ケース / 積算とコスト
積算とコスト

territorial authority 向けに development contributions を予算化する

議会の policy が測る方法で開発を記述し、土地価格が確定する前に査定された拠出金を feasibility に組み込み、policy が変わるリスクを織り込み、査定通知と異議申立てを処理し、その金額が建設費として読まれない場所に cost plan の中で配置し、各支払いの期限を把握する。

6ステップ14 分デベロッパー / 発注者コストコンサルティング会社 / 積算事務所プロジェクト / 施工管理会社

仕組みをステップごとに

プラットフォーム全体で6ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Describe the development the way the policy measures it

不動産開発

Restate the scheme in the units the council's policy counts in, usually household equivalent units or an equivalent measure per activity, split by the activities the policy charges for: water, wastewater, stormwater, transport, reserves and community infrastructure. Record the demand the site already carries, because a redevelopment is charged on the increase rather than on the whole.

スクリーンショット、ステップ 1: Describe the development the way the policy measures it (不動産開発, territorial authority 向けに development contributions を予算化する)
不動産開発: Describe the development the way the policy measures it

理由: The assessment is arithmetic once the units are agreed, so the units are the whole argument. A scheme described in the developer's language and assessed in the council's is a scheme whose figure nobody can reproduce, and the credit for existing demand is the single most commonly missed line, worth more than most of the details anybody spends time on.

入力Development schemeCouncil contributions policy出力Demand in the policy's own unitsCredit for existing demand
2

Put it in the feasibility before the land price is fixed

概算見積

Price the contribution into the early estimate as its own line, activity by activity, and read what it does to the residual land value. Do it at the point the scheme is still being sized, because the number moves with unit count and with the mix of activities rather than with the build cost.

理由: On a medium density scheme the contribution can be a substantial share of the total development cost and it lands before any revenue does. Discovered after the land is bought it comes straight off the margin, because the only remaining lever is the number of units, and that is the lever that changes the contribution too.

入力Demand in the policy's own unitsPolicy rates per unit出力Contribution in the feasibilityEffect on what the land is worth
3

Hold an allowance against the policy moving

引当金・予備費

Hold the contribution risk as a named allowance rather than inside a general contingency: the policy is reviewed on a cycle with the long-term plan, the rates move with it, and a project consented after a review is assessed on the rates in force at the time. Record what would release the allowance, which is usually the consent being lodged and assessed.

スクリーンショット、ステップ 3: Hold an allowance against the policy moving (引当金・予備費, territorial authority 向けに development contributions を予算化する)
引当金・予備費: Hold an allowance against the policy moving

理由: A long-dated scheme can cross a policy review between feasibility and consent, and the movement is a policy decision rather than market drift, so no cost index will predict it. Held as a named allowance it can be released deliberately when the assessment arrives; buried in contingency it is spent on something else long before the invoice comes.

入力Contribution in the feasibilityWhen the policy is next reviewed出力Allowance held against a policy changeWhat would release it
4

Read the assessment against your own calculation

やり取り

When the notice of assessment arrives, read it line by line against the calculation you made in the feasibility and settle a position: accept it, object to it inside the window the Act gives, or open a development agreement in which the works or the payment are agreed with the council instead. Keep the notice, the working and the reply together on the record.

スクリーンショット、ステップ 4: Read the assessment against your own calculation (やり取り, territorial authority 向けに development contributions を予算化する)
やり取り: Read the assessment against your own calculation

理由: An objection is heard by independent development contribution commissioners rather than by the council that made the assessment, which makes it a genuine route and not a complaint. It is also a route with a deadline, and it is argued on the grounds the Act allows, such as the assessment misdescribing the development or the policy having been applied incorrectly, so the work done at the scoping step is the evidence for it.

入力Notice of assessmentYour own calculation出力Accept, object or agreeCorrespondence on the record
5

Put it where nobody will read it as a build cost

Cost Explorer

Place the contribution in the cost plan as its own line under development costs rather than inside the infrastructure or external works packages, split by the activities the policy charges for. Keep it comparable across schemes so the cost per unit can be read from one project to the next.

理由: A contribution folded into external works distorts every rate benchmark the business keeps, and it does so silently, because the total still looks right. It also hides the one comparison that is genuinely useful to a developer, which is what different councils charge for the same building, and that comparison is a location decision rather than a design one.

入力Accept, object or agreeCost plan structure出力Contribution on its own lineComparable across schemes
6

Know what the council can withhold until it is paid

レポート

Report the contributions across the portfolio with the event that makes each one payable, which under the policy may be the resource consent, the building consent, the service connection or the certificate that lets a subdivision proceed, and with what the council may withhold until it is paid.

スクリーンショット、ステップ 6: Know what the council can withhold until it is paid (レポート, territorial authority 向けに development contributions を予算化する)
レポート: Know what the council can withhold until it is paid

理由: This is the step that turns a known cost into a programme risk. A council entitled to withhold a code compliance certificate or a water connection until the contribution is paid can stop a settlement date, and the money is usually wanted at exactly the point in a development when there is least of it. Read a quarter ahead it is a drawdown. Read on the day it is a delay.

入力Contribution on its own lineEvent that makes it payable出力When each payment falls dueWhat the council can withhold
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 6 個

The market this case is written for

ニュージーランド

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

積算とコストの他のケース

積算とコスト

送付前に見積を確認する

積算済みの内訳書を検証ルールにかけ、すべての警告とエラーを解消し、そのまま顧客に渡せるきれいなレポートを出力する。

3ステップ8 分開く
積算とコスト

コストデータベースから見積を作成する

実在のコストデータベースから積算項目を取り出して内訳書を組み立て、繰り返し使う積み上げをアセンブリにまとめ、入札額を確定する前にチェックを実行します。

4ステップ12 分開く
積算とコスト

コストリスクから予備費を設定する

単一値の見積を幅のある値に変え、本当に不確実性のある項目についてモンテカルロシミュレーションを実行し、P50からP90の分布を読み取り、行ごとに根拠を示せる予備費を設定します。

3ステップ11 分開く