케이스 / 적산 및 원가
적산 및 원가

NZS 4202에 따라 내역서 산출하기

뉴질랜드 표준 측정법에 따라 시공 상태 기준 순수량으로 측정하고, 각 단가가 규격상 포함된 것으로 간주되는 내용을 담도록 복합 항목을 구성하고, preliminary and general과 함께 내역서를 공종 구분대로 정렬하고, 손실은 단가에 포함하고, 내역서를 규칙에 대조해 확인하고, 방법과 모든 편차를 기록하는 preambles를 작성한다.

6단계16 분원가 컨설팅 / 적산 업체종합건설사시행사 / 발주처

작동 방식, 단계별로

플랫폼 전반에 걸친 6단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Measure net as fixed in place

수량 산출

Take off quantities the way the standard measures them: net as the work is fixed in place, in the unit the rule for that trade names, with the deductions the rule requires and no others. Keep each dimension attached to the drawing and revision it came from so the take-off can be re-read rather than re-done.

이유: Net measurement is what makes two bills comparable, and it is also what makes a bill re-measurable when the design moves. A quantity that already has an allowance baked into it cannot be checked against a drawing by anybody except the person who made it, and that person is usually the one not available when the tender query arrives.

입력Drawings and specificationMeasurement rules for the trade결과Net quantities as fixed in placeDimensions traceable to a drawing
2

Build items that carry what the rate includes

일위대가

Assemble each measured item as the composite the standard describes: the labour, the material, the plant and the incidental work the rule says the rate covers. Where a rule deems something included, put it inside the assembly rather than leaving it as a separate line somebody will price twice.

이유: Nearly every dispute about a bill is a coverage dispute, not a quantity one: two people agreeing on the square metres and disagreeing about whether the rate included the edge trim. Building the coverage into the item makes it visible to the estimator pricing it and to the contractor reading it, which is the only place it can be settled cheaply.

입력Net quantities as fixed in placeWhat the rate is deemed to include결과Composite items builtCoverage rules written into the item
3

Arrange the bill the way tenderers will read it

내역서

Put the measured work into the trade sections the standard uses, and keep preliminary and general as its own section rather than spreading site costs through the trades. Carry provisional and prime cost sums as their own items with what they cover written against them.

이유: A bill is priced by subcontractors who each read one section and ignore the rest, so the structure decides who sees what. Time-related site cost buried in the trades is cost nobody prices as time-related, and it is the first thing to be argued about when the job runs long.

입력Composite items builtTrade section structure결과Bill in its trade sectionsPreliminary and general separated
4

Keep waste in the rate and out of the quantity

할증률

Set the waste allowance per material as a factor the rate carries, and let the purchase quantity be derived from it rather than typed into the bill. The measured quantity stays the net one the drawing supports; the quantity ordered from the merchant is a different number for a different purpose.

이유: Waste added to the measured quantity breaks the one property that makes a bill useful, which is that anybody can check it against the drawing. It also double counts the moment a rate that already allows for waste is applied to a quantity that also does, and nobody notices because both numbers look reasonable on their own.

입력Net measured quantityMaterial and cutting pattern결과Waste held in the ratePurchase quantity kept separate
5

Check the bill against the rules it claims to follow

검증

Run the bill through the checks before it goes out: items with a unit that does not match the rule for their trade, items with no quantity, sections the drawings imply and the bill does not carry, and rates that fall outside a sane band for their unit. Fix what is wrong and record what is deliberate.

이유: A bill goes to several tenderers on the same day, so an error in it is not one error, it is one error multiplied by the number of people pricing it, and every one of them prices around it differently. Half an hour of checking before issue is the cheapest half hour in the whole tender period.

입력Bill in its trade sectionsRules the bill claims to follow결과Items that break a ruleBill fit to go out
6

State the method, the drawings and every departure

견적 근거

Record the basis of the bill in one place: that it is measured to NZS 4202, the drawings and revisions it was measured from, the specification it reads with, every departure from the standard and every exclusion and assumption the quantities rest on. Issue it with the bill rather than keeping it in the file.

이유: The standard only does its job when the departures are stated, because a tenderer is entitled to assume the rules were followed everywhere it is silent. A bill issued without its basis puts the risk of every unstated assumption onto whoever priced it, which is the party least able to see it, and that is exactly the claim that comes back nine months later.

입력Bill fit to go outDepartures from the standard결과Method of measurement statedExclusions and assumptions listed
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6

The market this case is written for

뉴질랜드

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

적산 및 원가 카테고리의 더 보기

적산 및 원가

발송 전 견적 점검

산출된 내역서를 검증 규칙에 통과시켜 모든 경고와 오류를 해결한 뒤, 발주자에게 바로 전달할 수 있는 깨끗한 보고서를 내보냅니다.

3단계8 분열기
적산 및 원가

원가 데이터베이스로 견적 산정하기

실제 원가 데이터베이스에서 가격 항목을 가져와 내역서를 작성하고, 반복되는 조합을 어셈블리로 묶은 뒤, 입찰 금액을 확정하기 전에 검토를 실행합니다.

4단계12 분열기
적산 및 원가

비용 리스크로 예비비 산정하기

단일 값 견적을 범위로 바꾸고, 실제로 불확실한 항목에 대해 몬테카를로 시뮬레이션을 실행하여 P50~P90 분포를 읽고, 항목별로 근거를 설명할 수 있는 예비비를 설…

3단계11 분열기