Casos prácticos / Comercial y contratos
Comercial y contratos

Atestar el boletim de medição y facturar el período

Mida el período frente a la planilha orçamentária, valórelo a los precios del contrato, haga que el fiscal do contrato ateste el boletim de medição y emita la nota fiscal sobre la cifra atestada, para que el gasto pueda liquidarse en vez de quedar en una cola que nadie puede explicar.

6 pasos12 minContratista generalSubcontratista especialistaPromotor / cliente

Cómo funciona, paso a paso

6 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Register the contract and its payment regime

Contratos

Record the contract, its the contract payment terms under Lei 14.133 payment regime and the dates it turns on, so every later step reads the same terms instead of somebody's memory of them.

Captura de pantalla, paso 1: Register the contract and its payment regime (Contratos, Atestar el boletim de medição y facturar el período)
Contratos: Register the contract and its payment regime

Por que: A payment regime that lives in a PDF nobody opens is a regime that gets applied differently by each person who applies it. Registered once, the deadlines below are computed rather than argued about.

EntradaSigned contratoPlanilha orcamentariaResultadoContract on recordMeasurement and payment terms attached
2

Measure the period item da planilha by item da planilha

Avance

Record what was executed against each item da planilha for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

Captura de pantalla, paso 2: Measure the period item da planilha by item da planilha (Avance, Atestar el boletim de medição y facturar el período)
Avance: Measure the period item da planilha by item da planilha

Por que: A boletim de medicao built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one item da planilha rather than about the whole month, and the rest of the money moves while that one is settled.

EntradaPlanilha orcamentariaWork executed this periodResultadoPercent complete per item da planilhaMeasured quantities for the period
3

Value it at the contract rates

Presupuesto

Read the valuation back against the bill and check the rates it used are the contract rates. Where an item da planilha has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

Captura de pantalla, paso 3: Value it at the contract rates (Presupuesto, Atestar el boletim de medição y facturar el período)
Presupuesto: Value it at the contract rates

Por que: A termo aditivo certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done. Quantity measured beyond what the contract carries has to become a termo aditivo before it is measured, not after it is paid. A public body that pays for it the other way round is asking its own audit to find the difference.

EntradaMeasured quantities for the periodContract unit ratesResultadoBoletim de medicao for the periodTermo aditivo flagged
4

Get it approved by the people who have to approve it

Rutas de aprobación

Route the boletim de medicao to the fiscal do contrato, and to whoever the contract adds after them. Keep the approval date, because the nota fiscal follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

Captura de pantalla, paso 4: Get it approved by the people who have to approve it (Rutas de aprobación, Atestar el boletim de medição y facturar el período)
Rutas de aprobación: Get it approved by the people who have to approve it

Por que: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

EntradaBoletim de medicao for the periodFiscal do contrato named for attestationResultadoAttested boletim de medicaoAttestation date on record
5

Issue the nota fiscal against the approved figure

Finanzas

Raise the nota fiscal against the approved boletim de medicao, carrying retencao contratual and any deduction the contract provides for, and reference the boletim de medicao on it. Reference the attested boletim on the nota fiscal itself. The accounts match the two by that reference, and an invoice carrying no reference is one a clerk has to chase somebody to explain.

Captura de pantalla, paso 5: Issue the nota fiscal against the approved figure (Finanzas, Atestar el boletim de medição y facturar el período)
Finanzas: Issue the nota fiscal against the approved figure

Por que: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the boletim de medicao also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

EntradaAttested boletim de medicaoRetencao and deductionsResultadoNota fiscal issuedAmount carried into the accounts
6

Reconcile what was certified against what was asked

Conciliación de eventos

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

Por que: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight.

EntradaAmount invoicedAmount attestedResultadoDifference carried forwardOutstanding by age
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Brasil

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Comercial y contratos

Comercial y contratos

Solicitud de pago y conciliación

Valora la obra ejecutada este periodo frente al contrato, presenta la solicitud con su docum…

3 pasos12 minAbrir