Construction Contracts Act के तहत retention money को trust में रखें

दर्ज करें कि अनुबंध आपको क्या रोकने की अनुमति देता है, इसे एक नामित पंक्ति के रूप में रोकें, इसे वहां रखें जहां Act चाहता है, वह बहीखाता रखें जो हर उपठेकेदार का हिस्सा पहचान योग्य बनाता है, इसे उस पक्ष को रिपोर्ट करें जिससे यह रोका गया है, और इसे उस तारीख़ पर जारी करें जो अनुबंध तय करता है।

7 चरण14 मिनटमुख्य ठेकेदारडेवलपर / क्लाइंटलागत परामर्श / QS फर्म

यह कैसे काम करता है, चरण दर चरण

प्लेटफ़ॉर्म भर में 7 चरण - हर एक में आप क्या करते हैं और यह क्यों मायने रखता है।

1

Record what the contract actually lets you retain

अनुबंध

Take the retention terms off the subcontract and record them where the people who compute payments can read them: the percentage, the maximum the contract caps retention at, what event releases the first half, what event releases the balance, and the date the contract was signed or last renewed. Record as well whether this is a commercial construction contract, because the retentions regime reaches those and not a residential occupier's own contract.

स्क्रीनशॉट, चरण 1: Record what the contract actually lets you retain (अनुबंध, Construction Contracts Act के तहत retention money को trust में रखें)
अनुबंध: Record what the contract actually lets you retain

क्यों: The signature date decides which version of the rules applies, and that is not a detail. Contracts entered into or renewed from 5 October 2023 sit under the automatic trust and the reporting duty the amendment introduced, while older ones sit under the lighter 2017 regime. A company running one process for a book of contracts written under both is complying with whichever one it happened to build its spreadsheet around.

इनपुटSigned subcontractRetention terms as writtenपरिणामRetention rate and cap on recordRelease trigger and dates
2

Withhold it as a line, not as a smaller total

फ़ाइनेंस

When you schedule a subcontractor's payment, take the retention as a separate deduction line carrying the period it relates to and the cumulative amount now held, and let the net figure fall out of it. Stop deducting once the cumulative total reaches the contract cap rather than continuing at the percentage.

स्क्रीनशॉट, चरण 2: Withhold it as a line, not as a smaller total (फ़ाइनेंस, Construction Contracts Act के तहत retention money को trust में रखें)
फ़ाइनेंस: Withhold it as a line, not as a smaller total

क्यों: A retention that exists only as the difference between two totals cannot be traced, and the whole regime rests on the money being identifiable as somebody else's. It is also the point at which the trust starts, so the day this line is created is the day the duties attach. A payer who cannot say which line created the trust is a payer who cannot show when the reporting clock began.

इनपुटSubcontractor payment claimRetention rate and cap on recordपरिणामRetention shown as its own lineNet amount scheduled for payment
3

Put the money where the Act says it has to sit

रोक राशि

Post each withheld amount to the retention ledger against the subcontractor it belongs to, and record which bank account it is held in or which complying instrument covers it. The account has to be used only for retention money, and the ledger has to name the party, the amount, the contract and the date it was withheld.

स्क्रीनशॉट, चरण 3: Put the money where the Act says it has to sit (रोक राशि, Construction Contracts Act के तहत retention money को trust में रखें)
रोक राशि: Put the money where the Act says it has to sit

क्यों: The 2023 amendment makes this money trust money automatically, which means it is outside the reach of your own creditors if the company fails, but only to the extent it can be identified. Money mixed into the working account and spent as float is money a liquidator will treat as yours, and the subcontractors it belonged to join the queue with everyone else. Using retention money as working capital is also an offence in itself.

इनपुटRetention shown as its own lineTrust account or complying instrumentपरिणामLedger of who holds whatBalance held per subcontractor
4

File the evidence that the money is where you say

दस्तावेज़

Keep the bank statement for the retention account for every period alongside the ledger it should agree with, and file the complying instrument itself where retention is covered by a guarantee or a policy rather than by cash. Keep the instrument's expiry date visible, because an expired guarantee leaves the money uncovered while the ledger still says it is fine.

