Retenha retention money em trust ao abrigo do Construction Contracts Act

Registe o que o contrato lhe permite reter, retenha-o como uma linha nomeada, coloque-o onde o Act exige que fique, mantenha o livro que torna identificável a parte de cada subempreiteiro, informe a parte a quem foi retido e liberte-o na data que o contrato fixa.

7 etapas14 minEmpreiteiro geralPromotor / clienteConsultoria de custos / QS

Como funciona, passo a passo

7 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Record what the contract actually lets you retain

Contratos

Take the retention terms off the subcontract and record them where the people who compute payments can read them: the percentage, the maximum the contract caps retention at, what event releases the first half, what event releases the balance, and the date the contract was signed or last renewed. Record as well whether this is a commercial construction contract, because the retentions regime reaches those and not a residential occupier's own contract.

Captura de tela, etapa 1: Record what the contract actually lets you retain (Contratos, Retenha retention money em trust ao abrigo do Construction Contracts Act)
Contratos: Record what the contract actually lets you retain

Por quê: The signature date decides which version of the rules applies, and that is not a detail. Contracts entered into or renewed from 5 October 2023 sit under the automatic trust and the reporting duty the amendment introduced, while older ones sit under the lighter 2017 regime. A company running one process for a book of contracts written under both is complying with whichever one it happened to build its spreadsheet around.

EntradaSigned subcontractRetention terms as writtenResultadoRetention rate and cap on recordRelease trigger and dates
2

Withhold it as a line, not as a smaller total

Finanças

When you schedule a subcontractor's payment, take the retention as a separate deduction line carrying the period it relates to and the cumulative amount now held, and let the net figure fall out of it. Stop deducting once the cumulative total reaches the contract cap rather than continuing at the percentage.

Captura de tela, etapa 2: Withhold it as a line, not as a smaller total (Finanças, Retenha retention money em trust ao abrigo do Construction Contracts Act)
Finanças: Withhold it as a line, not as a smaller total

Por quê: A retention that exists only as the difference between two totals cannot be traced, and the whole regime rests on the money being identifiable as somebody else's. It is also the point at which the trust starts, so the day this line is created is the day the duties attach. A payer who cannot say which line created the trust is a payer who cannot show when the reporting clock began.

EntradaSubcontractor payment claimRetention rate and cap on recordResultadoRetention shown as its own lineNet amount scheduled for payment
3

Put the money where the Act says it has to sit

Retenção

Post each withheld amount to the retention ledger against the subcontractor it belongs to, and record which bank account it is held in or which complying instrument covers it. The account has to be used only for retention money, and the ledger has to name the party, the amount, the contract and the date it was withheld.

Captura de tela, etapa 3: Put the money where the Act says it has to sit (Retenção, Retenha retention money em trust ao abrigo do Construction Contracts Act)
Retenção: Put the money where the Act says it has to sit

Por quê: The 2023 amendment makes this money trust money automatically, which means it is outside the reach of your own creditors if the company fails, but only to the extent it can be identified. Money mixed into the working account and spent as float is money a liquidator will treat as yours, and the subcontractors it belonged to join the queue with everyone else. Using retention money as working capital is also an offence in itself.

EntradaRetention shown as its own lineTrust account or complying instrumentResultadoLedger of who holds whatBalance held per subcontractor
4

File the evidence that the money is where you say

Documentos

Keep the bank statement for the retention account for every period alongside the ledger it should agree with, and file the complying instrument itself where retention is covered by a guarantee or a policy rather than by cash. Keep the instrument's expiry date visible, because an expired guarantee leaves the money uncovered while the ledger still says it is fine.

Captura de tela, etapa 4: File the evidence that the money is where you say (Documentos, Retenha retention money em trust ao abrigo do Construction Contracts Act)
Documentos: File the evidence that the money is where you say

Por quê: A ledger is an assertion and a bank statement is evidence, and the difference matters on the one day anyone asks. The regulator, an insolvency practitioner and a subcontractor's solicitor all ask the same question in the same order: what is held, where is it, and show me. Answering it takes minutes if the two documents were filed together each month and weeks if they were not.

EntradaLedger of who holds whatBank statements and instrumentResultadoCustody evidence filedAudit trail per period
5

Tell each party what you are holding from them

Correspondência

Send each subcontractor a report of the retention money held from them: the amount, the date it was withheld, where it is held or what instrument covers it, and how the total moved since the last report. Do it as soon as practicable after retention is first withheld from them and then on a regular cycle of no more than three months, and keep the sent copy against the contract.

Captura de tela, etapa 5: Tell each party what you are holding from them (Correspondência, Retenha retention money em trust ao abrigo do Construction Contracts Act)
Correspondência: Tell each party what you are holding from them

Por quê: This duty is the part of the regime most often missed, because nothing on site stops when it is skipped and no subcontractor chases a report they have never seen. It is still an obligation with an offence behind it, and the reports are also the cheapest defence there is: a party who has been told the same figure every quarter does not open the final account arguing about what was held.

EntradaBalance held per subcontractorReporting periodResultadoRetention report sentProof of what was sent and when
6

Tie each release to the defects period that triggers it

Garantias e responsabilidade por defeitos

Hold each subcontractor's retention against the defects liability period it is released by: the first half at practical completion and the balance when the period ends. Where a release is being held back, record the defect it is held against, who owes the fix and by when, rather than letting the date pass in silence.

Por quê: The release trigger is not a date somebody typed in, it is the end of a period that the defects record already tracks, so keeping the two apart is how a retention gets held for a year after the obligation it secured expired. A held release with a named defect against it is a commercial position. A held release with nothing against it is trust money that should have gone back, and a subcontractor can put that straight into adjudication.

EntradaRelease trigger and datesDefects positionResultadoRelease dates under watchWarning before each release
7

Reconcile the ledger against the account every period

Relatórios

Read the total the ledger says is held against the balance the account actually carries, across every project at once, and name the difference if there is one. Do it on the same day each period rather than when somebody asks.

Captura de tela, etapa 7: Reconcile the ledger against the account every period (Relatórios, Retenha retention money em trust ao abrigo do Construction Contracts Act)
Relatórios: Reconcile the ledger against the account every period

Por quê: A shortfall between the ledger and the account is the one number in this whole case that cannot be argued about, and it grows quietly: a release paid from the working account, a deduction never banked, a project closed without its balance moving. Found in the month it happens it is a transfer. Found at liquidation it is the evidence in somebody else's case.

EntradaLedger of who holds whatRetention account balanceResultadoShortfall named if there is oneRetention position across projects
Módulos

Módulos deste playbook

6 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Nova Zelândia

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • NZS 3910
  • Construction Contracts Act

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Comercial e contratos

Comercial e contratos

Gerir um pacote de subempreitada

Adjudique um pacote de trabalhos a um subempreiteiro, coloque-o num subcontrato com um mapa…

3 etapas11 minAbrir
Comercial e contratos

Fatura de pagamento e conciliação

Valorize o trabalho executado neste período face ao contrato, apresente a fatura com a evidê…

3 etapas12 minAbrir