ケース / 引き渡しとライフサイクル
引き渡しとライフサイクル

隠れた瑕疵の 5 年の期間を生かしたままにする

認証された最終完了日を確定し、隠れた瑕疵を立証できるようにする引渡しの記録を保存し、譲渡された各種の保証を誰でも見つけられる場所に保管し、5 年後の期限を、そのとき現場に残っている人の前に置く。

6ステップ11 分デベロッパー / 発注者オーナー / 運営者 (FM)プロジェクト / 施工管理会社

仕組みをステップごとに

プラットフォーム全体で6ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Record the certified date and count five years from it

完了

Take the certified date of final completion off the certificate itself, store the certificate with the project rather than in a personal folder, and calculate the date five years on that clause 22.1 gives as the end of the latent defects liability period.

理由: Everything else in this case counts from that one date, and it is not the date of practical completion, the date of the handover meeting or the date the client moved in. Clause 22.3 also runs five years from termination where the agreement was terminated early, so a job that ended badly has a different start date and usually nobody who wrote it down.

入力Certificate of final completionSigned contract出力Certified date recordedFive year end date
2

Keep the record that makes a hidden defect provable

文書

Hold the as-built drawings, the specifications, the test and commissioning results, the material approvals and the consolidated health and safety file handed over under regulation 7(1)(e) of the Construction Regulations, 2014, indexed so somebody who was not on the project can find a detail by where it is in the building.

理由: A latent defect claim turns on showing what was specified, what was actually built and why the difference was not visible at final completion. That is a documents case, and the documents are the ones handed over at the end of the job. A pack that exists but cannot be searched is, four years later, the same as no pack.

入力As-built drawingsHealth and safety file出力Handover packSearchable index
3

Register every warranty against what it covers

保証と瑕疵担保

Register the subcontractor guarantees and product warranties ceded to the employer at final completion under clauses 21.10 and 21.11, each against the element it covers, the party liable under it and the date it runs out.

理由: A waterproofing guarantee and the latent defects liability period are two separate routes to the same repair, and they expire on different days against different parties. An owner that registered neither ends up paying for a roof it had two claims for, and the subcontractor whose warranty it was has usually moved on by then.

入力Ceded warrantiesProduct guarantees出力Warranty registerParty liable
4

Put the building somewhere it will be looked at

資産台帳

Load the building and its plant onto the asset register with the warranty and the latent defects end date attached, and set an inspection before that date rather than only routine maintenance after it.

理由: Latent defects are latent, which means nobody is going to trip over them. The failures that are still recoverable in year four, movement in a slab, a failing membrane, a settled apron, are the ones somebody went looking for. An inspection booked deliberately against the end date is the only mechanism that turns a five year right into five years of use.

入力Handover packInstalled plant出力Asset registerInspection schedule
5

Log the fault as evidence, not only as a repair

サービス・保守

When a fault is reported, log it with the date, the location, photographs and any readings before anyone opens anything up, and classify it: wear, an operating fault, a defect covered by a live warranty, or a construction defect that was not discoverable at final completion.

理由: The most common way a good latent defect claim dies is that maintenance repaired the evidence in the first week. Once the failed detail has been cut out and replaced, what remains is an invoice and an opinion. Recording the condition before the repair costs an hour and is the whole difference between a claim and a complaint.

入力Reported faultPhotos and readings出力Logged jobCause and classification
6

Raise it in writing while the period is still open

期限

Put the defect to the contractor in writing with the evidence attached and the contractual basis named, track the claim against the end of the latent defects liability period, and keep the deadline visible to whoever holds the building rather than only to the project team that has moved on.

理由: Clause 21.12 makes the certificate of final completion conclusive as to the sufficiency of the works other than for latent defects, so the latent defects liability period in clause 22.0 is the only door left open. A claim raised a week after the five years is worth exactly nothing however good the evidence behind it, and the person who would have known the date usually left the company in year two.

入力Classified defectFive year end date出力Notice to the contractorTracked claim
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 6

The market this case is written for

南アフリカ

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

引き渡しとライフサイクルの他のケース

引き渡しとライフサイクル

引き渡しと竣工処理を行う

案件をきれいに終える。手直しリストをゼロにし、すべての検査が合格し未解決の不適合がないことを確認し、竣工図書一式をまとめ、署名済みの引き渡しを発行する。

5ステップ14 分開く
引き渡しとライフサイクル

竣工図と維持管理マニュアルの引渡し

竣工記録をまとめ、品質ファイルに漏れがないことを確認したうえで、運営者が実際に建物を管理・運用できる維持管理マニュアルを発行します。

3ステップ12 分開く
引き渡しとライフサイクル

引き渡し受入検査を実施する

施主と共に完成した工事を巡回し、受入基準に照らして合否を記録し、不具合リストをゼロまで解消し、清算された引き渡し受入を発行する。

3ステップ11 分開く