案例 / 招标与采购
招标与采购

为 LOPSRM 招标报价并完整组建综合单价分析

读懂招标公告,按发布的原样导入 conceptos 目录,搭好 precios unitarios 分析背后的基础成本,按 reglamento 规定的顺序依次叠加间接费、融资费、利润和附加费,并在标书离开办公室之前先用墨西哥规则集完整校验一遍。

8 个步骤25 分钟总承包商专业分包商造价咨询 / 工料测量顾问

运作方式,逐步说明

贯穿平台的 8 个步骤 - 每一步做什么,以及为什么重要。

1

Read the convocatoria before you price anything

投标管理

Register the opportunity with the four things that decide whether it is worth pricing: the contract type the LOPSRM allows and the convocatoria chose, precios unitarios, precio alzado or mixto; the anticipo offered; whether the contract provides for ajuste de costos; and the full list of documents the propuesta tecnica and the propuesta economica have to carry. Put the junta de aclaraciones and the closing in the calendar the day you register it.

屏幕截图,步骤 1:Read the convocatoria before you price anything (投标管理, 为 LOPSRM 招标报价并完整组建综合单价分析)
投标管理: Read the convocatoria before you price anything

原因: The contract type changes the whole shape of the work: on precios unitarios the quantities move and the rates do not, on precio alzado nothing moves and the risk of the quantity is yours. Firms that price first and read the bases afterwards discover this on a job they have already won, which is the most expensive order to discover it in.

输入Convocatoria and bases de licitacionJunta de aclaraciones and closing dates成果Bid or no bid, with a reasonDocument list the propuesta must carry
2

Load the catalogo exactly as it was issued

工程量清单

Bring the catalogo de conceptos in with its claves, units and quantities untouched, and read each concepto against the especificacion that describes it. Where the description and the specification disagree, or a unit cannot carry the work described, that is a question for the junta de aclaraciones and not a decision for the estimator.

屏幕截图,步骤 2:Load the catalogo exactly as it was issued (工程量清单, 为 LOPSRM 招标报价并完整组建综合单价分析)
工程量清单: Load the catalogo exactly as it was issued

原因: The catalogo is the contract's spine for years: estimaciones, extraordinarios and the finiquito all read against it. A clave changed at tender to make the spreadsheet tidier is a mismatch that shows up in every future estimacion, and a question not asked at the junta becomes a risk you priced without knowing you had.

输入Catalogo de conceptos as issuedEspecificaciones and drawings成果Catalogo loaded line for lineQueries for the junta de aclaraciones
3

Build the mano de obra on a salario real, not a wage

人工单价

Set one rate per labour category and build it from the salario base plus the factor de salario real: the days actually worked in a year against the days paid, and the statutory employer charges on top, IMSS contributions and the housing fund contributions among them. Keep the factor and the year it was computed for beside the rate.

屏幕截图,步骤 3:Build the mano de obra on a salario real, not a wage (人工单价, 为 LOPSRM 招标报价并完整组建综合单价分析)
人工单价: Build the mano de obra on a salario real, not a wage

原因: The gap between a daily wage and a salario real is not a rounding difference, it is the whole margin on a labour heavy concepto. It also has to be defensible: the convocante can ask how the factor was arrived at, and a rate carried forward from a job three years ago answers that question with a number nobody can reconstruct.

输入Salarios base by categoryStatutory charges on employment成果Salario real per categoryThe factor written down and dated
4

Price the materiales at site and the maquinaria by the hour

资源目录

Hold the materiales at the cost of getting them onto the site, not at the yard price, and build each machine as a costo horario: ownership, depreciation, the money tied up in it, maintenance, fuel and the operator. Herramienta menor rides as its own charge on the labour rather than as a guess inside every concepto.

屏幕截图,步骤 4:Price the materiales at site and the maquinaria by the hour (资源目录, 为 LOPSRM 招标报价并完整组建综合单价分析)
资源目录: Price the materiales at site and the maquinaria by the hour

原因: The costo horario is the piece the convocante takes apart hardest, because it is where a proposal can be made to look cheap without changing anything visible. Built once from real ownership and running costs, it also survives the machine moving to the next job, which a rate invented for one tender never does.

输入Supplier quotationsMachinery, its hours and its costs成果Materiales priced at the siteCosto horario per machine
5

Compose the costo directo of each concepto

组合单价

Build each concepto as an analisis: the quantity of each material per unit of work, the crew and the hours it takes, the machines and their hours. That sum is the costo directo, and it is the only part of the price that is composed rather than applied as a percentage.

