سناریوها / برآورد و هزینه‌یابی
برآورد و هزینه‌یابی

تعیین encargos sociais و تصمیم‌گیری درباره desoneração

هزینه ساعتی هر عملکرد را بسازید، رژیم حقوق‌ودستمزد را برای کل orçamento انتخاب کنید، هر composição را طبق همان جدول بازسازی کنید، ثابت کنید هیچ composição‌ای باقی‌مانده از دیگری نیست، و encargos قیمت‌گذاری‌شده را در برابر folha واقعاً پرداخت‌شده تأیید کنید.

6 مرحله16 دقیقهپیمانکار عمومیپیمانکار جزء تخصصیمشاوره هزینه / QS

چگونه کار می‌کند، گام به گام

6 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Build the hourly cost of each function

نرخ‌های نیروی کار

Enter the wage each function is paid under the collective agreement of the region and the year, and keep the base wage and the encargos as two visible numbers rather than one loaded rate. Do it for the servente and the encarregado as well as for the pedreiro.

چرا: A loaded rate cannot be re-based when the agreement is renewed or when the payroll regime changes, and both happen inside the life of one estimate. Split, the same change is one figure edited in one place, and the composicoes underneath follow it.

ورودیCollective agreement wage ratesFunctions the work needsخروجیHourly labour ratesBase wage separated from the burden
2

Choose the payroll regime for the whole orcamento

مبنای برآورد

Decide whether this estimate is priced with the contribution on payroll or on turnover, check the edital in case it fixes the answer for you, and record the decision on the basis of estimate together with the encargos percentage it implies. One regime, one percentage, one orcamento.

چرا: Lei 12.546 of 2011 makes this a company decision with a real effect on the labour cost, and the reference bases publish a separate table for each answer. Recorded once at the top, it becomes a fact everybody working on the estimate can check against. Left implicit, it is rediscovered by whoever opens the file next, and they will assume whichever table they used last.

ورودیCompany turnover and payrollEncargos tables for both regimesخروجیRegime recorded for this orcamentoEncargos rate that follows from it
3

Rebuild every composicao on the chosen table

اسمبلی‌ها

Push the chosen encargos percentage through every composicao that carries labour, including the auxiliares underneath them, and read the change in the total. Do it as one pass rather than as a correction applied to the items somebody happens to open.

چرا: The auxiliares are what get missed, because they are priced early and then behave like insumos. An argamassa still carrying the other table quietly prices the mason inside it under a regime the rest of the estimate has abandoned, and the item above it looks entirely normal.

ورودیEncargos rate that follows from itComposicoes holding labourخروجیComposicoes rebuilt on one tableCost analysis of the change
4

Prove nothing was left on the other table

اعتبارسنجی

Run the orcamento against the recorded regime and list every position whose labour still carries the percentage of the other one. Treat an empty list as the deliverable of this step, not as a formality.

چرا: This is the one error in the whole estimate that produces no symptom. A mixed orcamento totals cleanly, prints cleanly and reads as internally consistent, and it is discovered either by an analyst comparing your labour cost with the published table or by nobody at all. A machine asking the question line by line is the only reliable reader.

ورودیComposicoes rebuilt on one tableRegime recorded for this orcamentoخروجیValidation report on the regimePositions left on the other table
5

Compare the priced burden with the folha you paid

حقوق و دستمزد

Take a period that has closed and put the encargos you priced next to the encargos the payroll actually paid, split between the contributions, the paid absences and the provisions. Ask which part of the difference is a wrong percentage and which is a job that worked more overtime than it planned.

چرا: The published table describes an average company, and yours has a real absence rate, a real overtime pattern and a real turnover of labour. The gap is a fact about the company rather than about the job, and it is the same gap on every job until somebody measures it.

ورودیEncargos rate that follows from itPayroll actually paidخروجیGap between priced and paidDifference split by cause
6

Feed the difference back into the next estimate

محاسبه نهایی

Close the loop in post-calculation: put the difference beside the hours the site actually booked, decide which part is a permanent correction to your own encargos figure, and change the figure rather than remembering to add a bit next time.

چرا: A correction that lives in an estimator's head is applied on the jobs they price and nowhere else, and it leaves with them. A corrected rate in the cost database is applied by everybody, and the next comparison measures the correction instead of rediscovering the original gap.

ورودیGap between priced and paidHours booked on siteخروجیCorrected rate for the next orcamentoTrend across jobs
ماژول‌ها

ماژول‌های این سناریو

6 / 190 ماژول پلتفرم

The market this case is written for

برزیل

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

بیشتر در برآورد و هزینه‌یابی

برآورد و هزینه‌یابی

بررسی یک برآورد پیش از ارسال آن

یک صورت‌وضعیت قیمت‌گذاری‌شده را از قواعد validation عبور دهید، هر هشدار و خطا را رفع کنید، س…

3 مرحله8 دقیقهباز کردن
برآورد و هزینه‌یابی

برآورد از یک پایگاه داده هزینه

اقلام قیمت‌گذاری‌شده را از یک پایگاه داده هزینه واقعی بردارید، صورت‌وضعیت را از آن‌ها بسازید…

4 مرحله12 دقیقهباز کردن