latent defects süresini beş yıl boyunca canlı tutun

Onaylanan nihai tamamlanma tarihini sabitleyin, gizli bir kusuru kanıtlanabilir kılan teslim kaydını saklayın, devredilen garantileri birinin bulabileceği bir yerde tutun ve beş yıllık bitiş tarihini o zaman hâlâ orada olacak kişinin önüne koyun.

6 adım11 dkGeliştirici / işverenMal sahibi / işletmeci (FM)Proje / inşaat yönetim bürosu

Nasıl çalışır, adım adım

Platform genelinde 6 adım - her birinde ne yapacağınız ve neden önemli olduğu.

1

Record the certified date and count five years from it

Kapatma

Take the certified date of final completion off the certificate itself, store the certificate with the project rather than in a personal folder, and calculate the date five years on that clause 22.1 gives as the end of the latent defects liability period.

Ekran görüntüsü, adım 1: Record the certified date and count five years from it (Kapatma, latent defects süresini beş yıl boyunca canlı tutun)
Kapatma: Record the certified date and count five years from it

Neden: Everything else in this case counts from that one date, and it is not the date of practical completion, the date of the handover meeting or the date the client moved in. Clause 22.3 also runs five years from termination where the agreement was terminated early, so a job that ended badly has a different start date and usually nobody who wrote it down.

GirdiCertificate of final completionSigned contractÇıktıCertified date recordedFive year end date
2

Keep the record that makes a hidden defect provable

Belgeler

Hold the as-built drawings, the specifications, the test and commissioning results, the material approvals and the consolidated health and safety file handed over under regulation 7(1)(e) of the Construction Regulations, 2014, indexed so somebody who was not on the project can find a detail by where it is in the building.

Ekran görüntüsü, adım 2: Keep the record that makes a hidden defect provable (Belgeler, latent defects süresini beş yıl boyunca canlı tutun)
Belgeler: Keep the record that makes a hidden defect provable

Neden: A latent defect claim turns on showing what was specified, what was actually built and why the difference was not visible at final completion. That is a documents case, and the documents are the ones handed over at the end of the job. A pack that exists but cannot be searched is, four years later, the same as no pack.

GirdiAs-built drawingsHealth and safety fileÇıktıHandover packSearchable index
3

Register every warranty against what it covers

Garantiler ve Kusur Sorumlulugu

Register the subcontractor guarantees and product warranties ceded to the employer at final completion under clauses 21.10 and 21.11, each against the element it covers, the party liable under it and the date it runs out.

Ekran görüntüsü, adım 3: Register every warranty against what it covers (Garantiler ve Kusur Sorumlulugu, latent defects süresini beş yıl boyunca canlı tutun)
Garantiler ve Kusur Sorumlulugu: Register every warranty against what it covers

Neden: A waterproofing guarantee and the latent defects liability period are two separate routes to the same repair, and they expire on different days against different parties. An owner that registered neither ends up paying for a roof it had two claims for, and the subcontractor whose warranty it was has usually moved on by then.

GirdiCeded warrantiesProduct guaranteesÇıktıWarranty registerParty liable
4

Put the building somewhere it will be looked at

Varlık Kaydı

Load the building and its plant onto the asset register with the warranty and the latent defects end date attached, and set an inspection before that date rather than only routine maintenance after it.

Neden: Latent defects are latent, which means nobody is going to trip over them. The failures that are still recoverable in year four, movement in a slab, a failing membrane, a settled apron, are the ones somebody went looking for. An inspection booked deliberately against the end date is the only mechanism that turns a five year right into five years of use.

GirdiHandover packInstalled plantÇıktıAsset registerInspection schedule
5

Log the fault as evidence, not only as a repair

Servis ve Bakım

When a fault is reported, log it with the date, the location, photographs and any readings before anyone opens anything up, and classify it: wear, an operating fault, a defect covered by a live warranty, or a construction defect that was not discoverable at final completion.

Ekran görüntüsü, adım 5: Log the fault as evidence, not only as a repair (Servis ve Bakım, latent defects süresini beş yıl boyunca canlı tutun)
Servis ve Bakım: Log the fault as evidence, not only as a repair

Neden: The most common way a good latent defect claim dies is that maintenance repaired the evidence in the first week. Once the failed detail has been cut out and replaced, what remains is an invoice and an opinion. Recording the condition before the repair costs an hour and is the whole difference between a claim and a complaint.

GirdiReported faultPhotos and readingsÇıktıLogged jobCause and classification
6

Raise it in writing while the period is still open

Son tarihler

Put the defect to the contractor in writing with the evidence attached and the contractual basis named, track the claim against the end of the latent defects liability period, and keep the deadline visible to whoever holds the building rather than only to the project team that has moved on.

Neden: Clause 21.12 makes the certificate of final completion conclusive as to the sufficiency of the works other than for latent defects, so the latent defects liability period in clause 22.0 is the only door left open. A claim raised a week after the five years is worth exactly nothing however good the evidence behind it, and the person who would have known the date usually left the company in year two.

GirdiClassified defectFive year end dateÇıktıNotice to the contractorTracked claim
Modüller

Bu senaryodaki modüller

6 / 190 platform modülü

The market this case is written for

Güney Afrika

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Teslim ve yaşam döngüsü kategorisinde daha fazlası

Teslim ve yaşam döngüsü

As-built ve işletme-bakım teslimi

Yapıldığı gibi (as-built) kaydını bir araya getirin, kalite dosyasında boşluk olmadığını kan…

3 adım12 dkAç
Teslim ve yaşam döngüsü

Devir teslim kabul denetimi yürüt

Tamamlanan işleri müşteriyle birlikte gezin, kabul kriterlerine göre neyin geçtiğini neyin g…

3 adım11 dkAç