Expand production norms into resource quantities

Take a production norm per unit, expand it across the takeoff quantity into labour, plant and material, roll the resources up by trade and carry the resourced rate into the bill.

4 алхам11 минЕрөнхий гүйцэтгэгчМэргэшсэн дэд гүйцэтгэгчӨртгийн зөвлөх / QS

Хэрхэн ажилладаг, алхам алхмаар

Платформ даяар 4 алхам - алхам бүрт юу хийх, яагаад чухал болохыг.

1

Pick the norm

Үйлдвэрлэлийн норм

Find the production norm that matches the work item and the conditions - the trade, the material, the difficulty - so the consumption per unit reflects how the job will really be built.

Яагаад: A norm chosen for the wrong conditions carries the error into every unit. Matching the norm to the actual work is where the accuracy of the whole build-up is won or lost.

ОролтWork itemNorm libraryҮр дүнChosen norm
2

Expand across the quantity

Үйлдвэрлэлийн норм

Multiply the norm by the takeoff quantity to explode the item into the hours of labour, hours of plant and units of material it will actually consume.

Яагаад: Seeing the raw resource demand, not just a rate, is what lets you sanity check it against your crews and plant. A rate hides an impossible labour figure; the expansion shows it.

ОролтChosen normTakeoff quantityҮр дүнLabour, plant, material
3

Roll it up by trade

Нөөцийн нэгтгэл

Gather the expanded resources across the whole bill into a summary by trade, so you can see total labour hours, plant hours and key material tonnages in one place.

Яагаад: The resource summary is the reality check on the price. It tells you whether the labour you have priced can be manned and whether the material order matches the estimate.

ОролтExpanded resourcesҮр дүнResources by trade
4

Carry the rate into the bill

Ажил материалын жагсаалт

Price the resources at your labour, plant and material rates and carry the resulting unit rate into the bill, where it stands on a build-up you can defend line by line.

Яагаад: A rate backed by a resource build-up survives scrutiny that a lump-sum guess does not. When a client challenges a price, you can open the norm and show exactly what it is made of.

ОролтResourced quantitiesResource ratesҮр дүнResourced unit rate