Expand production norms into resource quantities

Take a production norm per unit, expand it across the takeoff quantity into labour, plant and material, roll the resources up by trade and carry the resourced rate into the bill.

4 个步骤11 分钟总承包商专业分包商造价咨询 / 工料测量师

运作方式,逐步说明

贯穿平台的 4 个步骤 - 每一步做什么,以及为什么重要。

1

Pick the norm

生产定额

Find the production norm that matches the work item and the conditions - the trade, the material, the difficulty - so the consumption per unit reflects how the job will really be built.

原因: A norm chosen for the wrong conditions carries the error into every unit. Matching the norm to the actual work is where the accuracy of the whole build-up is won or lost.

输入Work itemNorm library成果Chosen norm
2

Expand across the quantity

生产定额

Multiply the norm by the takeoff quantity to explode the item into the hours of labour, hours of plant and units of material it will actually consume.

原因: Seeing the raw resource demand, not just a rate, is what lets you sanity check it against your crews and plant. A rate hides an impossible labour figure; the expansion shows it.

输入Chosen normTakeoff quantity成果Labour, plant, material
3

Roll it up by trade

资源汇总

Gather the expanded resources across the whole bill into a summary by trade, so you can see total labour hours, plant hours and key material tonnages in one place.

原因: The resource summary is the reality check on the price. It tells you whether the labour you have priced can be manned and whether the material order matches the estimate.

输入Expanded resources成果Resources by trade
4

Carry the rate into the bill

工程量清单

Price the resources at your labour, plant and material rates and carry the resulting unit rate into the bill, where it stands on a build-up you can defend line by line.

原因: A rate backed by a resource build-up survives scrutiny that a lump-sum guess does not. When a client challenges a price, you can open the norm and show exactly what it is made of.

输入Resourced quantitiesResource rates成果Resourced unit rate