SINAPI tabanından orçamento de referência'yı fiyatlandır

Referans ay için SINAPI'yi yükleyin, orçamento'nun her kalemini kodunla eşleştirin, her birim maliyeti kararnamenin izin verdiği medyanda tutun ve SINAPI'nin taşımadığı kalemler için maliyetin nereden geldiğini kaydedin.

6 adım18 dkMaliyet danışmanlığı / QSAna yükleniciGeliştirici / işveren

Nasıl çalışır, adım adım

Platform genelinde 6 adım - her birinde ne yapacağınız ve neden önemli olduğu.

1

Bring in SINAPI for the state and the reference month

Maliyet Veritabanı

Load the SINAPI tables into the cost database for the state the work is in and the reference month the edital names, and keep the two on the record beside the prices. Load the encargos sociais table that goes with the same month rather than one you already had.

Neden: A SINAPI price without its state and its reference month is not a reference, it is a number. Every argument about the orcamento de referencia begins by agreeing which table both sides are reading, and that agreement is free now and costs a week once the proposals are in.

GirdiSINAPI reference pricesReference date the edital namesÇıktıPriced reference base loadedState and reference month recorded
2

Map every item of the orcamento to its SINAPI code

Keşif Özeti

Put the SINAPI code on each position of the bill and check that the code's description, its unit and its scope really are what your item measures. Where a position is served by two codes that differ only in a detail of the method, pick the one the design specifies and say so. Collect the items no code fits rather than forcing them onto the nearest one.

Neden: The code carries the composicao behind the price, so a code chosen for its description alone imports a productivity and a set of insumos nobody read. Forcing an item onto a near code is the quiet version of the same mistake: the total looks defensible and the composicao behind it describes different work.

GirdiItem list of the orcamentoSINAPI code catalogueÇıktıCoded bill positionsItems with no SINAPI code
3

Hold every unit cost to the median the decree allows

Doğrulama

Run the priced bill against the reference base and list every position whose unit cost sits above the SINAPI median for its code. Treat each one as a question with two possible answers: the code is wrong, or the price needs a written justification. Do not close the list by editing the number down until it fits.

Neden: Decreto 7.983 of 2013 makes the median a ceiling rather than a benchmark for works carried out with federal funds, so a position above it is not expensive, it is outside the rule until somebody explains why. Found here it is a paragraph. Found by the control body it is a finding against the whole orcamento, and the recalculation lands on the contract that was already signed.

GirdiCoded bill positionsSINAPI median unit pricesÇıktıValidation report on the ceilingPositions above the reference price
4

Follow the decree's order for what SINAPI does not carry

Tahmin Esası

For each item left over, work down the order the decree sets before reaching for a quote: another reference table formally approved by a federal body, then specialist technical publications or a sector system, and a market survey only after those. Record on the basis of estimate which one you used, for which item, and on what date.

Neden: The order is the justification. An item priced from three quotes is defensible when the tables above it genuinely carried nothing, and indefensible when nobody looked. Written down at the moment of the decision, the reasoning survives the estimator leaving the company, which is roughly the timescale on which the question gets asked.

GirdiItems with no SINAPI codeSupplier quotes and published ratesÇıktıSource recorded per itemFallback order followed
5

Total the custo global with the BDI shown separately

Cost Explorer

Total the direct costs by group and read them against each other before adding anything on top. Keep the BDI as its own visible line rather than folded into the unit costs, and see which groups carry the money so you know which numbers the whole orcamento actually rests on.

Neden: A custo global that arrives as one figure cannot be argued with, only accepted or rejected. Split by group it shows immediately whether the earthworks or the finishes are carrying the estimate, and a BDI folded into the unit costs makes both the median check and the later composition of the BDI impossible to run at all.

GirdiPriced bill positionsBDI rateÇıktıCusto global de referenciaCost analysis by group
6

Publish it with the base and the month on its face

Raporlar

Export the orcamento with the SINAPI reference month, the state and the encargos option printed on it, together with the list of items priced from another source. Send that set as one document rather than the bill alone.

Neden: The bill on its own is the only part anybody copies, and six months later the month it was priced in is the fact everyone needs and nobody has. Printed on the face of the export it travels with the numbers, and the reajustamento clause later has a data-base it can actually point at.

GirdiCusto global de referenciaSource recorded per itemÇıktıOrcamento export for the editalReference month on every page
Modüller

Bu senaryodaki modüller

6 / 190 platform modülü

The market this case is written for

Brezilya

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.