屏幕截图,步骤 5:Compose the costo directo of each concepto (组合单价, 为 LOPSRM 招标报价并完整组建综合单价分析)
组合单价: Compose the costo directo of each concepto

原因: The mexico.apu_completeness rule in the validation engine exists because an incomplete analisis is the most common defect in a Mexican proposal and the easiest one to miss in your own work: a concepto with materials and no labour reads perfectly well until somebody asks who places it. Composed properly, the same analisis prices the extraordinarios later without being rebuilt.

输入Labour, materials and machinery costsOutput per crew and per machine成果Costo directo per conceptoAnalisis a reviewer can take apart
6

Cascade indirectos, financiamiento, utilidad and cargos adicionales

工程量清单

In the bill's Markups & Overheads panel, apply the four charges in the order the reglamento of the LOPSRM fixes and on the base each one is applied to: indirectos on the costo directo, covering oficinas centrales and oficinas de campo; financiamiento on the costo directo plus indirectos, from the gap between spending the money and being paid it; utilidad on the accumulated cost; cargos adicionales on the lot, which on a federal contract is where the cinco al millar inspection fee sits. Keep IVA off the unit price entirely.

原因: The order is not a convention, it is what the integration means, and applying utilidad to the costo directo alone or folding the cinco al millar into indirectos produces a different total from the one the convocante will compute. Each percentage also has to be supported: the financiamiento comes from a cash flow against the programme, so it moves when the anticipo or the payment period moves, and a figure typed straight in cannot answer why.

输入Costo directo across the catalogoOffice and site overhead, and the cash curve成果Precio unitario integrated in orderAnalysis behind each percentage
7

Run the Mexican rule set before the proposal leaves

校验

Validate the priced catalogo against the mexico rule set: the APU completeness check on every concepto, the IVA rate check that will only accept sixteen, eight or zero, the retencion flag on subcontracted lines, and the CFDI issuer data the invoicing will need the moment the job is won. Fix the findings rather than filing them.

屏幕截图,步骤 7:Run the Mexican rule set before the proposal leaves (校验, 为 LOPSRM 招标报价并完整组建综合单价分析)
校验: Run the Mexican rule set before the proposal leaves

原因: A public proposal is discarded for a missing piece far more readily than it is discounted for a high price, and the pieces that go missing are the boring ones, an analisis with no labour line or an issuer field nobody filled in. Ten minutes against a rule set beats finding out at the apertura de proposiciones, where there is nothing to be done.

输入Fully priced catalogoIssuer fiscal data成果Findings against the Mexican rule setGaps closed before submission
8

Assemble the propuesta and keep what you sent

招投标

Put the two proposals together against the document list from the first step: the propuesta tecnica with the programmes of work, personnel and machinery, and the propuesta economica with the catalogo, the analisis, the basic costs and the explosion of insumos. Submission itself happens on the federal contracting platform the LOPSRM names, outside this product, so keep the exact package you uploaded here beside the tender record.

屏幕截图,步骤 8:Assemble the propuesta and keep what you sent (招投标, 为 LOPSRM 招标报价并完整组建综合单价分析)
招投标: Assemble the propuesta and keep what you sent

原因: What you submitted becomes the contract, and the version on somebody's laptop is not evidence of it. A year later, when an estimacion is queried or an extraordinario is priced, the argument is settled by the analisis that went in with the bid, and the firm that can produce it in a minute is negotiating from a different position from the one still looking for it.

输入Checked catalogo and analisisCompany, tax and programme documents成果Propuesta tecnica and economica assembledWhat was submitted, kept as issued
模块

此方案使用的模块

190 个平台模块中的 7 个

The market this case is written for

墨西哥

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 招标与采购 案例

招标与采购

基于工程量清单开展招标

将已计价的工程量清单推向市场:打包、邀请分包商、比选报价并确定中标方。五个步骤,全程贯通。

5 个步骤12 分钟打开
招标与采购

从工程量清单采购材料

采购已定价的工程量:从清单发起请购单,向供应商下单,并在现场验收入库。

4 个步骤10 分钟打开
招标与采购

比较投标并定标

面对一叠始终对不齐的投标文件,把它们统一还原到同一个工作范围,再向客户交出一份经得起审查的定标决定。

3 个步骤12 分钟打开