Eine Kalkulation vor dem Versand prüfen
Ein bepreistes Leistungsverzeichnis durch die Validierungsregeln schicken, jede Warnung und…
Laden Sie SINAPI für den Referenzmonat, ordnen Sie jede Position des orçamento ihrem Code zu, halten Sie jede Einheitskosten am vom Decreto erlaubten Median, und erfassen Sie die Herkunft der Kosten für die Positionen, die SINAPI nicht führt.
6 Schritte über die Plattform hinweg - was Sie bei jedem tun und warum es zählt.
Load the SINAPI tables into the cost database for the state the work is in and the reference month the edital names, and keep the two on the record beside the prices. Load the encargos sociais table that goes with the same month rather than one you already had.
Warum: A SINAPI price without its state and its reference month is not a reference, it is a number. Every argument about the orcamento de referencia begins by agreeing which table both sides are reading, and that agreement is free now and costs a week once the proposals are in.
Put the SINAPI code on each position of the bill and check that the code's description, its unit and its scope really are what your item measures. Where a position is served by two codes that differ only in a detail of the method, pick the one the design specifies and say so. Collect the items no code fits rather than forcing them onto the nearest one.
Warum: The code carries the composicao behind the price, so a code chosen for its description alone imports a productivity and a set of insumos nobody read. Forcing an item onto a near code is the quiet version of the same mistake: the total looks defensible and the composicao behind it describes different work.
Run the priced bill against the reference base and list every position whose unit cost sits above the SINAPI median for its code. Treat each one as a question with two possible answers: the code is wrong, or the price needs a written justification. Do not close the list by editing the number down until it fits.
Warum: Decreto 7.983 of 2013 makes the median a ceiling rather than a benchmark for works carried out with federal funds, so a position above it is not expensive, it is outside the rule until somebody explains why. Found here it is a paragraph. Found by the control body it is a finding against the whole orcamento, and the recalculation lands on the contract that was already signed.
For each item left over, work down the order the decree sets before reaching for a quote: another reference table formally approved by a federal body, then specialist technical publications or a sector system, and a market survey only after those. Record on the basis of estimate which one you used, for which item, and on what date.
Warum: The order is the justification. An item priced from three quotes is defensible when the tables above it genuinely carried nothing, and indefensible when nobody looked. Written down at the moment of the decision, the reasoning survives the estimator leaving the company, which is roughly the timescale on which the question gets asked.
Total the direct costs by group and read them against each other before adding anything on top. Keep the BDI as its own visible line rather than folded into the unit costs, and see which groups carry the money so you know which numbers the whole orcamento actually rests on.
Warum: A custo global that arrives as one figure cannot be argued with, only accepted or rejected. Split by group it shows immediately whether the earthworks or the finishes are carrying the estimate, and a BDI folded into the unit costs makes both the median check and the later composition of the BDI impossible to run at all.
Export the orcamento with the SINAPI reference month, the state and the encargos option printed on it, together with the list of items priced from another source. Send that set as one document rather than the bill alone.
Warum: The bill on its own is the only part anybody copies, and six months later the month it was priced in is the fact everyone needs and nobody has. Printed on the face of the export it travels with the numbers, and the reajustamento clause later has a data-base it can actually point at.
6 / 190 Plattform-Modulen
Alles in diesem Fallbeispiel folgt der Art, wie Bauleistungen in diesem Markt aufgemessen, kalkuliert und abgerechnet werden. Die Formulare, die Kostengliederung und die Zahlungsregeln sind die, die dort gelten, und keine allgemeine Fassung davon.
Standards, denen es folgt
Das müssen Sie nicht von Hand einrichten. Beim ersten Start fragt die Plattform, in welchem Markt Sie arbeiten. Wählen Sie diesen aus, und sie stellt die Oberflächensprache ein, lädt die passende Kostendatenbank, hinterlegt die Kostengliederung und legt ein Beispielprojekt an, das Sie sofort öffnen können.
Die Prüfregeln für diesen Markt sind ebenfalls dabei. Einmal eingeschaltet, fällt eine Kalkulation, der etwas Marktübliches fehlt, schon während der Arbeit auf und nicht erst nach der Abgabe.
Ein bepreistes Leistungsverzeichnis durch die Validierungsregeln schicken, jede Warnung und…
Übernehmen Sie bepreiste Positionen aus einer echten Kostendatenbank, bauen Sie daraus das L…
Machen Sie aus einer Punktschätzung eine Bandbreite, lassen Sie eine Monte-Carlo-Simulation…