यह तय करने के लिए contract data पढ़ें कि क्या work में contract price adjustment है, वह आधार महीना और work groups तय करें जिन्हें यह नाम देता है, उस work को अलग करें जहां प्रावधान पहुंचते हैं उससे जहां नहीं पहुंचते, प्रकाशित सूचकांकों पर फ़ैक्टर की गणना करें, और इसे एक अलग मद के रूप में प्रमाणित करें।

7 चरण15 मिनटमुख्य ठेकेदारलागत परामर्श / QS फर्मविशेषज्ञ उपठेकेदार

यह कैसे काम करता है, चरण दर चरण

प्लेटफ़ॉर्म भर में 7 चरण - हर एक में आप क्या करते हैं और यह क्यों मायने रखता है।

1

Settle whether the contract carries adjustment at all

अनुबंध

Read the contract data of the building agreement or of the civil engineering conditions and record four things before anything is measured: whether contract price adjustment applies, the base month it runs from, the work groups the contract names together with the weighting given to each, and the portion of the value the contract data holds non adjustable. Record as well what the contract says about the indices once the works are in delay.

स्क्रीनशॉट, चरण 1: Settle whether the contract carries adjustment at all (अनुबंध, CPAP सूचकांकों पर contract price adjustment वसूलें)
अनुबंध: Settle whether the contract carries adjustment at all

क्यों: A fixed price job and an adjustable one look identical on the drawings and differ by one page of the contract data. The difference is a year or two of inflation on the whole contract sum, and it is settled at tender stage by a person who is usually not the person certifying payment eighteen months later. Writing the terms down where the certificate is prepared is what stops the provisions being remembered at the final account.

इनपुटSigned contractContract dataपरिणामAdjustment terms recordedBase month fixed
2

Load the work group indices and pin the base month

मूल्य सूचकांक

Load the index series the contract data names, the work group indices published for building or for civil engineering work, and pin the base index to the month the contract fixes rather than to the month work started on site. Keep every month's figure with the date it was published and flag the ones that are still provisional.

स्क्रीनशॉट, चरण 2: Load the work group indices and pin the base month (मूल्य सूचकांक, CPAP सूचकांकों पर contract price adjustment वसूलें)
मूल्य सूचकांक: Load the work group indices and pin the base month

क्यों: The indices are published behind the month they describe and the early figures are revised, so an adjustment worked on a provisional number will have to be worked again. Pinning the base once, at the start, is what stops every later certificate reopening the argument about which month the escalation runs from, which is the argument that costs the most and settles the least.

इनपुटPublished index seriesWork groups the contract namesपरिणामBase index pinnedMonthly index record
3

Separate the work the provisions reach from the work they do not

मात्रा विवरण

Take the value certified for the period and set aside what the provisions do not adjust: materials on site that are not yet built in, the amounts the contract excludes by name, anything already adjusted under another clause, and the non adjustable portion the contract data fixes. What is left is the adjustable value for the month.

स्क्रीनशॉट, चरण 3: Separate the work the provisions reach from the work they do not (मात्रा विवरण, CPAP सूचकांकों पर contract price adjustment वसूलें)
मात्रा विवरण: Separate the work the provisions reach from the work they do not

क्यों: Applying escalation to the whole certificate is the commonest way an adjustment is refused in full rather than corrected in part. The exclusions are written in the contract and the person certifying knows them, so a submission that shows the split is checked once, while one that shows a single figure is queried every month until somebody stops asking for it.

इनपुटCertified valueExclusions the contract namesपरिणामAdjustable valueExcluded amounts
4

Work the factor the way the formula works it

मूल्य सूचकांक

Take each work group's current index over its base index, weight it as the contract data weights it, sum the weighted ratios, subtract one, and apply the result to the adjustable value with the non adjustable portion held out. Record the index figures actually used against the month, not just the answer they produced.

स्क्रीनशॉट, चरण 4: Work the factor the way the formula works it (मूल्य सूचकांक, CPAP सूचकांकों पर contract price adjustment वसूलें)
मूल्य सूचकांक: Work the factor the way the formula works it

क्यों: The formula is arithmetic and its result is only as defensible as the inputs printed beside it. An adjustment presented as one number is a request to be trusted, and the quantity surveyor certifying it is not permitted to trust it. The same working also says what the next few months cost if the trend holds, which is a figure the cash flow should have and usually does not.

इनपुटAdjustable valueCurrent indicesपरिणामAdjustment factorAmount for the month
5

Certify the adjustment as its own item

वित्त

Put the adjustment on the payment certificate as a separate item with its working attached, never folded into the rates or into a lump sum under preliminaries. Carry the cumulative adjustment forward so the figure claimed this month is the movement since last month and not the total again.

स्क्रीनशॉट, चरण 5: Certify the adjustment as its own item (वित्त, CPAP सूचकांकों पर contract price adjustment वसूलें)
वित्त: Certify the adjustment as its own item

क्यों: An adjustment buried in the rates cannot be checked, and what cannot be checked is deferred to the final account, where it is settled at whatever both sides can still evidence years later. Standing on its own line it is either paid this month or refused this month with a reason, and a refusal with a reason is something you can answer.

इनपुटAmount for the monthPayment certificateपरिणामAdjustment certifiedCumulative position
6

Fix the date the indices stop moving

समय-सीमाएँ

Record the date the works were to reach practical completion together with every extension of time actually granted, and put both under a reminder. Where the contract stops the adjustment moving once the delay is the contractor's own, work the later months on the indices current at that date rather than at the date the work was done.

क्यों: This is the half of the provisions that runs against the contractor, and it is applied by the person certifying whether or not you applied it first. Knowing the date the indices freeze turns an extension of time from a programme argument into a money one, with a figure attached to every week of it, which is the only form in which such an argument gets settled quickly.

इनपुटContract completion dateExtensions grantedपरिणामIndex cut-off dateAdjustment at risk
7

Rework the provisional months for the final account

पश्च-गणना

When the final index figures are published, rework every month that was certified on a provisional one, set the reworked cumulative adjustment against what was actually paid, and settle the difference in the final account instead of leaving it in a spreadsheet nobody opens again.

क्यों: Revisions run both ways, so a job that never reworks them leaves money on both sides of the table and has no way of saying which. The reconciliation is ten minutes of arithmetic while the file is open and an unprovable claim two years after the last certificate.

इनपुटFinal indicesCertified adjustmentsपरिणामReconciled totalFinal account line
मॉड्यूल

इस प्लेबुक के मॉड्यूल

प्लेटफ़ॉर्म के 190 में से 6 मॉड्यूल

The market this case is written for

दक्षिण अफ़्रीका

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

वाणिज्यिक और अनुबंध में और देखें

वाणिज्यिक और अनुबंध

उपठेकेदार पैकेज चलाएँ

किसी उपठेकेदार को एक ट्रेड पैकेज दें, इसे मूल्यों की अनुसूची और रिटेंशन के साथ एक उपअनुबंध प…

3 चरण11 मिनटखोलें
वाणिज्यिक और अनुबंध

भुगतान आवेदन और मिलान

इस अवधि में किए गए काम का अनुबंध के अनुसार मूल्यांकन करें, इसके पीछे के प्रमाण के साथ आवेदन…

3 चरण12 मिनटखोलें