CPAP 지수에 따라 contract price adjustment 회수하기

contract data를 읽어 현장이 contract price adjustment를 지니는지 확인하고, 기준월과 거기 명명된 work groups를 확정하고, 규정이 미치는 work와 미치지 않는 work를 구분하고, 공표된 지수로 계수를 계산하고, 이를 별도 항목으로 인증한다.

7단계15 분종합건설사원가 컨설팅 / 적산 업체전문건설사

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Settle whether the contract carries adjustment at all

계약

Read the contract data of the building agreement or of the civil engineering conditions and record four things before anything is measured: whether contract price adjustment applies, the base month it runs from, the work groups the contract names together with the weighting given to each, and the portion of the value the contract data holds non adjustable. Record as well what the contract says about the indices once the works are in delay.

스크린샷, 1단계: Settle whether the contract carries adjustment at all (계약, CPAP 지수에 따라 contract price adjustment 회수하기)
계약: Settle whether the contract carries adjustment at all

이유: A fixed price job and an adjustable one look identical on the drawings and differ by one page of the contract data. The difference is a year or two of inflation on the whole contract sum, and it is settled at tender stage by a person who is usually not the person certifying payment eighteen months later. Writing the terms down where the certificate is prepared is what stops the provisions being remembered at the final account.

입력Signed contractContract data결과Adjustment terms recordedBase month fixed
2

Load the work group indices and pin the base month

물가 지수

Load the index series the contract data names, the work group indices published for building or for civil engineering work, and pin the base index to the month the contract fixes rather than to the month work started on site. Keep every month's figure with the date it was published and flag the ones that are still provisional.

스크린샷, 2단계: Load the work group indices and pin the base month (물가 지수, CPAP 지수에 따라 contract price adjustment 회수하기)
물가 지수: Load the work group indices and pin the base month

이유: The indices are published behind the month they describe and the early figures are revised, so an adjustment worked on a provisional number will have to be worked again. Pinning the base once, at the start, is what stops every later certificate reopening the argument about which month the escalation runs from, which is the argument that costs the most and settles the least.

입력Published index seriesWork groups the contract names결과Base index pinnedMonthly index record
3

Separate the work the provisions reach from the work they do not

내역서

Take the value certified for the period and set aside what the provisions do not adjust: materials on site that are not yet built in, the amounts the contract excludes by name, anything already adjusted under another clause, and the non adjustable portion the contract data fixes. What is left is the adjustable value for the month.

스크린샷, 3단계: Separate the work the provisions reach from the work they do not (내역서, CPAP 지수에 따라 contract price adjustment 회수하기)
내역서: Separate the work the provisions reach from the work they do not

이유: Applying escalation to the whole certificate is the commonest way an adjustment is refused in full rather than corrected in part. The exclusions are written in the contract and the person certifying knows them, so a submission that shows the split is checked once, while one that shows a single figure is queried every month until somebody stops asking for it.

입력Certified valueExclusions the contract names결과Adjustable valueExcluded amounts
4

Work the factor the way the formula works it

물가 지수

Take each work group's current index over its base index, weight it as the contract data weights it, sum the weighted ratios, subtract one, and apply the result to the adjustable value with the non adjustable portion held out. Record the index figures actually used against the month, not just the answer they produced.

스크린샷, 4단계: Work the factor the way the formula works it (물가 지수, CPAP 지수에 따라 contract price adjustment 회수하기)
물가 지수: Work the factor the way the formula works it

이유: The formula is arithmetic and its result is only as defensible as the inputs printed beside it. An adjustment presented as one number is a request to be trusted, and the quantity surveyor certifying it is not permitted to trust it. The same working also says what the next few months cost if the trend holds, which is a figure the cash flow should have and usually does not.

입력Adjustable valueCurrent indices결과Adjustment factorAmount for the month
5

Certify the adjustment as its own item

재무

Put the adjustment on the payment certificate as a separate item with its working attached, never folded into the rates or into a lump sum under preliminaries. Carry the cumulative adjustment forward so the figure claimed this month is the movement since last month and not the total again.

스크린샷, 5단계: Certify the adjustment as its own item (재무, CPAP 지수에 따라 contract price adjustment 회수하기)
재무: Certify the adjustment as its own item

이유: An adjustment buried in the rates cannot be checked, and what cannot be checked is deferred to the final account, where it is settled at whatever both sides can still evidence years later. Standing on its own line it is either paid this month or refused this month with a reason, and a refusal with a reason is something you can answer.

입력Amount for the monthPayment certificate결과Adjustment certifiedCumulative position
6

Fix the date the indices stop moving

마감일

Record the date the works were to reach practical completion together with every extension of time actually granted, and put both under a reminder. Where the contract stops the adjustment moving once the delay is the contractor's own, work the later months on the indices current at that date rather than at the date the work was done.

이유: This is the half of the provisions that runs against the contractor, and it is applied by the person certifying whether or not you applied it first. Knowing the date the indices freeze turns an extension of time from a programme argument into a money one, with a figure attached to every week of it, which is the only form in which such an argument gets settled quickly.

입력Contract completion dateExtensions granted결과Index cut-off dateAdjustment at risk
7

Rework the provisional months for the final account

사후 원가계산

When the final index figures are published, rework every month that was certified on a provisional one, set the reworked cumulative adjustment against what was actually paid, and settle the difference in the final account instead of leaving it in a spreadsheet nobody opens again.

이유: Revisions run both ways, so a job that never reworks them leaves money on both sides of the table and has no way of saying which. The reconciliation is ten minutes of arithmetic while the file is open and an unprovable claim two years after the last certificate.

입력Final indicesCertified adjustments결과Reconciled totalFinal account line
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6개

The market this case is written for

남아프리카

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

상업 및 계약 카테고리의 더 보기

상업 및 계약

변경사항을 유상 변경계약으로 전환

신선할 때 범위 변경을 기록하고, 합의된 단가로 계약 변경계약으로 산정한 뒤 다음 기성청구에 포함시켜, 추가 작업을 조용히 흡수하지 않고 회수합니다.

3단계11 분열기
상업 및 계약

협력업체 패키지 운영

협력업체에 공종 패키지를 발주하고, 기성 내역서와 유보금 조건을 포함한 하도급 계약으로 전환한 뒤, 실제 완료된 작업에 대해 기성 청구별로 지급합니다.

3단계11 분열기
상업 및 계약

기성 청구 및 대사

계약서 대비 해당 기간 시공된 물량을 평가하고, 근거 자료와 함께 기성 청구를 제출하며, 승인된 금액을 실제 입금액과 대조 확인한다.

3단계12 분열기