תרחישים / מסחרי וחוזים
מסחרי וחוזים

גביית contract price adjustment לפי מדדי CPAP

קראו את ה-contract data כדי לקבוע אם העבודה נושאת contract price adjustment, קבעו את חודש הבסיס ואת ה-work groups שהוא מכנה, הפרידו את העבודה שההוראות מגיעות אליה מזו שלא, חשבו את המקדם על המדדים שפורסמו, ואשרו אותו כסעיף עצמאי.

7 שלבים15 דק׳קבלן ראשיייעוץ עלויות / כמויותקבלן משנה מתמחה

איך זה עובד, שלב אחר שלב

7 שלבים לאורך הפלטפורמה - מה עושים בכל שלב ולמה זה חשוב.

1

Settle whether the contract carries adjustment at all

חוזים

Read the contract data of the building agreement or of the civil engineering conditions and record four things before anything is measured: whether contract price adjustment applies, the base month it runs from, the work groups the contract names together with the weighting given to each, and the portion of the value the contract data holds non adjustable. Record as well what the contract says about the indices once the works are in delay.

למה: A fixed price job and an adjustable one look identical on the drawings and differ by one page of the contract data. The difference is a year or two of inflation on the whole contract sum, and it is settled at tender stage by a person who is usually not the person certifying payment eighteen months later. Writing the terms down where the certificate is prepared is what stops the provisions being remembered at the final account.

נכנסSigned contractContract dataיוצאAdjustment terms recordedBase month fixed
2

Load the work group indices and pin the base month

מדד מחירים

Load the index series the contract data names, the work group indices published for building or for civil engineering work, and pin the base index to the month the contract fixes rather than to the month work started on site. Keep every month's figure with the date it was published and flag the ones that are still provisional.

למה: The indices are published behind the month they describe and the early figures are revised, so an adjustment worked on a provisional number will have to be worked again. Pinning the base once, at the start, is what stops every later certificate reopening the argument about which month the escalation runs from, which is the argument that costs the most and settles the least.

נכנסPublished index seriesWork groups the contract namesיוצאBase index pinnedMonthly index record
3

Separate the work the provisions reach from the work they do not

כתב כמויות

Take the value certified for the period and set aside what the provisions do not adjust: materials on site that are not yet built in, the amounts the contract excludes by name, anything already adjusted under another clause, and the non adjustable portion the contract data fixes. What is left is the adjustable value for the month.

למה: Applying escalation to the whole certificate is the commonest way an adjustment is refused in full rather than corrected in part. The exclusions are written in the contract and the person certifying knows them, so a submission that shows the split is checked once, while one that shows a single figure is queried every month until somebody stops asking for it.

נכנסCertified valueExclusions the contract namesיוצאAdjustable valueExcluded amounts
4

Work the factor the way the formula works it

מדד מחירים

Take each work group's current index over its base index, weight it as the contract data weights it, sum the weighted ratios, subtract one, and apply the result to the adjustable value with the non adjustable portion held out. Record the index figures actually used against the month, not just the answer they produced.

למה: The formula is arithmetic and its result is only as defensible as the inputs printed beside it. An adjustment presented as one number is a request to be trusted, and the quantity surveyor certifying it is not permitted to trust it. The same working also says what the next few months cost if the trend holds, which is a figure the cash flow should have and usually does not.

נכנסAdjustable valueCurrent indicesיוצאAdjustment factorAmount for the month
5

Certify the adjustment as its own item

כספים

Put the adjustment on the payment certificate as a separate item with its working attached, never folded into the rates or into a lump sum under preliminaries. Carry the cumulative adjustment forward so the figure claimed this month is the movement since last month and not the total again.

למה: An adjustment buried in the rates cannot be checked, and what cannot be checked is deferred to the final account, where it is settled at whatever both sides can still evidence years later. Standing on its own line it is either paid this month or refused this month with a reason, and a refusal with a reason is something you can answer.

נכנסAmount for the monthPayment certificateיוצאAdjustment certifiedCumulative position
6

Fix the date the indices stop moving

מועדי יעד

Record the date the works were to reach practical completion together with every extension of time actually granted, and put both under a reminder. Where the contract stops the adjustment moving once the delay is the contractor's own, work the later months on the indices current at that date rather than at the date the work was done.

למה: This is the half of the provisions that runs against the contractor, and it is applied by the person certifying whether or not you applied it first. Knowing the date the indices freeze turns an extension of time from a programme argument into a money one, with a figure attached to every week of it, which is the only form in which such an argument gets settled quickly.

נכנסContract completion dateExtensions grantedיוצאIndex cut-off dateAdjustment at risk
7

Rework the provisional months for the final account

חישוב בדיעבד

When the final index figures are published, rework every month that was certified on a provisional one, set the reworked cumulative adjustment against what was actually paid, and settle the difference in the final account instead of leaving it in a spreadsheet nobody opens again.

למה: Revisions run both ways, so a job that never reworks them leaves money on both sides of the table and has no way of saying which. The reconciliation is ten minutes of arithmetic while the file is open and an unprovable claim two years after the last certificate.

נכנסFinal indicesCertified adjustmentsיוצאReconciled totalFinal account line
מודולים

המודולים בתרחיש הזה

6 מתוך 190 מודולי הפלטפורמה

The market this case is written for

דרום אפריקה

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

עוד ב-מסחרי וחוזים

מסחרי וחוזים

הפיכת שינוי לשינוי חוזי משולם

תעדו שינוי היקף בעוד הוא טרי, תמחרו אותו כשינוי חוזי לפי התעריפים המוסכמים שלכם, וחייבו אותו…

3 שלבים11 דק׳פתיחה
מסחרי וחוזים

ניהול חבילת קבלן משנה

העניקו חבילת עבודה לקבלן משנה, הציבו אותה על חוזה משנה עם לוח ערכים וניכוי עיכבון, ואז שלמו…

3 שלבים11 דק׳פתיחה
מסחרי וחוזים

בקשת תשלום והתאמה

העריכו את העבודה שבוצעה בתקופה זו מול החוזה, העלו את הבקשה עם הראיות מאחוריה, והתאימו את מה…

3 שלבים12 דק׳פתיחה