Expand production norms into resource quantities

Take a production norm per unit, expand it across the takeoff quantity into labour, plant and material, roll the resources up by trade and carry the resourced rate into the bill.

Шагов: 411 минГенеральный подрядчикСпециализированный субподрядчикСметный консультант / QS

Как это работает, шаг за шагом

4 шагов через всю платформу - что делать на каждом и почему это важно.

1

Pick the norm

Производственные нормы

Find the production norm that matches the work item and the conditions - the trade, the material, the difficulty - so the consumption per unit reflects how the job will really be built.

Зачем: A norm chosen for the wrong conditions carries the error into every unit. Matching the norm to the actual work is where the accuracy of the whole build-up is won or lost.

На входеWork itemNorm libraryНа выходеChosen norm
2

Expand across the quantity

Производственные нормы

Multiply the norm by the takeoff quantity to explode the item into the hours of labour, hours of plant and units of material it will actually consume.

Зачем: Seeing the raw resource demand, not just a rate, is what lets you sanity check it against your crews and plant. A rate hides an impossible labour figure; the expansion shows it.

На входеChosen normTakeoff quantityНа выходеLabour, plant, material
3

Roll it up by trade

Сводка по ресурсам

Gather the expanded resources across the whole bill into a summary by trade, so you can see total labour hours, plant hours and key material tonnages in one place.

Зачем: The resource summary is the reality check on the price. It tells you whether the labour you have priced can be manned and whether the material order matches the estimate.

На входеExpanded resourcesНа выходеResources by trade
4

Carry the rate into the bill

Ведомость объёмов работ

Price the resources at your labour, plant and material rates and carry the resulting unit rate into the bill, where it stands on a build-up you can defend line by line.

Зачем: A rate backed by a resource build-up survives scrutiny that a lump-sum guess does not. When a client challenges a price, you can open the norm and show exactly what it is made of.

На входеResourced quantitiesResource ratesНа выходеResourced unit rate