names, which is the signing of the acceptance document rather than the day you got round to issuing the invoice.

لماذا: The deductions do not move the due date. On work under 44-FZ payment falls due within seven working days of the acceptance document being signed and interest on delay runs at a statutory rate, so the day the clock starts is the difference between a claim you can put a number on and a complaint you cannot.

المدخلاتNet payableEvent the term runs fromالمخرجاتDue dateInterest if it is late
6

Release the retention when its trigger actually arrives

المحتجزات

Track the accumulated retention against its release conditions, completion of the works, the end of the guarantee period, defects actually closed out, and release it against the condition that has been met rather than against a date somebody remembered.

لقطة شاشة، الخطوة 6: Release the retention when its trigger actually arrives (المحتجزات, تسوية الدفعة المقدمة (avans) والإفراج عن ضمان الاحتجاز)
المحتجزات: Release the retention when its trigger actually arrives

لماذا: Retention is money already earned and held back, and it is the balance most often forgotten on a finished job, because by the time it falls due the project team has moved to the next one. The condition that releases it is usually not a date at all, it is the closing of the last defect, which means somebody has to still be watching.

المدخلاتRetention accumulatedRelease conditionsالمخرجاتRetention releasedAmount still held
7

Agree the closing balance with the other side

المدفوعات

Assemble the statement from the invoices and payments on this contract, acts certified, advance received and recovered, retention withheld and released, tax at each rate and every payment made, then set it against the figures the client is carrying and have the two sides agreed and signed.

لقطة شاشة، الخطوة 7: Agree the closing balance with the other side (المدفوعات, تسوية الدفعة المقدمة (avans) والإفراج عن ضمان الاحتجاز)
المدفوعات: Agree the closing balance with the other side

لماذا: A signed akt sverki is what closes the contract as a financial matter, and it is the document any later dispute starts from. Left unagreed, the two ledgers stay a few percent apart for years, and the difference is usually one deduction taken on the wrong base far enough back that nobody can reconstruct which month it was.

المدخلاتYour ledger for the contractClient's figuresالمخرجاتSigned reconciliationAgreed closing balance
الوحدات

وحدات هذا الدليل

4 / 190 من وحدات المنصة

The market this case is written for

روسيا

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

المزيد في التجاري والعقود

التجاري والعقود

تحويل تغيير إلى أمر تغيير مدفوع

التقط تغيير النطاق وهو طازج، وسعّره كأمر تغيير تعاقدي على أسعارك المتفق عليها، وحاسب عليه في…

3 خطوة11 دقيقةفتح
التجاري والعقود

إدارة حزمة مقاول باطن

أرسِ حزمة تخصص على مقاول باطن، وضعها في عقد باطن بجدول قيم ومحتجزات، ثم اسددها مستخلصاً بعد…

3 خطوة11 دقيقةفتح
التجاري والعقود

مطالبة الدفع ومطابقتها

قيّم العمل المنفَّذ خلال هذه الفترة مقابل العقد، وقدّم المطالبة مدعومة بأدلّتها، وطابِق ما ا…

3 خطوة12 دقيقةفتح