Orce o orçamento de referência a partir da base SINAPI

Carregue o SINAPI para o mês de referência, mapeie cada item do orçamento para o seu código, mantenha cada custo unitário na mediana que o decreto permite, e registe de onde veio o custo dos itens que o SINAPI não tem.

6 etapas18 minConsultoria de custos / QSEmpreiteiro geralPromotor / cliente

Como funciona, passo a passo

6 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Bring in SINAPI for the state and the reference month

Banco de Dados de Custos

Load the SINAPI tables into the cost database for the state the work is in and the reference month the edital names, and keep the two on the record beside the prices. Load the encargos sociais table that goes with the same month rather than one you already had.

Captura de tela, etapa 1: Bring in SINAPI for the state and the reference month (Banco de Dados de Custos, Orce o orçamento de referência a partir da base SINAPI)
Banco de Dados de Custos: Bring in SINAPI for the state and the reference month

Por quê: A SINAPI price without its state and its reference month is not a reference, it is a number. Every argument about the orcamento de referencia begins by agreeing which table both sides are reading, and that agreement is free now and costs a week once the proposals are in.

EntradaSINAPI reference pricesReference date the edital namesResultadoPriced reference base loadedState and reference month recorded
2

Map every item of the orcamento to its SINAPI code

Planilha Orçamentária

Put the SINAPI code on each position of the bill and check that the code's description, its unit and its scope really are what your item measures. Where a position is served by two codes that differ only in a detail of the method, pick the one the design specifies and say so. Collect the items no code fits rather than forcing them onto the nearest one.

Captura de tela, etapa 2: Map every item of the orcamento to its SINAPI code (Planilha Orçamentária, Orce o orçamento de referência a partir da base SINAPI)
Planilha Orçamentária: Map every item of the orcamento to its SINAPI code

Por quê: The code carries the composicao behind the price, so a code chosen for its description alone imports a productivity and a set of insumos nobody read. Forcing an item onto a near code is the quiet version of the same mistake: the total looks defensible and the composicao behind it describes different work.

EntradaItem list of the orcamentoSINAPI code catalogueResultadoCoded bill positionsItems with no SINAPI code
3

Hold every unit cost to the median the decree allows

Validação

Run the priced bill against the reference base and list every position whose unit cost sits above the SINAPI median for its code. Treat each one as a question with two possible answers: the code is wrong, or the price needs a written justification. Do not close the list by editing the number down until it fits.

Captura de tela, etapa 3: Hold every unit cost to the median the decree allows (Validação, Orce o orçamento de referência a partir da base SINAPI)
Validação: Hold every unit cost to the median the decree allows

Por quê: Decreto 7.983 of 2013 makes the median a ceiling rather than a benchmark for works carried out with federal funds, so a position above it is not expensive, it is outside the rule until somebody explains why. Found here it is a paragraph. Found by the control body it is a finding against the whole orcamento, and the recalculation lands on the contract that was already signed.

EntradaCoded bill positionsSINAPI median unit pricesResultadoValidation report on the ceilingPositions above the reference price
4

Follow the decree's order for what SINAPI does not carry

Base da estimativa

For each item left over, work down the order the decree sets before reaching for a quote: another reference table formally approved by a federal body, then specialist technical publications or a sector system, and a market survey only after those. Record on the basis of estimate which one you used, for which item, and on what date.

Por quê: The order is the justification. An item priced from three quotes is defensible when the tables above it genuinely carried nothing, and indefensible when nobody looked. Written down at the moment of the decision, the reasoning survives the estimator leaving the company, which is roughly the timescale on which the question gets asked.

EntradaItems with no SINAPI codeSupplier quotes and published ratesResultadoSource recorded per itemFallback order followed
5

Total the custo global with the BDI shown separately

Explorador de custos

Total the direct costs by group and read them against each other before adding anything on top. Keep the BDI as its own visible line rather than folded into the unit costs, and see which groups carry the money so you know which numbers the whole orcamento actually rests on.

Por quê: A custo global that arrives as one figure cannot be argued with, only accepted or rejected. Split by group it shows immediately whether the earthworks or the finishes are carrying the estimate, and a BDI folded into the unit costs makes both the median check and the later composition of the BDI impossible to run at all.

EntradaPriced bill positionsBDI rateResultadoCusto global de referenciaCost analysis by group
6

Publish it with the base and the month on its face

Relatórios

Export the orcamento with the SINAPI reference month, the state and the encargos option printed on it, together with the list of items priced from another source. Send that set as one document rather than the bill alone.

Captura de tela, etapa 6: Publish it with the base and the month on its face (Relatórios, Orce o orçamento de referência a partir da base SINAPI)
Relatórios: Publish it with the base and the month on its face

Por quê: The bill on its own is the only part anybody copies, and six months later the month it was priced in is the fact everyone needs and nobody has. Printed on the face of the export it travels with the numbers, and the reajustamento clause later has a data-base it can actually point at.

EntradaCusto global de referenciaSource recorded per itemResultadoOrcamento export for the editalReference month on every page
Módulos

Módulos deste playbook

6 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Brasil

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Orçamentação e custos