잠재하자 기간을 5년간 유효하게 유지하기

최종준공 확정일을 확정하고, 숨은 하자를 입증할 수 있게 하는 인계 기록을 보관하고, 양도된 워런티를 누군가 찾을 수 있는 곳에 보관하고, 그때까지 남아 있을 사람 앞에 5년 만료일을 제시해 둔다.

6단계11 분시행사 / 발주처소유주 / 운영사(FM)PM/CM 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 6단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Record the certified date and count five years from it

마감

Take the certified date of final completion off the certificate itself, store the certificate with the project rather than in a personal folder, and calculate the date five years on that clause 22.1 gives as the end of the latent defects liability period.

이유: Everything else in this case counts from that one date, and it is not the date of practical completion, the date of the handover meeting or the date the client moved in. Clause 22.3 also runs five years from termination where the agreement was terminated early, so a job that ended badly has a different start date and usually nobody who wrote it down.

입력Certificate of final completionSigned contract결과Certified date recordedFive year end date
2

Keep the record that makes a hidden defect provable

문서

Hold the as-built drawings, the specifications, the test and commissioning results, the material approvals and the consolidated health and safety file handed over under regulation 7(1)(e) of the Construction Regulations, 2014, indexed so somebody who was not on the project can find a detail by where it is in the building.

이유: A latent defect claim turns on showing what was specified, what was actually built and why the difference was not visible at final completion. That is a documents case, and the documents are the ones handed over at the end of the job. A pack that exists but cannot be searched is, four years later, the same as no pack.

입력As-built drawingsHealth and safety file결과Handover packSearchable index
3

Register every warranty against what it covers

보증 및 하자담보책임

Register the subcontractor guarantees and product warranties ceded to the employer at final completion under clauses 21.10 and 21.11, each against the element it covers, the party liable under it and the date it runs out.

이유: A waterproofing guarantee and the latent defects liability period are two separate routes to the same repair, and they expire on different days against different parties. An owner that registered neither ends up paying for a roof it had two claims for, and the subcontractor whose warranty it was has usually moved on by then.

입력Ceded warrantiesProduct guarantees결과Warranty registerParty liable
4

Put the building somewhere it will be looked at

자산 등록

Load the building and its plant onto the asset register with the warranty and the latent defects end date attached, and set an inspection before that date rather than only routine maintenance after it.

이유: Latent defects are latent, which means nobody is going to trip over them. The failures that are still recoverable in year four, movement in a slab, a failing membrane, a settled apron, are the ones somebody went looking for. An inspection booked deliberately against the end date is the only mechanism that turns a five year right into five years of use.

입력Handover packInstalled plant결과Asset registerInspection schedule
5

Log the fault as evidence, not only as a repair

서비스 및 유지보수

When a fault is reported, log it with the date, the location, photographs and any readings before anyone opens anything up, and classify it: wear, an operating fault, a defect covered by a live warranty, or a construction defect that was not discoverable at final completion.

이유: The most common way a good latent defect claim dies is that maintenance repaired the evidence in the first week. Once the failed detail has been cut out and replaced, what remains is an invoice and an opinion. Recording the condition before the repair costs an hour and is the whole difference between a claim and a complaint.

입력Reported faultPhotos and readings결과Logged jobCause and classification
6

Raise it in writing while the period is still open

마감일

Put the defect to the contractor in writing with the evidence attached and the contractual basis named, track the claim against the end of the latent defects liability period, and keep the deadline visible to whoever holds the building rather than only to the project team that has moved on.

이유: Clause 21.12 makes the certificate of final completion conclusive as to the sufficiency of the works other than for latent defects, so the latent defects liability period in clause 22.0 is the only door left open. A claim raised a week after the five years is worth exactly nothing however good the evidence behind it, and the person who would have known the date usually left the company in year two.

입력Classified defectFive year end date결과Notice to the contractorTracked claim
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6

The market this case is written for

남아프리카

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

인계 및 생애주기 카테고리의 더 보기

인계 및 생애주기

인수인계 및 종결

현장을 깔끔하게 마무리합니다. 펀치 리스트를 0으로 만들고, 모든 검사가 통과되었으며 미결 부적합이 없는지 확인한 뒤, 준공 기록을 취합하여 서명된 인수인계서를 발행…

5단계14 분열기
인계 및 생애주기

준공도서 및 운영/유지관리 인계

준공 기록을 정리하고, 품질 파일에 누락이 없음을 확인한 뒤, 운영자가 실제로 건물을 운영할 수 있는 운영/유지관리 패키지를 발행합니다.

3단계12 분열기
인계 및 생애주기

인수 점검 실시

발주자와 함께 완공된 공사를 점검하고, 인수 기준 대비 합격·불합격을 기록하며, 하자 목록을 0건으로 만들고 깔끔한 인수를 발행한다.