Casos prácticos / Comercial y contratos
Comercial y contratos

Recover contract price adjustment on the CPAP indices

Read the contract data to settle whether the job carries contract price adjustment, pin the base month and the work groups it names, separate the work the provisions reach from the work they do not, work the factor on the published indices and certify it as its own item.

7 pasos15 minContratista generalConsultoría de costos / QSSubcontratista especializado

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué haces en cada uno y por qué importa.

1

Settle whether the contract carries adjustment at all

Contratos

Read the contract data of the building agreement or of the civil engineering conditions and record four things before anything is measured: whether contract price adjustment applies, the base month it runs from, the work groups the contract names together with the weighting given to each, and the portion of the value the contract data holds non adjustable. Record as well what the contract says about the indices once the works are in delay.

Captura de pantalla, paso 1: Settle whether the contract carries adjustment at all (Contratos, Recover contract price adjustment on the CPAP indices)
Contratos: Settle whether the contract carries adjustment at all

Por que: A fixed price job and an adjustable one look identical on the drawings and differ by one page of the contract data. The difference is a year or two of inflation on the whole contract sum, and it is settled at tender stage by a person who is usually not the person certifying payment eighteen months later. Writing the terms down where the certificate is prepared is what stops the provisions being remembered at the final account.

EntradaSigned contractContract dataResultadoAdjustment terms recordedBase month fixed
2

Load the work group indices and pin the base month

Índice de precios

Load the index series the contract data names, the work group indices published for building or for civil engineering work, and pin the base index to the month the contract fixes rather than to the month work started on site. Keep every month's figure with the date it was published and flag the ones that are still provisional.

Captura de pantalla, paso 2: Load the work group indices and pin the base month (Índice de precios, Recover contract price adjustment on the CPAP indices)
Índice de precios: Load the work group indices and pin the base month

Por que: The indices are published behind the month they describe and the early figures are revised, so an adjustment worked on a provisional number will have to be worked again. Pinning the base once, at the start, is what stops every later certificate reopening the argument about which month the escalation runs from, which is the argument that costs the most and settles the least.

EntradaPublished index seriesWork groups the contract namesResultadoBase index pinnedMonthly index record
3

Separate the work the provisions reach from the work they do not

Presupuesto

Take the value certified for the period and set aside what the provisions do not adjust: materials on site that are not yet built in, the amounts the contract excludes by name, anything already adjusted under another clause, and the non adjustable portion the contract data fixes. What is left is the adjustable value for the month.

Captura de pantalla, paso 3: Separate the work the provisions reach from the work they do not (Presupuesto, Recover contract price adjustment on the CPAP indices)
Presupuesto: Separate the work the provisions reach from the work they do not

Por que: Applying escalation to the whole certificate is the commonest way an adjustment is refused in full rather than corrected in part. The exclusions are written in the contract and the person certifying knows them, so a submission that shows the split is checked once, while one that shows a single figure is queried every month until somebody stops asking for it.

EntradaCertified valueExclusions the contract namesResultadoAdjustable valueExcluded amounts
4

Work the factor the way the formula works it

Índice de precios

Take each work group's current index over its base index, weight it as the contract data weights it, sum the weighted ratios, subtract one, and apply the result to the adjustable value with the non adjustable portion held out. Record the index figures actually used against the month, not just the answer they produced.

Captura de pantalla, paso 4: Work the factor the way the formula works it (Índice de precios, Recover contract price adjustment on the CPAP indices)
Índice de precios: Work the factor the way the formula works it

Por que: The formula is arithmetic and its result is only as defensible as the inputs printed beside it. An adjustment presented as one number is a request to be trusted, and the quantity surveyor certifying it is not permitted to trust it. The same working also says what the next few months cost if the trend holds, which is a figure the cash flow should have and usually does not.

EntradaAdjustable valueCurrent indicesResultadoAdjustment factorAmount for the month
5

Certify the adjustment as its own item

Finanzas

Put the adjustment on the payment certificate as a separate item with its working attached, never folded into the rates or into a lump sum under preliminaries. Carry the cumulative adjustment forward so the figure claimed this month is the movement since last month and not the total again.

Captura de pantalla, paso 5: Certify the adjustment as its own item (Finanzas, Recover contract price adjustment on the CPAP indices)
Finanzas: Certify the adjustment as its own item

Por que: An adjustment buried in the rates cannot be checked, and what cannot be checked is deferred to the final account, where it is settled at whatever both sides can still evidence years later. Standing on its own line it is either paid this month or refused this month with a reason, and a refusal with a reason is something you can answer.

EntradaAmount for the monthPayment certificateResultadoAdjustment certifiedCumulative position
6

Fix the date the indices stop moving

Plazos

Record the date the works were to reach practical completion together with every extension of time actually granted, and put both under a reminder. Where the contract stops the adjustment moving once the delay is the contractor's own, work the later months on the indices current at that date rather than at the date the work was done.

Por que: This is the half of the provisions that runs against the contractor, and it is applied by the person certifying whether or not you applied it first. Knowing the date the indices freeze turns an extension of time from a programme argument into a money one, with a figure attached to every week of it, which is the only form in which such an argument gets settled quickly.

EntradaContract completion dateExtensions grantedResultadoIndex cut-off dateAdjustment at risk
7

Rework the provisional months for the final account

Postcálculo

When the final index figures are published, rework every month that was certified on a provisional one, set the reworked cumulative adjustment against what was actually paid, and settle the difference in the final account instead of leaving it in a spreadsheet nobody opens again.

Por que: Revisions run both ways, so a job that never reworks them leaves money on both sides of the table and has no way of saying which. The reconciliation is ten minutes of arithmetic while the file is open and an unprovable claim two years after the last certificate.

EntradaFinal indicesCertified adjustmentsResultadoReconciled totalFinal account line
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

The market this case is written for

Sudáfrica

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Más en Comercial y contratos

Comercial y contratos

Estimación de pago y conciliación

Valúa el trabajo ejecutado en el periodo contra el contrato, presenta la estimación con la e…

3 pasos12 minAbrir