Notera vad kontraktet låter dig hålla inne, håll inne det som en namngiven post, placera det där lagen kräver att det ska ligga, för den bok som gör varje underentreprenörs andel identifierbar, rapportera till parten det hålls inne från och frigör det på det datum kontraktet fastställer.

7 steg14 minGeneralentreprenörByggherre / beställareKostnadsrådgivning / QS

Så fungerar det, steg för steg

7 steg genom plattformen - vad du gör i varje och varför det spelar roll.

1

Record what the contract actually lets you retain

Kontrakt

Take the retention terms off the subcontract and record them where the people who compute payments can read them: the percentage, the maximum the contract caps retention at, what event releases the first half, what event releases the balance, and the date the contract was signed or last renewed. Record as well whether this is a commercial construction contract, because the retentions regime reaches those and not a residential occupier's own contract.

Skärmbild, steg 1: Record what the contract actually lets you retain (Kontrakt, Håll retention money i trust enligt Construction Contracts Act)
Kontrakt: Record what the contract actually lets you retain

Varför: The signature date decides which version of the rules applies, and that is not a detail. Contracts entered into or renewed from 5 October 2023 sit under the automatic trust and the reporting duty the amendment introduced, while older ones sit under the lighter 2017 regime. A company running one process for a book of contracts written under both is complying with whichever one it happened to build its spreadsheet around.

IndataSigned subcontractRetention terms as writtenResultatRetention rate and cap on recordRelease trigger and dates
2

Withhold it as a line, not as a smaller total

Ekonomi

When you schedule a subcontractor's payment, take the retention as a separate deduction line carrying the period it relates to and the cumulative amount now held, and let the net figure fall out of it. Stop deducting once the cumulative total reaches the contract cap rather than continuing at the percentage.

Skärmbild, steg 2: Withhold it as a line, not as a smaller total (Ekonomi, Håll retention money i trust enligt Construction Contracts Act)
Ekonomi: Withhold it as a line, not as a smaller total

Varför: A retention that exists only as the difference between two totals cannot be traced, and the whole regime rests on the money being identifiable as somebody else's. It is also the point at which the trust starts, so the day this line is created is the day the duties attach. A payer who cannot say which line created the trust is a payer who cannot show when the reporting clock began.

IndataSubcontractor payment claimRetention rate and cap on recordResultatRetention shown as its own lineNet amount scheduled for payment
3

Put the money where the Act says it has to sit

Innehållna medel

Post each withheld amount to the retention ledger against the subcontractor it belongs to, and record which bank account it is held in or which complying instrument covers it. The account has to be used only for retention money, and the ledger has to name the party, the amount, the contract and the date it was withheld.

Skärmbild, steg 3: Put the money where the Act says it has to sit (Innehållna medel, Håll retention money i trust enligt Construction Contracts Act)
Innehållna medel: Put the money where the Act says it has to sit

Varför: The 2023 amendment makes this money trust money automatically, which means it is outside the reach of your own creditors if the company fails, but only to the extent it can be identified. Money mixed into the working account and spent as float is money a liquidator will treat as yours, and the subcontractors it belonged to join the queue with everyone else. Using retention money as working capital is also an offence in itself.

IndataRetention shown as its own lineTrust account or complying instrumentResultatLedger of who holds whatBalance held per subcontractor
4

File the evidence that the money is where you say

Dokument

Keep the bank statement for the retention account for every period alongside the ledger it should agree with, and file the complying instrument itself where retention is covered by a guarantee or a policy rather than by cash. Keep the instrument's expiry date visible, because an expired guarantee leaves the money uncovered while the ledger still says it is fine.

Skärmbild, steg 4: File the evidence that the money is where you say (Dokument, Håll retention money i trust enligt Construction Contracts Act)
Dokument: File the evidence that the money is where you say

Varför: A ledger is an assertion and a bank statement is evidence, and the difference matters on the one day anyone asks. The regulator, an insolvency practitioner and a subcontractor's solicitor all ask the same question in the same order: what is held, where is it, and show me. Answering it takes minutes if the two documents were filed together each month and weeks if they were not.

IndataLedger of who holds whatBank statements and instrumentResultatCustody evidence filedAudit trail per period
5

Tell each party what you are holding from them

Korrespondens

Send each subcontractor a report of the retention money held from them: the amount, the date it was withheld, where it is held or what instrument covers it, and how the total moved since the last report. Do it as soon as practicable after retention is first withheld from them and then on a regular cycle of no more than three months, and keep the sent copy against the contract.

Skärmbild, steg 5: Tell each party what you are holding from them (Korrespondens, Håll retention money i trust enligt Construction Contracts Act)
Korrespondens: Tell each party what you are holding from them

Varför: This duty is the part of the regime most often missed, because nothing on site stops when it is skipped and no subcontractor chases a report they have never seen. It is still an obligation with an offence behind it, and the reports are also the cheapest defence there is: a party who has been told the same figure every quarter does not open the final account arguing about what was held.

IndataBalance held per subcontractorReporting periodResultatRetention report sentProof of what was sent and when
6

Tie each release to the defects period that triggers it

Garantier & felansvar

Hold each subcontractor's retention against the defects liability period it is released by: the first half at practical completion and the balance when the period ends. Where a release is being held back, record the defect it is held against, who owes the fix and by when, rather than letting the date pass in silence.

Varför: The release trigger is not a date somebody typed in, it is the end of a period that the defects record already tracks, so keeping the two apart is how a retention gets held for a year after the obligation it secured expired. A held release with a named defect against it is a commercial position. A held release with nothing against it is trust money that should have gone back, and a subcontractor can put that straight into adjudication.

IndataRelease trigger and datesDefects positionResultatRelease dates under watchWarning before each release
7

Reconcile the ledger against the account every period

Rapporter

Read the total the ledger says is held against the balance the account actually carries, across every project at once, and name the difference if there is one. Do it on the same day each period rather than when somebody asks.

Skärmbild, steg 7: Reconcile the ledger against the account every period (Rapporter, Håll retention money i trust enligt Construction Contracts Act)
Rapporter: Reconcile the ledger against the account every period

Varför: A shortfall between the ledger and the account is the one number in this whole case that cannot be argued about, and it grows quietly: a release paid from the working account, a deduction never banked, a project closed without its balance moving. Found in the month it happens it is a transfer. Found at liquidation it is the evidence in somebody else's case.

IndataLedger of who holds whatRetention account balanceResultatShortfall named if there is oneRetention position across projects
Moduler

Moduler i denna playbook

6 / 190 plattformsmoduler

The market this case is written for

Nya Zeeland

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mer inom Kommersiellt och kontrakt

Kommersiellt och kontrakt

Driv ett underentreprenadpaket

Tilldela ett entreprenadpaket till en underentreprenör, sätt det på ett underentreprenadkont…

3 steg11 minÖppna
Kommersiellt och kontrakt

Fakturaunderlag och avstämning

Värdera arbetet som utförts under perioden mot kontraktet, skapa fakturaunderlaget med under…

3 steg12 minÖppna