案例 / 估算与成本
估算与成本

确定encargos sociais并就desoneração做出决定

建立每个岗位的小时成本,为整个orçamento选定工资制度,按与之匹配的表格重建每一份composição,证明没有任何composição遗留在另一份表格上,并把已计价的encargos对照你实际支付的folha核查。

6 个步骤16 分钟总承包商专业分包商造价咨询 / 工料测量顾问

运作方式,逐步说明

贯穿平台的 6 个步骤 - 每一步做什么,以及为什么重要。

1

Build the hourly cost of each function

人工单价

Enter the wage each function is paid under the collective agreement of the region and the year, and keep the base wage and the encargos as two visible numbers rather than one loaded rate. Do it for the servente and the encarregado as well as for the pedreiro.

原因: A loaded rate cannot be re-based when the agreement is renewed or when the payroll regime changes, and both happen inside the life of one estimate. Split, the same change is one figure edited in one place, and the composicoes underneath follow it.

输入Collective agreement wage ratesFunctions the work needs成果Hourly labour ratesBase wage separated from the burden
2

Choose the payroll regime for the whole orcamento

估算依据

Decide whether this estimate is priced with the contribution on payroll or on turnover, check the edital in case it fixes the answer for you, and record the decision on the basis of estimate together with the encargos percentage it implies. One regime, one percentage, one orcamento.

原因: Lei 12.546 of 2011 makes this a company decision with a real effect on the labour cost, and the reference bases publish a separate table for each answer. Recorded once at the top, it becomes a fact everybody working on the estimate can check against. Left implicit, it is rediscovered by whoever opens the file next, and they will assume whichever table they used last.

输入Company turnover and payrollEncargos tables for both regimes成果Regime recorded for this orcamentoEncargos rate that follows from it
3

Rebuild every composicao on the chosen table

组合单价

Push the chosen encargos percentage through every composicao that carries labour, including the auxiliares underneath them, and read the change in the total. Do it as one pass rather than as a correction applied to the items somebody happens to open.

原因: The auxiliares are what get missed, because they are priced early and then behave like insumos. An argamassa still carrying the other table quietly prices the mason inside it under a regime the rest of the estimate has abandoned, and the item above it looks entirely normal.

输入Encargos rate that follows from itComposicoes holding labour成果Composicoes rebuilt on one tableCost analysis of the change
4

Prove nothing was left on the other table

校验

Run the orcamento against the recorded regime and list every position whose labour still carries the percentage of the other one. Treat an empty list as the deliverable of this step, not as a formality.

原因: This is the one error in the whole estimate that produces no symptom. A mixed orcamento totals cleanly, prints cleanly and reads as internally consistent, and it is discovered either by an analyst comparing your labour cost with the published table or by nobody at all. A machine asking the question line by line is the only reliable reader.

输入Composicoes rebuilt on one tableRegime recorded for this orcamento成果Validation report on the regimePositions left on the other table
5

Compare the priced burden with the folha you paid

薪资管理

Take a period that has closed and put the encargos you priced next to the encargos the payroll actually paid, split between the contributions, the paid absences and the provisions. Ask which part of the difference is a wrong percentage and which is a job that worked more overtime than it planned.

原因: The published table describes an average company, and yours has a real absence rate, a real overtime pattern and a real turnover of labour. The gap is a fact about the company rather than about the job, and it is the same gap on every job until somebody measures it.

输入Encargos rate that follows from itPayroll actually paid成果Gap between priced and paidDifference split by cause
6

Feed the difference back into the next estimate

结算后核算

Close the loop in post-calculation: put the difference beside the hours the site actually booked, decide which part is a permanent correction to your own encargos figure, and change the figure rather than remembering to add a bit next time.

原因: A correction that lives in an estimator's head is applied on the jobs they price and nowhere else, and it leaves with them. A corrected rate in the cost database is applied by everybody, and the next comparison measures the correction instead of rediscovering the original gap.

输入Gap between priced and paidHours booked on site成果Corrected rate for the next orcamentoTrend across jobs
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

巴西

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 估算与成本 案例

估算与成本

发出估算前进行核查

让已计价的清单通过核查规则,清除所有警告和错误,再导出一份可以直接交给客户的干净报告。

3 个步骤8 分钟打开
估算与成本

根据成本数据库进行估算

从真实的成本数据库中提取已计价项目,据此构建清单,把常用的组合做法打包成组合定额,提交投标数字前先做校核。

4 个步骤12 分钟打开
估算与成本

根据成本风险设定应急费

把单点估算转化为区间估算,对真正存在不确定性的项目运行蒙特卡洛模拟,读取P50到P90的分布区间,设定一个可以逐项说清楚的应急费。

3 个步骤11 分钟打开