مدت کو planilha orcamentaria کے مقابلے میں ناپیں، اسے کنٹریکٹ ریٹس پر price کریں، fiscal do contrato سے boletim de medicao attest کروائیں اور attested نمبر کے خلاف nota fiscal جاری کریں، تاکہ expense liquidate ہو سکے بجائے اس کے کہ ایک ایسی قطار میں پڑا رہے جسے کوئی explain نہ کر سکے۔

6 مراحل12 منٹجنرل کنٹریکٹرخصوصی سب کنٹریکٹرڈیولپر / کلائنٹ

یہ کیسے کام کرتا ہے، قدم بہ قدم

6 قدم پوری پلیٹ فارم میں - ہر قدم پر کیا کرنا ہے اور یہ کیوں اہم ہے۔

1

Register the contract and its payment regime

کنٹریکٹس

Record the contract, its the contract payment terms under Lei 14.133 payment regime and the dates it turns on, so every later step reads the same terms instead of somebody's memory of them.

کیوں: A payment regime that lives in a PDF nobody opens is a regime that gets applied differently by each person who applies it. Registered once, the deadlines below are computed rather than argued about.

اندر جاتا ہےSigned contratoPlanilha orcamentariaباہر آتا ہےContract on recordMeasurement and payment terms attached
2

Measure the period item da planilha by item da planilha

پیش رفت

Record what was executed against each item da planilha for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

کیوں: A boletim de medicao built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one item da planilha rather than about the whole month, and the rest of the money moves while that one is settled.

اندر جاتا ہےPlanilha orcamentariaWork executed this periodباہر آتا ہےPercent complete per item da planilhaMeasured quantities for the period
3

Value it at the contract rates

مقدار کا بل (BOQ)

Read the valuation back against the bill and check the rates it used are the contract rates. Where an item da planilha has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

کیوں: A termo aditivo certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done. Quantity measured beyond what the contract carries has to become a termo aditivo before it is measured, not after it is paid. A public body that pays for it the other way round is asking its own audit to find the difference.

اندر جاتا ہےMeasured quantities for the periodContract unit ratesباہر آتا ہےBoletim de medicao for the periodTermo aditivo flagged
4

Get it approved by the people who have to approve it

منظوری روٹس

Route the boletim de medicao to the fiscal do contrato, and to whoever the contract adds after them. Keep the approval date, because the nota fiscal follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

کیوں: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

اندر جاتا ہےBoletim de medicao for the periodFiscal do contrato named for attestationباہر آتا ہےAttested boletim de medicaoAttestation date on record
5

Issue the nota fiscal against the approved figure

مالیات

Raise the nota fiscal against the approved boletim de medicao, carrying retencao contratual and any deduction the contract provides for, and reference the boletim de medicao on it. Reference the attested boletim on the nota fiscal itself. The accounts match the two by that reference, and an invoice carrying no reference is one a clerk has to chase somebody to explain.

کیوں: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the boletim de medicao also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

اندر جاتا ہےAttested boletim de medicaoRetencao and deductionsباہر آتا ہےNota fiscal issuedAmount carried into the accounts
6

Reconcile what was certified against what was asked

واقعہ مصالحت

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

کیوں: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight.

اندر جاتا ہےAmount invoicedAmount attestedباہر آتا ہےDifference carried forwardOutstanding by age
ماڈیولز

اس سیناریو کے ماڈیولز

6 / 190 پلیٹ فارم ماڈیولز

The market this case is written for

برازیل

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

کمرشل اور کنٹریکٹس میں مزید

کمرشل اور کنٹریکٹس

سب کنٹریکٹر پیکج چلائیں

ٹریڈ پیکج کسی سب کنٹریکٹر کو دیں، اسے شیڈول آف ویلیوز اور ریٹینشن کے ساتھ سب کنٹریکٹ پر رکھی…

3 مراحل11 منٹکھولیں
کمرشل اور کنٹریکٹس

ادائیگی کی درخواست اور مصالحت

اس مدت میں جگہ پر لگے کام کی قیمت کنٹریکٹ کے مقابلے میں لگائیں، پیچھے ثبوت کے ساتھ درخواست ا…

3 مراحل12 منٹکھولیں