케이스 / 상업 및 계약
상업 및 계약

Construction Contracts Act에 따라 retention money를 trust로 보유하기

계약이 보류를 허용하는 범위를 기록하고, 이를 명명된 항목으로 보류하고, Act가 요구하는 위치에 두고, 각 하도급업체의 몫을 식별할 수 있게 하는 장부를 유지하고, 보류당한 상대방에게 보고하고, 계약이 정한 날짜에 해제한다.

7단계14 분종합건설사시행사 / 발주처원가 컨설팅 / 적산 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Record what the contract actually lets you retain

계약

Take the retention terms off the subcontract and record them where the people who compute payments can read them: the percentage, the maximum the contract caps retention at, what event releases the first half, what event releases the balance, and the date the contract was signed or last renewed. Record as well whether this is a commercial construction contract, because the retentions regime reaches those and not a residential occupier's own contract.

스크린샷, 1단계: Record what the contract actually lets you retain (계약, Construction Contracts Act에 따라 retention money를 trust로 보유하기)
계약: Record what the contract actually lets you retain

이유: The signature date decides which version of the rules applies, and that is not a detail. Contracts entered into or renewed from 5 October 2023 sit under the automatic trust and the reporting duty the amendment introduced, while older ones sit under the lighter 2017 regime. A company running one process for a book of contracts written under both is complying with whichever one it happened to build its spreadsheet around.

입력Signed subcontractRetention terms as written결과Retention rate and cap on recordRelease trigger and dates
2

Withhold it as a line, not as a smaller total

재무

When you schedule a subcontractor's payment, take the retention as a separate deduction line carrying the period it relates to and the cumulative amount now held, and let the net figure fall out of it. Stop deducting once the cumulative total reaches the contract cap rather than continuing at the percentage.

스크린샷, 2단계: Withhold it as a line, not as a smaller total (재무, Construction Contracts Act에 따라 retention money를 trust로 보유하기)
재무: Withhold it as a line, not as a smaller total

이유: A retention that exists only as the difference between two totals cannot be traced, and the whole regime rests on the money being identifiable as somebody else's. It is also the point at which the trust starts, so the day this line is created is the day the duties attach. A payer who cannot say which line created the trust is a payer who cannot show when the reporting clock began.

입력Subcontractor payment claimRetention rate and cap on record결과Retention shown as its own lineNet amount scheduled for payment
3

Put the money where the Act says it has to sit

유보금

Post each withheld amount to the retention ledger against the subcontractor it belongs to, and record which bank account it is held in or which complying instrument covers it. The account has to be used only for retention money, and the ledger has to name the party, the amount, the contract and the date it was withheld.

스크린샷, 3단계: Put the money where the Act says it has to sit (유보금, Construction Contracts Act에 따라 retention money를 trust로 보유하기)
유보금: Put the money where the Act says it has to sit

이유: The 2023 amendment makes this money trust money automatically, which means it is outside the reach of your own creditors if the company fails, but only to the extent it can be identified. Money mixed into the working account and spent as float is money a liquidator will treat as yours, and the subcontractors it belonged to join the queue with everyone else. Using retention money as working capital is also an offence in itself.

입력Retention shown as its own lineTrust account or complying instrument결과Ledger of who holds whatBalance held per subcontractor
4

File the evidence that the money is where you say

문서

Keep the bank statement for the retention account for every period alongside the ledger it should agree with, and file the complying instrument itself where retention is covered by a guarantee or a policy rather than by cash. Keep the instrument's expiry date visible, because an expired guarantee leaves the money uncovered while the ledger still says it is fine.

스크린샷, 4단계: File the evidence that the money is where you say (문서, Construction Contracts Act에 따라 retention money를 trust로 보유하기)
문서: File the evidence that the money is where you say

이유: A ledger is an assertion and a bank statement is evidence, and the difference matters on the one day anyone asks. The regulator, an insolvency practitioner and a subcontractor's solicitor all ask the same question in the same order: what is held, where is it, and show me. Answering it takes minutes if the two documents were filed together each month and weeks if they were not.

입력Ledger of who holds whatBank statements and instrument결과Custody evidence filedAudit trail per period
5

Tell each party what you are holding from them

서신

Send each subcontractor a report of the retention money held from them: the amount, the date it was withheld, where it is held or what instrument covers it, and how the total moved since the last report. Do it as soon as practicable after retention is first withheld from them and then on a regular cycle of no more than three months, and keep the sent copy against the contract.

스크린샷, 5단계: Tell each party what you are holding from them (서신, Construction Contracts Act에 따라 retention money를 trust로 보유하기)
서신: Tell each party what you are holding from them

이유: This duty is the part of the regime most often missed, because nothing on site stops when it is skipped and no subcontractor chases a report they have never seen. It is still an obligation with an offence behind it, and the reports are also the cheapest defence there is: a party who has been told the same figure every quarter does not open the final account arguing about what was held.

입력Balance held per subcontractorReporting period결과Retention report sentProof of what was sent and when
6

Tie each release to the defects period that triggers it

보증 및 하자담보책임

Hold each subcontractor's retention against the defects liability period it is released by: the first half at practical completion and the balance when the period ends. Where a release is being held back, record the defect it is held against, who owes the fix and by when, rather than letting the date pass in silence.

이유: The release trigger is not a date somebody typed in, it is the end of a period that the defects record already tracks, so keeping the two apart is how a retention gets held for a year after the obligation it secured expired. A held release with a named defect against it is a commercial position. A held release with nothing against it is trust money that should have gone back, and a subcontractor can put that straight into adjudication.

입력Release trigger and datesDefects position결과Release dates under watchWarning before each release
7

Reconcile the ledger against the account every period

보고서

Read the total the ledger says is held against the balance the account actually carries, across every project at once, and name the difference if there is one. Do it on the same day each period rather than when somebody asks.

스크린샷, 7단계: Reconcile the ledger against the account every period (보고서, Construction Contracts Act에 따라 retention money를 trust로 보유하기)
보고서: Reconcile the ledger against the account every period

이유: A shortfall between the ledger and the account is the one number in this whole case that cannot be argued about, and it grows quietly: a release paid from the working account, a deduction never banked, a project closed without its balance moving. Found in the month it happens it is a transfer. Found at liquidation it is the evidence in somebody else's case.

입력Ledger of who holds whatRetention account balance결과Shortfall named if there is oneRetention position across projects
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6개

The market this case is written for

뉴질랜드

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

상업 및 계약 카테고리의 더 보기

상업 및 계약

변경사항을 유상 변경계약으로 전환

신선할 때 범위 변경을 기록하고, 합의된 단가로 계약 변경계약으로 산정한 뒤 다음 기성청구에 포함시켜, 추가 작업을 조용히 흡수하지 않고 회수합니다.

3단계11 분열기
상업 및 계약

협력업체 패키지 운영

협력업체에 공종 패키지를 발주하고, 기성 내역서와 유보금 조건을 포함한 하도급 계약으로 전환한 뒤, 실제 완료된 작업에 대해 기성 청구별로 지급합니다.

3단계11 분열기
상업 및 계약

기성 청구 및 대사

계약서 대비 해당 기간 시공된 물량을 평가하고, 근거 자료와 함께 기성 청구를 제출하며, 승인된 금액을 실제 입금액과 대조 확인한다.

3단계12 분열기