Casos prácticos / Presupuestación y costes
Presupuestación y costes

Medir un bill of quantities según NZS 4202

Mida neto tal como queda fijado en obra según el método estándar neozelandés, construya las partidas compuestas de modo que cada tasa lleve lo que el estándar da por incluido, ordene el bill en sus secciones de oficio con Preliminary and General, mantenga el desperdicio en la tasa, verifique el bill contra las reglas, y escriba los preambles que registran el método y cada desviación de él.

6 pasos16 minConsultoría de costes / QSContratista generalPromotor / cliente

Cómo funciona, paso a paso

6 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Measure net as fixed in place

Cubicación

Take off quantities the way the standard measures them: net as the work is fixed in place, in the unit the rule for that trade names, with the deductions the rule requires and no others. Keep each dimension attached to the drawing and revision it came from so the take-off can be re-read rather than re-done.

Por que: Net measurement is what makes two bills comparable, and it is also what makes a bill re-measurable when the design moves. A quantity that already has an allowance baked into it cannot be checked against a drawing by anybody except the person who made it, and that person is usually the one not available when the tender query arrives.

EntradaDrawings and specificationMeasurement rules for the tradeResultadoNet quantities as fixed in placeDimensions traceable to a drawing
2

Build items that carry what the rate includes

Partidas compuestas

Assemble each measured item as the composite the standard describes: the labour, the material, the plant and the incidental work the rule says the rate covers. Where a rule deems something included, put it inside the assembly rather than leaving it as a separate line somebody will price twice.

Por que: Nearly every dispute about a bill is a coverage dispute, not a quantity one: two people agreeing on the square metres and disagreeing about whether the rate included the edge trim. Building the coverage into the item makes it visible to the estimator pricing it and to the contractor reading it, which is the only place it can be settled cheaply.

EntradaNet quantities as fixed in placeWhat the rate is deemed to includeResultadoComposite items builtCoverage rules written into the item
3

Arrange the bill the way tenderers will read it

Presupuesto

Put the measured work into the trade sections the standard uses, and keep preliminary and general as its own section rather than spreading site costs through the trades. Carry provisional and prime cost sums as their own items with what they cover written against them.

Por que: A bill is priced by subcontractors who each read one section and ignore the rest, so the structure decides who sees what. Time-related site cost buried in the trades is cost nobody prices as time-related, and it is the first thing to be argued about when the job runs long.

EntradaComposite items builtTrade section structureResultadoBill in its trade sectionsPreliminary and general separated
4

Keep waste in the rate and out of the quantity

Coeficientes de merma

Set the waste allowance per material as a factor the rate carries, and let the purchase quantity be derived from it rather than typed into the bill. The measured quantity stays the net one the drawing supports; the quantity ordered from the merchant is a different number for a different purpose.

Por que: Waste added to the measured quantity breaks the one property that makes a bill useful, which is that anybody can check it against the drawing. It also double counts the moment a rate that already allows for waste is applied to a quantity that also does, and nobody notices because both numbers look reasonable on their own.

EntradaNet measured quantityMaterial and cutting patternResultadoWaste held in the ratePurchase quantity kept separate
5

Check the bill against the rules it claims to follow

Validación

Run the bill through the checks before it goes out: items with a unit that does not match the rule for their trade, items with no quantity, sections the drawings imply and the bill does not carry, and rates that fall outside a sane band for their unit. Fix what is wrong and record what is deliberate.

Por que: A bill goes to several tenderers on the same day, so an error in it is not one error, it is one error multiplied by the number of people pricing it, and every one of them prices around it differently. Half an hour of checking before issue is the cheapest half hour in the whole tender period.

EntradaBill in its trade sectionsRules the bill claims to followResultadoItems that break a ruleBill fit to go out
6

State the method, the drawings and every departure

Bases de la estimación

Record the basis of the bill in one place: that it is measured to NZS 4202, the drawings and revisions it was measured from, the specification it reads with, every departure from the standard and every exclusion and assumption the quantities rest on. Issue it with the bill rather than keeping it in the file.

Por que: The standard only does its job when the departures are stated, because a tenderer is entitled to assume the rules were followed everywhere it is silent. A bill issued without its basis puts the risk of every unstated assumption onto whoever priced it, which is the party least able to see it, and that is exactly the claim that comes back nine months later.

EntradaBill fit to go outDepartures from the standardResultadoMethod of measurement statedExclusions and assumptions listed
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Nueva Zelanda

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • NZS 3910
  • Construction Contracts Act

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Presupuestación y costes