स्क्रीनशॉट, चरण 4: File the evidence that the money is where you say (दस्तावेज़, Construction Contracts Act के तहत retention money को trust में रखें)
दस्तावेज़: File the evidence that the money is where you say

क्यों: A ledger is an assertion and a bank statement is evidence, and the difference matters on the one day anyone asks. The regulator, an insolvency practitioner and a subcontractor's solicitor all ask the same question in the same order: what is held, where is it, and show me. Answering it takes minutes if the two documents were filed together each month and weeks if they were not.

इनपुटLedger of who holds whatBank statements and instrumentपरिणामCustody evidence filedAudit trail per period
5

Tell each party what you are holding from them

पत्राचार

Send each subcontractor a report of the retention money held from them: the amount, the date it was withheld, where it is held or what instrument covers it, and how the total moved since the last report. Do it as soon as practicable after retention is first withheld from them and then on a regular cycle of no more than three months, and keep the sent copy against the contract.

स्क्रीनशॉट, चरण 5: Tell each party what you are holding from them (पत्राचार, Construction Contracts Act के तहत retention money को trust में रखें)
पत्राचार: Tell each party what you are holding from them

क्यों: This duty is the part of the regime most often missed, because nothing on site stops when it is skipped and no subcontractor chases a report they have never seen. It is still an obligation with an offence behind it, and the reports are also the cheapest defence there is: a party who has been told the same figure every quarter does not open the final account arguing about what was held.

इनपुटBalance held per subcontractorReporting periodपरिणामRetention report sentProof of what was sent and when
6

Tie each release to the defects period that triggers it

वारंटी और दोष दायित्व

Hold each subcontractor's retention against the defects liability period it is released by: the first half at practical completion and the balance when the period ends. Where a release is being held back, record the defect it is held against, who owes the fix and by when, rather than letting the date pass in silence.

क्यों: The release trigger is not a date somebody typed in, it is the end of a period that the defects record already tracks, so keeping the two apart is how a retention gets held for a year after the obligation it secured expired. A held release with a named defect against it is a commercial position. A held release with nothing against it is trust money that should have gone back, and a subcontractor can put that straight into adjudication.

इनपुटRelease trigger and datesDefects positionपरिणामRelease dates under watchWarning before each release
7

Reconcile the ledger against the account every period

रिपोर्ट

Read the total the ledger says is held against the balance the account actually carries, across every project at once, and name the difference if there is one. Do it on the same day each period rather than when somebody asks.

स्क्रीनशॉट, चरण 7: Reconcile the ledger against the account every period (रिपोर्ट, Construction Contracts Act के तहत retention money को trust में रखें)
रिपोर्ट: Reconcile the ledger against the account every period

क्यों: A shortfall between the ledger and the account is the one number in this whole case that cannot be argued about, and it grows quietly: a release paid from the working account, a deduction never banked, a project closed without its balance moving. Found in the month it happens it is a transfer. Found at liquidation it is the evidence in somebody else's case.

इनपुटLedger of who holds whatRetention account balanceपरिणामShortfall named if there is oneRetention position across projects
मॉड्यूल

इस प्लेबुक के मॉड्यूल

प्लेटफ़ॉर्म के 190 में से 6 मॉड्यूल

The market this case is written for

न्यूज़ीलैंड

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

वाणिज्यिक और अनुबंध में और देखें

वाणिज्यिक और अनुबंध

उपठेकेदार पैकेज चलाएँ

किसी उपठेकेदार को एक ट्रेड पैकेज दें, इसे मूल्यों की अनुसूची और रिटेंशन के साथ एक उपअनुबंध प…

3 चरण11 मिनटखोलें
वाणिज्यिक और अनुबंध

भुगतान आवेदन और मिलान

इस अवधि में किए गए काम का अनुबंध के अनुसार मूल्यांकन करें, इसके पीछे के प्रमाण के साथ आवेदन…

3 चरण12 मिनटखोलें