Măsoară un bill of quantities conform NZS 4202

Măsoară net, așa cum e fixat în lucrare, conform metodei standard neozeelandeze, construiește articole compuse astfel încât fiecare tarif să poarte ce presupune standardul că include, aranjează devizul în secțiunile lui de meserie cu preliminary and general, ține deșeul în tarif, verifică devizul față de reguli și scrie preambles care înregistrează metoda și fiecare abatere de la ea.

6 pași16 minConsultanță costuri / QSAntreprenor generalDezvoltator / client

Cum funcționează, pas cu pas

6 pași în cadrul platformei - ce faceți la fiecare și de ce contează.

1

Measure net as fixed in place

Cuantificare

Take off quantities the way the standard measures them: net as the work is fixed in place, in the unit the rule for that trade names, with the deductions the rule requires and no others. Keep each dimension attached to the drawing and revision it came from so the take-off can be re-read rather than re-done.

Captură de ecran, pasul 1: Measure net as fixed in place (Cuantificare, Măsoară un bill of quantities conform NZS 4202)
Cuantificare: Measure net as fixed in place

De ce: Net measurement is what makes two bills comparable, and it is also what makes a bill re-measurable when the design moves. A quantity that already has an allowance baked into it cannot be checked against a drawing by anybody except the person who made it, and that person is usually the one not available when the tender query arrives.

IntrareDrawings and specificationMeasurement rules for the tradeRezultatNet quantities as fixed in placeDimensions traceable to a drawing
2

Build items that carry what the rate includes

Ansambluri

Assemble each measured item as the composite the standard describes: the labour, the material, the plant and the incidental work the rule says the rate covers. Where a rule deems something included, put it inside the assembly rather than leaving it as a separate line somebody will price twice.

Captură de ecran, pasul 2: Build items that carry what the rate includes (Ansambluri, Măsoară un bill of quantities conform NZS 4202)
Ansambluri: Build items that carry what the rate includes

De ce: Nearly every dispute about a bill is a coverage dispute, not a quantity one: two people agreeing on the square metres and disagreeing about whether the rate included the edge trim. Building the coverage into the item makes it visible to the estimator pricing it and to the contractor reading it, which is the only place it can be settled cheaply.

IntrareNet quantities as fixed in placeWhat the rate is deemed to includeRezultatComposite items builtCoverage rules written into the item
3

Arrange the bill the way tenderers will read it

Antemăsurătoare

Put the measured work into the trade sections the standard uses, and keep preliminary and general as its own section rather than spreading site costs through the trades. Carry provisional and prime cost sums as their own items with what they cover written against them.

Captură de ecran, pasul 3: Arrange the bill the way tenderers will read it (Antemăsurătoare, Măsoară un bill of quantities conform NZS 4202)
Antemăsurătoare: Arrange the bill the way tenderers will read it

De ce: A bill is priced by subcontractors who each read one section and ignore the rest, so the structure decides who sees what. Time-related site cost buried in the trades is cost nobody prices as time-related, and it is the first thing to be argued about when the job runs long.

IntrareComposite items builtTrade section structureRezultatBill in its trade sectionsPreliminary and general separated
4

Keep waste in the rate and out of the quantity

Factori de pierderi

Set the waste allowance per material as a factor the rate carries, and let the purchase quantity be derived from it rather than typed into the bill. The measured quantity stays the net one the drawing supports; the quantity ordered from the merchant is a different number for a different purpose.

Captură de ecran, pasul 4: Keep waste in the rate and out of the quantity (Factori de pierderi, Măsoară un bill of quantities conform NZS 4202)
Factori de pierderi: Keep waste in the rate and out of the quantity

De ce: Waste added to the measured quantity breaks the one property that makes a bill useful, which is that anybody can check it against the drawing. It also double counts the moment a rate that already allows for waste is applied to a quantity that also does, and nobody notices because both numbers look reasonable on their own.

IntrareNet measured quantityMaterial and cutting patternRezultatWaste held in the ratePurchase quantity kept separate
5

Check the bill against the rules it claims to follow

Validare

Run the bill through the checks before it goes out: items with a unit that does not match the rule for their trade, items with no quantity, sections the drawings imply and the bill does not carry, and rates that fall outside a sane band for their unit. Fix what is wrong and record what is deliberate.

Captură de ecran, pasul 5: Check the bill against the rules it claims to follow (Validare, Măsoară un bill of quantities conform NZS 4202)
Validare: Check the bill against the rules it claims to follow

De ce: A bill goes to several tenderers on the same day, so an error in it is not one error, it is one error multiplied by the number of people pricing it, and every one of them prices around it differently. Half an hour of checking before issue is the cheapest half hour in the whole tender period.

IntrareBill in its trade sectionsRules the bill claims to followRezultatItems that break a ruleBill fit to go out
6

State the method, the drawings and every departure

Baza estimării

Record the basis of the bill in one place: that it is measured to NZS 4202, the drawings and revisions it was measured from, the specification it reads with, every departure from the standard and every exclusion and assumption the quantities rest on. Issue it with the bill rather than keeping it in the file.

De ce: The standard only does its job when the departures are stated, because a tenderer is entitled to assume the rules were followed everywhere it is silent. A bill issued without its basis puts the risk of every unstated assumption onto whoever priced it, which is the party least able to see it, and that is exactly the claim that comes back nine months later.

IntrareBill fit to go outDepartures from the standardRezultatMethod of measurement statedExclusions and assumptions listed
Module

Modulele acestui playbook

6 / 190 module ale platformei

The market this case is written for

Noua Zeelandă

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.