תרחישים / אומדן ותמחור
אומדן ותמחור

קביעת ה-encargos sociais והחלטה על ה-desoneração

בנו את העלות השעתית של כל תפקיד, בחרו את משטר השכר עבור כל ה-orçamento, בנו מחדש כל composição על הטבלה שמתאימה לו, הוכיחו שאף composição לא נשארה על הטבלה האחרת, ובדקו את ה-encargos המתומחרים מול ה-folha ששילמתם בפועל.

6 שלבים16 דק׳קבלן ראשיקבלן משנה מתמחהייעוץ עלויות / כמויות

איך זה עובד, שלב אחר שלב

6 שלבים לאורך הפלטפורמה - מה עושים בכל שלב ולמה זה חשוב.

1

Build the hourly cost of each function

תעריפי עבודה

Enter the wage each function is paid under the collective agreement of the region and the year, and keep the base wage and the encargos as two visible numbers rather than one loaded rate. Do it for the servente and the encarregado as well as for the pedreiro.

צילום מסך, שלב 1: Build the hourly cost of each function (תעריפי עבודה, קביעת ה-encargos sociais והחלטה על ה-desoneração)
תעריפי עבודה: Build the hourly cost of each function

למה: A loaded rate cannot be re-based when the agreement is renewed or when the payroll regime changes, and both happen inside the life of one estimate. Split, the same change is one figure edited in one place, and the composicoes underneath follow it.

נכנסCollective agreement wage ratesFunctions the work needsיוצאHourly labour ratesBase wage separated from the burden
2

Choose the payroll regime for the whole orcamento

בסיס האומדן

Decide whether this estimate is priced with the contribution on payroll or on turnover, check the edital in case it fixes the answer for you, and record the decision on the basis of estimate together with the encargos percentage it implies. One regime, one percentage, one orcamento.

למה: Lei 12.546 of 2011 makes this a company decision with a real effect on the labour cost, and the reference bases publish a separate table for each answer. Recorded once at the top, it becomes a fact everybody working on the estimate can check against. Left implicit, it is rediscovered by whoever opens the file next, and they will assume whichever table they used last.

נכנסCompany turnover and payrollEncargos tables for both regimesיוצאRegime recorded for this orcamentoEncargos rate that follows from it
3

Rebuild every composicao on the chosen table

מכלולים

Push the chosen encargos percentage through every composicao that carries labour, including the auxiliares underneath them, and read the change in the total. Do it as one pass rather than as a correction applied to the items somebody happens to open.

צילום מסך, שלב 3: Rebuild every composicao on the chosen table (מכלולים, קביעת ה-encargos sociais והחלטה על ה-desoneração)
מכלולים: Rebuild every composicao on the chosen table

למה: The auxiliares are what get missed, because they are priced early and then behave like insumos. An argamassa still carrying the other table quietly prices the mason inside it under a regime the rest of the estimate has abandoned, and the item above it looks entirely normal.

נכנסEncargos rate that follows from itComposicoes holding labourיוצאComposicoes rebuilt on one tableCost analysis of the change
4

Prove nothing was left on the other table

אימות

Run the orcamento against the recorded regime and list every position whose labour still carries the percentage of the other one. Treat an empty list as the deliverable of this step, not as a formality.

צילום מסך, שלב 4: Prove nothing was left on the other table (אימות, קביעת ה-encargos sociais והחלטה על ה-desoneração)
אימות: Prove nothing was left on the other table

למה: This is the one error in the whole estimate that produces no symptom. A mixed orcamento totals cleanly, prints cleanly and reads as internally consistent, and it is discovered either by an analyst comparing your labour cost with the published table or by nobody at all. A machine asking the question line by line is the only reliable reader.

נכנסComposicoes rebuilt on one tableRegime recorded for this orcamentoיוצאValidation report on the regimePositions left on the other table
5

Compare the priced burden with the folha you paid

שכר

Take a period that has closed and put the encargos you priced next to the encargos the payroll actually paid, split between the contributions, the paid absences and the provisions. Ask which part of the difference is a wrong percentage and which is a job that worked more overtime than it planned.

למה: The published table describes an average company, and yours has a real absence rate, a real overtime pattern and a real turnover of labour. The gap is a fact about the company rather than about the job, and it is the same gap on every job until somebody measures it.

נכנסEncargos rate that follows from itPayroll actually paidיוצאGap between priced and paidDifference split by cause
6

Feed the difference back into the next estimate

חישוב בדיעבד

Close the loop in post-calculation: put the difference beside the hours the site actually booked, decide which part is a permanent correction to your own encargos figure, and change the figure rather than remembering to add a bit next time.

צילום מסך, שלב 6: Feed the difference back into the next estimate (חישוב בדיעבד, קביעת ה-encargos sociais והחלטה על ה-desoneração)
חישוב בדיעבד: Feed the difference back into the next estimate

למה: A correction that lives in an estimator's head is applied on the jobs they price and nowhere else, and it leaves with them. A corrected rate in the cost database is applied by everybody, and the next comparison measures the correction instead of rediscovering the original gap.

נכנסGap between priced and paidHours booked on siteיוצאCorrected rate for the next orcamentoTrend across jobs
מודולים

המודולים בתרחיש הזה

6 מתוך 190 מודולי הפלטפורמה

The market this case is written for

ברזיל

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

עוד ב-אומדן ותמחור

אומדן ותמחור

בדיקת אומדן לפני שליחתו

העבירו כתב מתומחר דרך כללי האימות, נקו כל אזהרה ושגיאה, ואז ייצאו דוח נקי שאפשר למסור ישירות…

3 שלבים8 דק׳פתיחה
אומדן ותמחור

אומדן ממאגר עלויות

משכו סעיפים מתומחרים ממאגר עלויות אמיתי, בנו מהם את הכתב, קבצו מבני חישוב חוזרים למכלולים וה…

4 שלבים12 דק׳פתיחה
אומדן ותמחור

קביעת רזרבה מסיכון עלות

הפכו אומדן חד-נקודתי לטווח, הריצו סימולציית מונטה קרלו על השורות שבאמת לא ודאיות, קראו את הפ…

3 שלבים11 דק׳פתיחה