Saudization ve local content kapsamında bir alt sözleşme paketleyin

İşleri paketlere bölün, ön yeterliliği yalnızca fiyata değil sınıflandırmaya, Saudization bandına ve local content'e göre yapın, eşiti eşitle karşılaştırın, her iki yükümlülüğü de alt sözleşmeye yazın ve fiilen ay ay teslim edileni belgeleyin.

7 adım18 dkAna yükleniciProje / inşaat yönetim bürosuUzman taşeron

Nasıl çalışır, adım adım

Platform genelinde 7 adım - her birinde ne yapacağınız ve neden önemli olduğu.

1

Break the works into packages that carry their own share

Tedarik

Split the works into procurement packages and give each one its share of what the main contract committed you to: the labour content, the local content percentage and the value it represents. Say which packages are labour heavy and which are supply heavy, because they carry the two obligations in opposite proportions.

Ekran görüntüsü, adım 1: Break the works into packages that carry their own share (Tedarik, Saudization ve local content kapsamında bir alt sözleşme paketleyin)
Tedarik: Break the works into packages that carry their own share

Neden: A commitment held only at project level is one nobody can be held to. Split across packages, each buyer knows the number their package has to deliver and can see at award whether they have bought it. A local content target that arrives at the end as a single project percentage is a target that gets discovered as a shortfall when there is nothing left to buy.

GirdiWorks scopeMain contract obligationsÇıktıPackage breakdownTarget per package
2

Prequalify on the things that can stop the work

Alt Yüklenici Dizini

Check each candidate on the record rather than on the reference: contractor classification in the field and activity the package needs, current commercial registration, zakat, tax and social insurance certificates, the Nitaqat band, and the local content certificate with the percentage it actually states.

Ekran görüntüsü, adım 2: Prequalify on the things that can stop the work (Alt Yüklenici Dizini, Saudization ve local content kapsamında bir alt sözleşme paketleyin)
Alt Yüklenici Dizini: Prequalify on the things that can stop the work

Neden: The band is the one people skip because it looks like the subcontractor's own business. It is not. A firm in the red band cannot renew work permits or transfer workers in, so the crew it promised for month four is a crew it has no lawful way to assemble. Reading the band at prequalification is how you find that out while there is still another bidder.

GirdiCandidate subcontractorsPrequalification criteriaÇıktıApproved bidder listCertificates on file
3

Enquire so the answers can be compared

İhale

Send one enquiry with one bill, and require each bidder to state the same things beside the price: the local content he will deliver and how it is made up, the crew he will staff the package with, and where that labour comes from. Compare the returns on those columns as well as on the total.

Ekran görüntüsü, adım 3: Enquire so the answers can be compared (İhale, Saudization ve local content kapsamında bir alt sözleşme paketleyin)
İhale: Enquire so the answers can be compared

Neden: Priced against a common bill, the cheapest number is a fact. Priced against three different assumptions about who supplies the labour, it is a guess. Asking for the local content composition at enquiry also does something the award cannot: it lets you see which bidder has thought about it, because the one who has will answer with named suppliers and the one who has not will answer with a percentage.

GirdiApproved bidder listPackage documentsÇıktıComparable quotationsComparison on one basis
4

Write both obligations into the subcontract

Sözleşmeler

Draw the subcontract with the commitments as terms rather than as expectations: the local content percentage and how it will be evidenced, wage protection compliance as a condition of payment, the obligation to keep the classification and the certificates current, and notice to you if the band changes.

Ekran görüntüsü, adım 4: Write both obligations into the subcontract (Sözleşmeler, Saudization ve local content kapsamında bir alt sözleşme paketleyin)
Sözleşmeler: Write both obligations into the subcontract

Neden: You are answerable to the employer for numbers you do not control. Where the obligation is written down, a shortfall is a breach with a remedy attached and the conversation happens in month three. Where it is not, the first anybody hears of it is your own report to the client, and by then the only remedy left is to explain.

GirdiAward decisionCommitments made at tenderÇıktıSubcontract executedObligations written in
5

Watch the certificates and the band, because both move

Son tarihler

Register the expiry of every certificate you prequalified on and re-check the band at agreed points through the package rather than only at award. Ask for the evidence again before each milestone payment, not because the subcontractor is suspected but because a band is a moving measurement.

Neden: A band is recalculated as the workforce changes, so a subcontractor who was green at award can be red by the time he mobilises without having done anything visible. Since April 2026 an employment contract that is not documented electronically on the labour platform stops counting toward the percentage, which means a firm can slip a band through paperwork alone.

GirdiSubcontractor certificatesBands at awardÇıktıRenewal registerSlippage caught early
6

Evidence what was delivered, not what was promised

Raporlar

Build the local content position from the spend that actually went out, supplier by supplier, with the certificate or declaration behind each line, and report it against what was committed. Where the job also reports under the in-Kingdom total value add programme of an operator, keep that measurement separate rather than reusing the government figure, because the two methodologies are not the same.

Ekran görüntüsü, adım 6: Evidence what was delivered, not what was promised (Raporlar, Saudization ve local content kapsamında bir alt sözleşme paketleyin)
Raporlar: Evidence what was delivered, not what was promised

Neden: Local content is audited against invoices, so a figure assembled from intentions does not survive the first sample. Keeping the two schemes apart matters just as much: they are administered by different bodies, measured on different rules and reported on different platforms, and a contractor who submits one authority's number to the other has filed something he cannot support.

GirdiSpend by supplierSupplier declarationsÇıktıLocal content deliveredVariance against commitment
7

Certify against the evidence the subcontract asked for

Finans

Value the subcontractor's work as measured and check the conditions the subcontract attached to payment before certifying: wage compliance evidence for the period, the certificates still current, the local content return submitted. Where something is withheld, state which term it is withheld under and what would release it.

Ekran görüntüsü, adım 7: Certify against the evidence the subcontract asked for (Finans, Saudization ve local content kapsamında bir alt sözleşme paketleyin)
Finans: Certify against the evidence the subcontract asked for

Neden: A condition nobody checks is a condition that was never agreed. Checking it at each valuation is also fairer than the alternative, which is a large deduction at the end for months of small omissions nobody mentioned. A withholding that names its clause and its cure gets fixed. One that just appears becomes a dispute about the deduction rather than about the obligation.

GirdiSubcontractor applicationCompliance evidenceÇıktıPayment certifiedAmounts withheld with a reason
Modüller

Bu senaryodaki modüller

7 / 190 platform modülü

The market this case is written for

Suudi Arabistan

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.