Casi / Commerciale e contratti
Commerciale e contratti

Recuperare il contract price adjustment sugli indici CPAP

Leggi il contract data per stabilire se il cantiere porta il contract price adjustment, fissa il mese base e i work groups che nomina, separa il lavoro che le clausole raggiungono da quello che non raggiungono, calcola il fattore sugli indici pubblicati e certificalo come voce a se stante.

7 passaggi15 minImpresa generaleConsulenza costi / QSSubappaltatore specializzato

Come funziona, passo dopo passo

7 passi attraverso la piattaforma - cosa fare a ciascuno e perché conta.

1

Settle whether the contract carries adjustment at all

Contratti

Read the contract data of the building agreement or of the civil engineering conditions and record four things before anything is measured: whether contract price adjustment applies, the base month it runs from, the work groups the contract names together with the weighting given to each, and the portion of the value the contract data holds non adjustable. Record as well what the contract says about the indices once the works are in delay.

Schermata, passaggio 1: Settle whether the contract carries adjustment at all (Contratti, Recuperare il contract price adjustment sugli indici CPAP)
Contratti: Settle whether the contract carries adjustment at all

Perché: A fixed price job and an adjustable one look identical on the drawings and differ by one page of the contract data. The difference is a year or two of inflation on the whole contract sum, and it is settled at tender stage by a person who is usually not the person certifying payment eighteen months later. Writing the terms down where the certificate is prepared is what stops the provisions being remembered at the final account.

In entrataSigned contractContract dataIn uscitaAdjustment terms recordedBase month fixed
2

Load the work group indices and pin the base month

Indice dei prezzi

Load the index series the contract data names, the work group indices published for building or for civil engineering work, and pin the base index to the month the contract fixes rather than to the month work started on site. Keep every month's figure with the date it was published and flag the ones that are still provisional.

Schermata, passaggio 2: Load the work group indices and pin the base month (Indice dei prezzi, Recuperare il contract price adjustment sugli indici CPAP)
Indice dei prezzi: Load the work group indices and pin the base month

Perché: The indices are published behind the month they describe and the early figures are revised, so an adjustment worked on a provisional number will have to be worked again. Pinning the base once, at the start, is what stops every later certificate reopening the argument about which month the escalation runs from, which is the argument that costs the most and settles the least.

In entrataPublished index seriesWork groups the contract namesIn uscitaBase index pinnedMonthly index record
3

Separate the work the provisions reach from the work they do not

Computo metrico estimativo

Take the value certified for the period and set aside what the provisions do not adjust: materials on site that are not yet built in, the amounts the contract excludes by name, anything already adjusted under another clause, and the non adjustable portion the contract data fixes. What is left is the adjustable value for the month.

Schermata, passaggio 3: Separate the work the provisions reach from the work they do not (Computo metrico estimativo, Recuperare il contract price adjustment sugli indici CPAP)
Computo metrico estimativo: Separate the work the provisions reach from the work they do not

Perché: Applying escalation to the whole certificate is the commonest way an adjustment is refused in full rather than corrected in part. The exclusions are written in the contract and the person certifying knows them, so a submission that shows the split is checked once, while one that shows a single figure is queried every month until somebody stops asking for it.

In entrataCertified valueExclusions the contract namesIn uscitaAdjustable valueExcluded amounts
4

Work the factor the way the formula works it

Indice dei prezzi

Take each work group's current index over its base index, weight it as the contract data weights it, sum the weighted ratios, subtract one, and apply the result to the adjustable value with the non adjustable portion held out. Record the index figures actually used against the month, not just the answer they produced.

Schermata, passaggio 4: Work the factor the way the formula works it (Indice dei prezzi, Recuperare il contract price adjustment sugli indici CPAP)
Indice dei prezzi: Work the factor the way the formula works it

Perché: The formula is arithmetic and its result is only as defensible as the inputs printed beside it. An adjustment presented as one number is a request to be trusted, and the quantity surveyor certifying it is not permitted to trust it. The same working also says what the next few months cost if the trend holds, which is a figure the cash flow should have and usually does not.

In entrataAdjustable valueCurrent indicesIn uscitaAdjustment factorAmount for the month
5

Certify the adjustment as its own item

Finanza

Put the adjustment on the payment certificate as a separate item with its working attached, never folded into the rates or into a lump sum under preliminaries. Carry the cumulative adjustment forward so the figure claimed this month is the movement since last month and not the total again.

Schermata, passaggio 5: Certify the adjustment as its own item (Finanza, Recuperare il contract price adjustment sugli indici CPAP)
Finanza: Certify the adjustment as its own item

Perché: An adjustment buried in the rates cannot be checked, and what cannot be checked is deferred to the final account, where it is settled at whatever both sides can still evidence years later. Standing on its own line it is either paid this month or refused this month with a reason, and a refusal with a reason is something you can answer.

In entrataAmount for the monthPayment certificateIn uscitaAdjustment certifiedCumulative position
6

Fix the date the indices stop moving

Scadenze

Record the date the works were to reach practical completion together with every extension of time actually granted, and put both under a reminder. Where the contract stops the adjustment moving once the delay is the contractor's own, work the later months on the indices current at that date rather than at the date the work was done.

Perché: This is the half of the provisions that runs against the contractor, and it is applied by the person certifying whether or not you applied it first. Knowing the date the indices freeze turns an extension of time from a programme argument into a money one, with a figure attached to every week of it, which is the only form in which such an argument gets settled quickly.

In entrataContract completion dateExtensions grantedIn uscitaIndex cut-off dateAdjustment at risk
7

Rework the provisional months for the final account

Post-calcolo

When the final index figures are published, rework every month that was certified on a provisional one, set the reworked cumulative adjustment against what was actually paid, and settle the difference in the final account instead of leaving it in a spreadsheet nobody opens again.

Perché: Revisions run both ways, so a job that never reworks them leaves money on both sides of the table and has no way of saying which. The reconciliation is ten minutes of arithmetic while the file is open and an unprovable claim two years after the last certificate.

In entrataFinal indicesCertified adjustmentsIn uscitaReconciled totalFinal account line
Moduli

Moduli di questo playbook

6 / 190 moduli della piattaforma

The market this case is written for

Sudafrica

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.